- SKULL VALLEY SHADED BREAK PHASE 2 Federal contract opportunity
- Solicitation number
- 140L6423Q0008
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B04_Attachment_5_Skull_Valley_Technical_Evaluation_Criteria_0001.docx | DOCX document | |
| Sol_140L6423Q0008_Amd_0001.pdf | ||
| B08_Attachment_1_Skull_Valley_SOW_Update_0001.pdf | ||
| B03_Attachment_4_Wage_Determination2015-5469.pdf | ||
| Sol_140L6423Q0008.pdf | ||
| B08_Attachment_3__Contract_Clauses____Provisions.docx | DOCX document | |
| B04_Attachment_5_Skull_Valley_Technical_Evaluation_Criteria.docx | DOCX document | |
| B08_Attachment_2_Value_Bid_Schedule.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bureau of Land Management
Skull Valley (Phase 2)
2023 Fuel Break
Statement of Work
Purpose: The purpose of this order is to secure the services for manual (Chain saw) of approximately 50 acres of chaparral communities within the Skull Valley unit near the communities of Skull Valley and Wilhiot, AZ (see attached map).
Vegetation: The primary plant community found within the Planning Area is Interior Chaparral.
The vegetation is dominated by shrubs with small, thick, evergreen leaves and wide-spreading, deep root systems. Historic fire was an important component of the ecosystem (Pase and Brown
1982a). As such, the shrubs are well adapted to fire and reproduce readily from heat-scarified seed that is stored in soil for decades. Some species readily sprout from root crowns after fire.
The dense compacted leafy growths of the shrubs are naturally flammable, which leads to a high fire hazard. The eastern portions of the planning area are dominated by bunch grass species, including side oats grama, ring muhly, black grama, and squirrel tail. Shrubs include snakeweed, Apache plume, and barberry. The western and rolling hill portions of the planning area are dominated by Sonoran scrub oak and catclaw mimosa. Shrub cover in the western portion of the planning area is nearly contiguous in many of the upland areas, particularly along north and western facing slopes. Other shrubs include desert ceanothus, snakeweed, and fairy duster.
Location: Work under contract is in Yavapai County, State of Arizona, as shown on location map. Project is located east and southeast of Skull Valley, northeast of Kirkland, Arizona, and northwest of Wilhoit, Arizona.
Access to the Work:
Project site is accessible in dry conditions with two-wheel drive, high clearance vehicle. In wet conditions four-wheel drive high clearance vehicle may be needed. Absolutely NO motorized travel will be authorized with-in the project site.
Site Tour: Project site is located on Public Lands, prospective contractors may visit the site at their own discretion.
Description of Work: The work shall be manual (chainsaw) of approximately 50 acres on mostly steep terrain with a small number of rolling hills. Contractor will furnish all equipment to compete thinning project. Specifics area as follows:
• The BLM will mark the treatment area boundary with orange-ribbon flagging.
• The BLM will flag areas within the treatment boundary where treatment is not allowed with pink-ribbon and or blue-ribbon flagging. The contractor will not treat or enter these areas.
• No treatment will occur outside the marked treatment area.
• Standing dead will be treated.
• All brush is to be flush cut and piled:
• All tree species 6- inches (DBH) and below will be flush cut and piled:
• All tree species greater than 6-inches (DBH) and above will be limbed up to shoulder height.
• No piles will be within 50-feet of the forest Boundary.
• No piles will be constructed under the canopy of mature trees.
• Whenever possible piles will be constructed with smaller materials (brush) underneath larger branches.
• Piles not to exceed 8’x 8’ x 6’. Piles will be stacked on remaining stumps where possible.
• Cut trees will not have stumps left exceeding six inches (6”) above the ground.
• Off road vehicle travel is NOT permitted on this treatment
• The BLM may temporarily suspend work during periods of high fire danger.
• The BLM may temporarily suspend work to mitigate concerns regarding migratory birds.
• The BLM may temporarily suspend work to mitigate concerns regarding weather.
• The BLM may temporarily suspend work to mitigate concerns regarding safety.
• Complete work by 9/30/2023.
Surface Conditions: Motorized vehicles shall not be operated on access roads when soil becomes wet, and the vehicle causes a three inch or greater rut. If such conditions are encountered, the Contractor shall stop work and notify the Contracting Officer or Contracting
Officers Representative.
Terrain/Slope: The project area generally consists of steep slopes greater than 50% and may have loose footing.
Access to Work Site: Public or private access roads damaged by the contractor shall be restored, at the contractors’ expense, to the same condition they were in at the commencement of work.
Project Layout: The Government will flag or otherwise define areas to be treated by this
Contract, as identified above. The Contractor is required to protect all section corners, benchmarks, and other markers and stakes. In the event of destruction or removal by the contractor the incident will be noted negatively in the final review. The Contractor will not enter areas flagged in pink-ribbon flagging by the Government to preserve historical, archaeological, paleontological, wilderness, or other resources.
Cultural Considerations: Because cultural resources may be present in the area, project activities and any other action which causes disturbance of the earth’s surface shall be limited to those areas approved by the BLM. Deviations from routes flagged or shown on the drawings are not allowable without prior written approval of the Contracting Officer. The Contractor shall ensure that he/she, employees, or representatives do not collect or disturb historic or prehistoric artifacts in accordance with the Archaeological Resources Protection Act (43 CFR 7). Should the condition of the cultural resources in the area be altered during construction due to unauthorized activity by the Contractor or his employees, the Contractor shall be responsible for all costs of mitigating the cultural resources involved. If deterioration of the archaeological sites is found to be occurring during the implementation phase of the fuel break, work on the project shall be terminated until a data recovery plan is prepared and completed in accordance with the National
Historic Preservation Act (36 CFR 800). The Contractor shall immediately bring to the attention of the Contracting Officer all cultural resources including, but not limited to, historic and prehistoric sites or artifacts, buried artifacts, and buried features such as fire pits, burials, and house floors discovered as a result of drilling operations. The Contractor shall immediately suspend all activities in the immediate vicinity that might harm the object(s), notify the
Contracting Officer, and shall leave such discoveries intact until instructed to proceed by the
Contracting Officer.
Work Camps: The location of any work camps established by the contractor must be approved in advance by the Contracting Officer. Contractor shall maintain the camp in a sanitary, orderly manner, and upon vacating the camp, remove refuse and any other signs of occupancy. In the equipment maintenance area, special precaution shall be taken to contain spilled fuel, lubricants, and wash water.
Work Hours: Operations shall be permitted only during daylight hours unless additional working hours are authorized by the Contracting Officer.
CONTRACTOR PROVIDED EQUIPMENT
General: Contractor shall furnish at the worksite all equipment, labor, supplies, and materials required to complete the work within the specified performance time. The Contractor shall service and maintain such equipment as necessary to maintain satisfactory progress on the work.
Motor Vehicles: The Contractor shall finish motor vehicles for hauling equipment and personnel to the worksite.
Fire Prevention/Suppression: Contractor Shall:
Ensure all equipment diesel and/or gas engines are equipped with an approved spark arrester.
Spark arresters shall meet the requirements of the U.S. Forest Service Spark Arrester Guide, dated May 1985.
Have one shovel and a minimum of one 10-pound ABC fire extinguisher available.
Government furnished Property and Service: The BLM will:
• Supply one map or Geo-referenced PDF map depicting project area.
SEQUENCING AND SCHEDULING:
Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, the Contractor shall submit an updated schedule within three (3) calendar days.
Start Date: Tentative start of work will be within 120 days after award.
Performance Period: Complete work by 9/30/2023.
Pre-work Conference: A pre-work conference will be held prior to the start of work. The
Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the contract.
The Contractor, and the persons responsible for coordination of the work shall be present at the meeting.
The Contractor shall be prepared to summarize and explain procedures planned for the project.
Final Inspection: The meeting shall be held at the project site, or as determined by the
Contracting Officer Representative (COR). The Contractor shall require his or her superintendent (if designated) to be present during the inspections. The Contractor shall correct any deficiencies noted and the project will be re-inspected by the COR.
The Contractor shall notify the COR in writing, at least three (3) working days before the completion date so the Government can schedule a final inspection.
MOBILIZATION, MEASUREMENTS AND PAYMENTS
Mobilization: Includes all preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed, or cost incurred prior to beginning work on the various items on the project site. All costs associated with mobilization will be incorporated into the cost per acre to be mowed.
Measurement and Payment: Measurement for payment will be performed by GPS survey conducted by the Government and are based on horizontal distances.
Kirkland
Co Rd 10
Copper Basin Rd
?@89
No warranty is made by the Bureau of Land Management as to the accuracy, reliability, or completeness of these data for individual use or aggregate use with other data. Decisions in this
§̈¦15
§̈¦19
§̈¦17
§̈¦8
§̈¦40
§̈¦10
º 0 1.5 30.75 Miles
Date: 9/22/2022
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
PHOENIX DISTRICT
1:95,579
Skull Valley Thinning 23' Project Access
SymbolID Project Access Project Area Bureau of Land Management Private State US Forest Service
Arizona
Map Location
Skull Valley
No warranty is made by the Bureau of Land Management as to the accuracy, reliability, or completeness of these data for individual use or aggregate use with other data. Decisions in this
§̈¦15
§̈¦19
§̈¦17
§̈¦8
§̈¦40
§̈¦10
º 0 0.1 0.20.05 Miles
Date: 9/22/2022
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
PHOENIX DISTRICT
1:7,141
Skull Valley Thinning 23' Project Area
Project Area Bureau of Land Management US Forest Service
Arizona
Wilhoit
Skull Valley
Co Rd 10
Copper Basin Rd
?@89
No warranty is made by the Bureau of Land Management as to the accuracy, reliability, or completeness of these data for individual use or aggregate use with other data. Decisions in this
§̈¦15
§̈¦19
§̈¦17
§̈¦8
§̈¦40
§̈¦10
º 0 1 20.5 Miles
Date: 9/22/2022
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
PHOENIX DISTRICT
1:70,268
Skull Valley Thinning 23' Vicinity Project Area