This statement of work outlines requirements for a concrete sidewalk replacement project at the Cosumnes River Preserve Visitor Center in California. The Bureau of Land Management seeks a contractor to demolish and dispose of approximately 600 square feet of existing 4-inch thick concrete sidewalk; excavate and prepare the subgrade; furnish and place 8 cubic yards of class 2 base rock and 4 inches of concrete for the new sidewalk section. Additional tasks include grading and drainage work, and providing erosion control measures, project signage and fencing. The contractor must meet specifications for concrete mix design, placement and curing, and perform compaction testing of the subgrade. The work must be completed within the period of performance following award of the contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L1223Q0068.pdf | ||
| B08_Attachment_No__3_Bid_Schedule.pdf | ||
| B08_Attachment_No__2_DBA.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
Bureau of Land Management
Vault Toilet Sidewalk Demolition and Replacement
Location: Cosumnes River Preserve
13501 Franklin Blvd
Galt, CA 95632
Sacramento County, California
Address: U.S. Department of the Interior
Bureau of Land Management
Mother Load Field Office
152 Hillsdale Cir
El Dorado Hills, CA 95762
October 2022
Contents
I. BACKGROUND ON THE GOVERNMENT’S REQUIREMENT:
II. GENERAL SCOPE OF WORK:
III. OVERALL OBJECTIVE(S):
IV. REQUIREMENTS AND TASKS:
Concrete Sidewalk Section Removal Task
Subgrade Preparation Task
Base Coarse Material Requirements
Concrete Placement Task
Concrete Requirements
Grading & Drainage Task
V. GOVERNMENT‐FURNISHED PROPERTY, MATERIALS, SERVICES:
VI. SECURITY AND ADMINISTRATIVE MATTERS:
VII. DEFINITIONS:
APPENDIX
I. BACKGROUND ON THE GOVERNMENT’S REQUIREMENT:
Consumnes River Preserve (CRP) is located within California’s Central Valley, north of the city of Stockton and south of the city of Sacramento. The Cosumnes River Preserve consists of over 50,000 acres of wildlife habitat and agricultural lands owned by seven land‐owning Partners. The Preserve is centered along the Cosumnes River, its floodplains and riparian habitat. This habitat is buffered by a variety of agricultural operations. The Preserve provides numerous social, economic, and recreational benefits to local communities and to people residing in the larger Sacramento and San Joaquin areas. The habitat supports wildlife, including birds that migrate throughout the Pacific Flyway.
The CRP Visitor Center features a publicly accessible double vault toilet, located within an interior island of the public parking lot. Sidewalk providing access to these facilities requires repairs to restore functionality, improve safety, and preserve the facility for future use. Work includes demolition, disposal, and replacement of deficient sidewalk sections to maintain the facilities in a safe working order and meet ADA accessibility requirements. This Statement of Work, along with supporting information, is intended to define the tasks and expectations for work to be accomplished under this contract.
II. GENERAL SCOPE OF WORK:
The contractor shall provide all materials, equipment, and personnel to accomplish the overall objectives according to the requirements and task descriptions contained within this Statement of Work, as well as associated drawings and specifications.
Location of Work:
All work is to be accomplished at the vault toilet sidewalk and its associated visitor parking lot. The Preserve is located 8 miles west of Galt, CA (38.265742, ‐121.440548). The visitor center parking lot and vault toilet sidewalk is accessible via I‐5 or CA 99 off the Twin Cities Rd exit, 1.75 miles after turning south on Franklin Blvd. Roads to the job site are paved, use of four‐wheel drive vehicles not required but recommended during wet conditions. See appendix A.
Period of Work Performance:
The period of work performance for this contract will be subject to timing of the award and weather. The wet season, typically October through March, may present a difficult and unsafe environment in which to work. As such, construction may not be advisable during the wet season, but may be allowed with proper precautions.
Contract work including the pre‐work conference meeting, site visits and planning meetings, mobilization, construction, and de‐mobilization must be completed within the Period of Performance.
III. OVERALL OBJECTIVE(S):
The objectives of this Contract are to:
Demolish and dispose of identified existing concrete sidewalk.
Excavate and prepare subgrade.
Furnish, place, and compact base coarse material.
Grade surrounding material for drainage.
IV. REQUIREMENTS AND TASKS:
Proposals will be evaluated, in part, on the demonstrated understanding of the following requirements.
A pre‐bid conference will be scheduled to allow potential contractors the opportunity to inspect the site conditions and to ask clarifying questions regarding the expected scope of work. Attendance at the pre‐bid conference is encouraged but not required to submit a proposal. All questions asked during the pre‐bid conference will be recorded with answers posted in an addendum to the original solicitation to inform all prospective contractors.
Contractors unable to attend the pre‐bid conference may inspect the site to become familiar with the existing conditions relating to the work to be performed and the difficulties and restrictions to the work to be performed.
The awarded contractor is responsible for controlling pedestrian traffic and dust control throughout all phases of the project. The Contractor shall take measures to not damage the parking lot or other existing structures, utilities, vegetation, private/government owned property.
Concrete Sidewalk Section Removal Task The sidewalk is intended to restore ADA access to the vault toilets, interpretive kiosk, and benches. Not all the existing concrete in the area will be removed. The concrete section slated for removal and replacement, is provided in the Appendix B Section of this Statement of Work. All concrete removal to occur within the north side of the visitor center parking lot.
The contractor shall remove and properly dispose of the existing Concrete sidewalk section, shown in appendix B. This section of concrete is estimated to be 4‐inches thick and cover approximately 600 square feet. Demolition shall be done in manner to avoid damage to the slabs that are to remain in place. Damage to existing slabs caused by contractor demolition shall be repaired and/or replaced at no additional cost to the government. All demolished concrete shall be removed from the government premises on the day that it is excavated. The contractor shall not store demolition spoil and other construction waste on‐site.
Subgrade Preparation Task The contractor shall clear areas to be affected by construction prior to completing subsequent tasks.
Contractor shall remove material under disposed sidewalk section to a minimum of 4 inches.
The awarded contractor is to employ an independent third‐part tester to provide the following testing results:
Pre‐compacted moisture content and density of native earth.
Post‐compacted moisture content and density of native earth, prior to placement of subgrade material.
The awarded contractor shall notify the COR five (5) days in advance of when compaction is expected to begin. The contractor is required to submit intended source of water to be used for compaction. Contractor is responsible for ensuring acceptable subgrade compaction. COR retains the right to reject the subgrade based on perceived moisture and compaction deficiencies.
Excess material from this task shall be stockpiled in designated area, see Appendix C.
Base Coarse Material Requirements Within twenty (20) days of award, contractor shall submit to the COR the proposed materials to be used for the base course.
The COR shall have seven (7) days to review and approve or note deficiencies for correction. Contractor shall place, compact, and maintain minimum depth of 4‐inches (Class II Base Rock) base coarse material.
Furnish and compact an estimated eight (8) cubic yards of hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Los Angeles abrasion, AASHTO T 96 50 percent max.
(2) Soundness of aggregate using sodium sulfate, 12 percent loss max.
AASHTO T 104 (5 cycles)
(3) Durability index (coarse), AASHTO T 210 35 min.
(4) Durability index (fine), AASHTO T 210 35 min.
(5) Fractured faces, ASTM D5821 50 percent min.
(6) Without organic matter and lumps or balls of clay.
(b) Surface coarse aggregate. In addition to general requirements, the surface course materials shall conform to the following:
(1) Gradation Table 703‐3
(2) Liquid limit, AASHTO T 89, Method A 35 max.
(3) Plasticity index, AASHTO T 90 10±3
Do not furnish material that contains asbestos fibers.
Table 703-3 Target Value Ranges for Surface Course Gradations
Sieve Size Percent by Mass Passing Designate Sieve
(AASHTO T 27 & AASHTO T 11)
1 inch (25 mm) 100(1)
½ inch (12.5 mm) 70 – 80 (5)
No. 4 (4.75 mm) 40 – 50 (7)
No. 10 (2.0 mm) 25 – 40 (6)
No. 40 (425 µm) 15 – 25 (5)
No. 200 (75 µm) 8.0 – 14.0 (4)
(1) Statistical procedures do not apply.
( ) The value in the parentheses is the allowable deviation () from the target values.
Concrete Placement Task Place 600 sq ft, 4‐inch‐thick minimum, ADA compliant, concrete sidewalk. Concrete pour area map can be found in
Appendix C. The elevation of the new concrete sidewalk section must match elevations of existing sidewalk, vault toilet concrete slab, and parking lot asphalt surfaces to a tolerance of 1/16th of an inch.
Coordination is required prior to concrete pour to ensure access to the worksite, or to close the visitor parking lot, if necessary. Contractor will be responsible for scheduling concrete pour with COR. Contractor to place and finish concrete in accordance with industry standards, and ensure enough craftsmen are on site to complete concrete installation.
No additional water shall be mixed on site for the purpose of placement or finishing ease. Admixtures, materials, and other chemicals not mentioned in this document, will require Contracting Officer’s approval prior to any use.
Contracting Officer may request submittal of manufacturer's product data with installation instructions for proprietary materials including reinforcement and forming accessories, admixtures, joint materials, hardeners, and curing materials. Admixtures shall be in accordance with ASTM C494, Standard Specification for Chemical Admixtures for
Concrete and ASTM C260, Standard Specification of Air‐Entraining Admixtures for Concrete. Dosages shall be in accordance with manufacturer’s recommendation, unless stated otherwise in this document.
Form materials must have sufficient stability to withstand pressure of placed concrete without bow or deflection.
Construct so that concrete members and structures are of correct size, shape, alignment, elevation, and position. Provide openings in formwork to accommodate work of other trades as required.
Accurately place and securely support items built into forms.
Clean and adjust forms or existing concrete edges, prior to concrete placement. Apply form release agents or wet forms, as required. Retighten forms during concrete placement if required to eliminate mortar leaks.
Do not begin placement until work of other trades affecting concrete is completed.
Concrete Requirements Within twenty (30) days of award, the contractor shall submit a description of the ready‐mix concrete specifications for
COR’s review, COR will have seven days to approve or ask for further information. Portland Cement Concrete (PCC) shall conform to the requirements for Cement Type I or Cement Type II in accordance with ASTM C 150.
(a) Ready Mix (ASTM C 94) conforming to the following:
(1) Coarse Aggregate, AASHTO T 27 & T 11 30% ± 3
(2) Fine Aggregate, AASHTO T 27 & T 11 70% ± 3
(3) Maximum Water Cement Ratio, ASTM C 94 .042
(4) Minimum 28‐Day Compressive Strength, ASTM C39 4000 PSI
(5) Air Content, ASTM C231 5.0% ± 1.0
(6) Slump, ASTM C 143 1.5 IN ± 1.5
(7) Fly Ash, % or GGBF % 15% or 25%
(8) PCC Temperature during placement 70°F ± 20
Contractor is responsible for providing independent third‐part testing results for two (2) random sample Concrete
Cylinder Compression tests, as well as a single Slump Test.
Additional Requirements:
Consolidate placed concrete using mechanical vibrating equipment with hand rodding and tamping.
Joints o Joints shall be made using the same method as existing sidewalk o Joints shall be ¼ inch wide by a depth no less than ¼ of the installed pad depth.
o Spaced 6‐10 feet apart o Cut in chamfered joints. All joints shall be cut or tooled in completely.
Protect concrete from physical damage or reduced strength due to weather extremes during mixing, placement, and curing.
o In cold weather comply with ACI 306 o In hot weather comply with ACI 305.
Concrete Cure. ASTM C 309, Type I, 1‐D or 2, Class A.
Refer to Codes and Standards: ACI 301 "Specifications for Structural Concrete Buildings"; ACI 318, "Building
Code Requirements for Reinforced Concrete"; comply with applicable provisions except as otherwise indicated.
Grading & Drainage Task The contractor shall wait 24 hours after concrete pour prior to starting subsequent tasks.
Excess material from subgrade preparation task, to be placed in planters adjacent to sidewalk. Borrow material to be spread out to allow for proper drainage and minimal erosion. If borrow material requires removal for proper drainage, BLM will provide on‐site location to place excess material.
Warranty Materials and equipment furnished under this Contract shall be covered by the most favorable commercial warranties given to customers for such materials or equipment. The rights or remedies provided herein are in addition to and do not limit rights afforded to the Government by other clauses of this Contract. With respect to warranties, expressed or implied, from manufacturers or suppliers for materials or equipment furnished under the Contract the Contractor shall:
1. Obtain warranties that would be given in normal commercial practices.
2. Require warranties to be executed, in writing, for the benefit of the Government.
3. Submit warranties to the Contracting Officer prior to the final inspection.
4. All concrete cracked within the warranty period shall be replaced at no additional cost to the government.
Standards
Moving of Equipment and Supplies: The moving of equipment and supplies to the job site and between job sites shall be the responsibility of the Contractor.
Replacement of Equipment: Contractor shall provide quality equipment capable of safely performing the work under the terms of the contract. If equipment is rejected because it does not meet minimum requirements, including but not limited to safety and operability, or if it becomes inoperative, the Contractor shall correct the deficiencies or furnish replacement equipment meeting contract requirements within 2 calendar days. All repairs are the total responsibility of the Contractor.
Equipment Standards: Contractor shall make equipment available for inspection and approval before use. The
Contractor must satisfy all applicable OSHA and DOT requirements or certifications for the operation of offered equipment. There will be no obligation to make payment for any equipment delivered that does not meet the
Technical Specifications.
Existing Facilities: All existing facilities damaged by the Contractor's operations shall be replaced or repaired by the Contractor at no cost to the Government.
Watershed Protection and Erosion Control: The awarded contractor shall submit an erosion control plan prior to receiving a Notice to Proceed. The erosion control plan will outline the contractor’s methods to prevent runoff from the site from reaching the local slough.
During all operations under this contract, the Contractor shall exercise reasonable measures to direct surface runoff water to stabilized waterways and to keep the drainage systems functioning effectively to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and equipment maintenance areas shall be stored and collected in a sanitary manner and disposed of in a State‐ approved sanitary landfill, per local, State, and Federal regulations.
Oil from crankcases or gear boxes, equipment waste or spilled or excess fuel shall be placed in containers and removed from the work site and disposed of as approved and required by local, State, and Federal regulations.
Contractor shall undertake every reasonable measure to minimize erosion and soil damage in connection with any operations under this contract. Contractor shall immediately discontinue any operations under this contract that due to weather or soil moisture conditions, such operations will cause excessive damage to the soil as determined by the Contracting Officer.
Equipment shall not be fueled, nor fluids changed within 100 feet of waters of the state. Any equipment operated adjacent to state waters shall be maintained in a good state of repair and have no damaged hoses, fittings, lines, tanks, etc. that may release pollutants into the water. Waste oil and fluids shall not be stored on site. If any such material is released into the waters, the responsible person must make an effort to contain the spill and notify the Contracting Officer within 24 hours. If unable to contain spill, immediately notify the Contracting Officer and call the National Response Center (NRC) at 1‐800‐424‐8802.
Emergency Spill Kit: Keep sufficient quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum produce spills. Use absorbent materials that are biodegradable, non‐ water absorbing and designed specifically for the types of spills associated with the Contractor’s operations.
Project site construction not completed during dry weather periods shall be winterized (along with Contractor’s approved onsite staging areas and storage sites) to minimize erosion and other damage to roadways, trails, watercourses, and sensitive habitat, as directed by the Contracting Officer.
Disposal of Debris: The Contractor shall transport and dispose of all debris and excess material off‐site at an approved facility, per local, State, and Federal regulations.
Any debris left onsite after the completion of the Contract shall become the property of the Contractor, and the Contractor shall be responsible for it. Dispose of materials in a legal manner and payment of fees required is the Contractor's responsibility. Sale of material onsite is not allowed unless authorized in writing by the Contracting Officer. Burning of removed materials is not permitted on the work site.
Project Boundary: Prior to implementation of Contract deliverables, a pre‐work meeting will be held at the project sites with the Contractor, Contracting Officer Representative (COR), and/or Project Inspector (PI). The intent is to ensure the Contractor understands where the project sites are located, project site specifics and specifications of the contract, and review the Contractor’s plan of operations. It is encouraged that all potential Contractors complete a thorough site visit before bidding on the contract.
Access: Access to the project area is identified on the map. If roads or any type of access become subject to damage, because of adverse weather conditions or other natural causes, the Contracting Officer or COR will relay that information to the Contractor by phone, email, or in person and the contract could be delayed.
Notification of Cessation or Restart of work: The Contractor shall notify the Contracting Officer prior to ceasing operations for three or more days, and before re‐starting operations after a shutdown of three or more days. This can be done by phone, E‐ mail, or in person.
Protection of Cultural Resources: If objects of cultural value on the project area are discovered, the
Contractor shall immediately suspend all operations in the vicinity of the cultural value and notify the
Authorized Office of the findings.
Weed Prevention: To reduce the potential for introduction of noxious weeds to the contract area, the
Contractor shall, prior to moving in motorized equipment to be used for mastication, clean all such equipment to remove all dirt, plant parts and materials that may carry noxious weed seeds. All equipment shall be inspected by the Contracting Officer prior to moving said equipment to the contract area.
Fire Prevention: Contractor shall take necessary measures for prevention and suppression of fire on the contract area and other adjacent Government lands used or traversed by the Contractor in connection with operations as are required by applicable laws and regulations. Contractor shall comply with all applicable local, State, and Federal fire prevention regulations and standards. At all times during closed fire season, each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
Fire extinguisher, dry chemical type of not less than 2‐1/2 pound capacity with a 4 BC or higher rating
Shovel, round point #0 lady or equal
Axe, 2 pounds or over, 26‐inch minimum length, or one Pulaski
Delivery
Within 15 business days of the completion of work, the Contractor shall provide site‐specific photographs clearly showing the before and after repair conditions to document compliance with applicable BMPs. The photographs should be clearly labeled with the project site name, date(s), and a description of what was being photographed. The photos shall be submitted to the BLM in a digital format and should be clearly organized and labeled.
Final Inspection and Acceptance
The Contracting Officer’s Representative or designated government representative will review all work. The Government’s final project inspections shall take place 1‐3 business days following the Contractor’s written notification to the CO and COR of the completion of work. At the conclusion of the work, the Contracting Officer, or their representative, will inspect all sites for conformance with the specifications and requirements. Any deficiencies noted during the inspection will be corrected by the Contractor prior to release of final payment, at no additional cost to the Government. Prior to final payment the Contractor shall properly disposed of all waste materials including excess soil, completed site resurfacing and grooming of staging and storage areas, and submitted project photographs and project reports.
Work Schedule The schedule shall be submitted at the pre‐work conference. When requested by the CO or COR, submit an updated work schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.
Health and Safety Plan Before construction commences, the Contractor shall submit a health and safety plan to the CO for approval.
The health and safety plan shall include the location of the nearest hospital and procedures to follow in case of an emergency. The Contractor is required to have a portable toilet on‐site for the duration of construction.
V. GOVERNMENT‐FURNISHED PROPERTY, MATERIALS, SERVICES:
General: The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, supervision, and other items and non‐personal services necessary to perform the work tasks defined in this Statement of Work.
The Contractor shall furnish fencing and signage (where applicable) for project sites, staging areas, and storage areas.
The Contractor will be responsible for the installation and removal of fencing and signage during project construction.
The Contractor shall furnish all materials to secure project sites, staging areas, and storage areas during use by the Contractor. These materials and operations shall be considered incidental to the work required and shall not be paid separately.
The Contractor’s proposed on‐site storage and staging areas are required to be approved of by the CO and COR before mobilization and construction begin.
Applicable Publications (Current Editions) Best Management Practices for the Protection of Water Quality (see Technical Exhibit 1)
Water Quality Construction Best Management Practices Manual o https://www.waterboards.ca.gov/water_issues/programs/cwa401/docs/certifications/snrse_h.pdf
Recommended Best Management Practices for Bridges (see Technical Exhibit 2) o https://www.fws.gov/daphne/section7/BMPs‐bridges.pdf
The Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects (FP‐14) o https://highways.dot.gov/federal‐lands/specs
VI. SECURITY AND ADMINISTRATIVE MATTERS:
Contingency Plan:
Sudden or unusual events could result in a negative impact to the delivery/work of these requirements. As an aid to properly plan for such events, the Contractor shall prepare and submit for approval a Contingency Plan for each Location of Work for these requirements. The Contractor will outline in detail the method(s) that the Contractor shall use in meeting Contract requirements in the following circumstances:
a natural disaster occurs which impacts upon the Contractor's ability to perform a labor strike occurs which impacts upon the Contractor's ability to perform.
a hazardous materials spill which impacts the Contractor’s ability to perform or which may affects public safety an incident which causes major damage which impacts the Contractor's ability to perform other unforeseen circumstances
In all cases, the Contractor will assume that government cannot provide supplemental forces, and continues to need the same or additional work under the Contract, which the Contractor must meet. This Contingency Plan shall be submitted as a part of the Contractor proposal.
Emergency Response:
Response to emergency service calls outside of the normal business hours shall not exceed four (4) hours regardless of the time during the day or night, weekends, or holidays. Response to emergency service during normal business hours shall not exceed two (2) hours. Response is defined as having all personnel and equipment required to correct an emergency at the site of the emergency or at a pre‐approved staging area, ready willing and able to perform the emergency work. The Contractor will provide a draft emergency response plan prior to Contract start date.
Emergency Services:
On occasion, services may be required to support an activation or exercise of contingency plans outside the normal business hours described above. The Contractor's responsibilities for emergency support will be in accordance with the contingency plan.
Hazardous Materials and Hazardous Response:
The Contractor will conform to all Reclamation, Federal, State, and local regulations in the use and disposal of hazardous materials and hazardous waste. The Contractor will provide the appropriate response to any emergency involving hazardous materials at any of the facilities covered by this Contract. The Contractor will provide proof/certification of its personnel qualified to work with hazardous materials and wastes to Reclamation. The Contractor will notify Reclamation immediately upon discovering a release of hazardous waste into the environment.
Public Contact:
Contractor personnel may have a close working relationship with adjacent landowners within their area of responsibility.
Contractor personnel will inform any trespassers along the right of way, of hazards and when necessary, request trespassers to leave fence restricted areas immediately.
When Contractor personnel are confronted with the news media, they may respond to general questions of the media with common sense approach and will refer all controversial questions to the O&M Manager. The Contractor Manager will keep the COR informed of all news media contacts.
When Contractor personnel are confronted with emergency personnel, policemen or firemen along the right of way, the Contractor personnel will notify the O&M Manager.
Government Observations:
Government personnel other than COR may from time to time observe, photograph, or otherwise record Contract operations. However, these personnel will not interfere with Contractor work performance.
Regular Work Hours:
The work period established for this contract is based upon all work being conducted during regular working hours between 7:00am and 4:00pm, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made for access to the work site.
Communications:
“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.
Federal Holidays:
The following Federal Legal Holidays are observed:
New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
Fire Danger Season:
If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.
Preservation of Historical and Archeological Data:
(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
(b) If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
(c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of work performance and/or changes in the work. If such delays and/or changes are ordered, the time of work performance and contract price shall be adjusted in accordance with the Changes clause.
(d) The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
VII. DEFINITIONS:
Standard Definitions:
Physical Condition
The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR. Physical condition may be determined by visual as well as diagnostic means.
Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.
Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.
Quality Assurance (QA) Surveillance of Contractor work to determine work requirements are met.
Work Requirements Summary (WRS) (see Technical Exhibit 6) The WRS identifies the key work performance indicators of the Contract that will be evaluated by the Government to assure Contract work performance standards are met by the Contractor.
Quality Control (QC) Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the work statement.
Approvals Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing. After approval of an item, submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.
Acronyms:
The following is a list of acronyms with their definition that are referenced in this project:
AASHTO American Association of State Highway and Transportation Officials
AWPA American Wood Protection Association
BLM Bureau of Land Management
CRP Cosumnes River Preserve
ACI American Concrete Institute
APPENDIX
APPENDIX A: Map of Project Location APPENDIX B: Concrete Sidewalk Section Removal & Replacement APPENDIX C: Subgrade Preparation Task Excess Material Relocation APPENDIX D: Site Photographs
APPENDIX A: MAP OF PROJECT LOCATION
APPENDIX B: CONCRETE SIDEWALK SECTION REMOVAL & REPLACEMENT
APPENDIX C: SUBGRADE PREPARATION TASK; EXCESS MATERIAL RELOCATION
APPENDIX C: SITE PHOTOGRAPHS
* Highlighted area subject to concrete removal, excavation, sub‐grade preparation and compaction, 4” Base coarse, and 4” Think concrete sidewalk.