This Statement of Work (SOW) details the replacement of an existing potable water well at the Nauset Light Beach bathhouse within Cape Cod National Seashore in Eastham, Massachusetts. The project requires a turnkey installation of a new water well with specific technical requirements, including drilling to a maximum depth of 95 feet, achieving a minimum yield of 29 gallons per minute, and meeting Massachusetts Department of Environmental Protection (MassDEP) water quality standards. The contractor must provide all labor, materials, equipment, and permits, and perform comprehensive tasks such as well drilling, water quality testing, installation of well components (including a 4" stainless steel well screen, submersible pump, PVC casing, and electrical connections), and complete site restoration.

Key technical specifications include using a 1-1/2 HP submersible pump operating on 230-volt, 1-phase power, 1" 200 psi NSF poly pipe for water lines, and 4" PVC schedule 40 well casing. The contractor must conduct a 4-hour yield test, submit detailed documentation including well completion reports and pumping test reports, and ensure the well is installed more than 100 feet from existing septic systems. Additional requirements involve obtaining all necessary permits, following Massachusetts and local building codes, maintaining site safety, minimizing environmental disturbance, and coordinating with Dig Safe for utility marking prior to ground disturbance.

View the file

Other files for this federal contract opportunity

Other files attached to CACO - REPLACEMENT NAUSET LIGHT BEACH WELL & PUMP, newest first.
File Type Posted
Sol_140P4325Q0019_Amd_0002.pdf PDF
B08_ATTACHMENT_002_NLB_Well_Location_Photo_0001.jpg JPG image
Sol_140P4325Q0019_Amd_0001.pdf PDF
Sol_140P4325Q0019.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

INSTALLATION AND REPAIR OF WATER WELL

Nauset Light Beach Bathhouse, Eastham, MA

CAPE COD NATIONAL SEASHORE

WELLFLEET, MA

General:

Provide a turnkey installation of a potable water well, including all required equipment, labor, materials, and permits, as described below.

At Nauset Light Beach bathhouse, the contractor shall replace the existing operating potable water well, which serves the Nauset Light Beach commercial facilities. The work includes drilling, placing, fitting, and switching over from the existing water line, as well as performing all required testing and documentation. The well shall be drilled to a depth sufficient to achieve a minimum yield of 29 gallons per minute (GPM). The contractor is required to cease drilling as soon as the yield of 29 GPM is achieved, and no further drilling shall be performed beyond that point, provided the water quality meets applicable potable water standards. If the water does not meet potable water standards (as defined by MassDEP and other applicable regulations), the contractor shall continue drilling, if necessary, to obtain water of sufficient quality or depth, up to the maximum depth of 95 feet

If a yield of 29 GPM is achieved before reaching the maximum depth of 95 feet, the contractor shall conduct water quality testing to ensure the water meets the required standards for potable water, including but not limited to levels of iron, manganese, sulfur, and total coliform. If the water does not meet these standards, the contractor shall continue drilling to obtain water of sufficient quality or depth, up to the maximum depth of 95 feet.

In the event that the required yield of 29 GPM is not met by 95 feet, the contractor shall immediately cease drilling and notify the Contracting Officer. The Contractor shall provide a written evaluation including:

1. Summary of subsurface conditions encountered

a. Yield testing results

b. Professional recommendations for achieving the required yield, which may include increasing well depth

The contractor shall obtain and pay for all required permits, including but not limited to those required by the Massachusetts Department of Environmental Protection (MassDEP) for the abandonment of the existing well and development of the new well. The contractor shall submit a stamped shop drawing, prepared by a Massachusetts-licensed professional engineer, showing the proposed well location in compliance with MassDEP siting requirements. (See Attachment A:

Proposed Well Location Plan.)

The Contractor shall minimize disturbance to the site unless otherwise directed by the Contracting Officer. All disturbed areas shall be restored to pre-project condition at no additional cost to the Government.

Quality Assurance, Safety, and Code Requirements:

All work shall be completed using industry-standard materials and methods, and in full compliance with applicable state and local codes, including Massachusetts General Laws, Town of Eastham Board of Health Regulations, OSHA, and NIOSH guidelines. The Contractor shall provide all labor, materials, tools, and equipment required to complete the work. Any necessary demolition, cutting, or removal of existing work to facilitate the installation of the new well shall be considered part of this contract.

All work shall conform to the following codes, as applicable and in effect at the time of construction:

a. Massachusetts State Building Code (780 CMR)

b. Massachusetts Plumbing Code (248 CMR)

c. Massachusetts Electrical Code (527 CMR, based on NFPA 70)

d. Massachusetts Environmental Code (310 CMR), including applicable private well regulations

d. Applicable local Town of Eastham Board of Health and building regulations

Measurements:

Estimated dimensions and quantities are provided as a guide only. The contractor is responsible for verifying all measurements and dimensions. The contractor shall take all measurements for quantities of materials and note existing conditions for the installation of new work.

Operational Testing:

Upon completion of the well installation, the contractor shall perform a well yield test in accordance with the Commonwealth of Massachusetts Private Well Guidelines (latest edition) and National Ground Water Association (NGWA) best practices.

The test shall demonstrate a sustained yield of at least 29 GPM over a continuous 4-hour period using a calibrated flow meter.

The following documentation shall be submitted within 10 days of the yield test:

1. A graph or table showing flow rate over time

2. Well Completion Report (Mass DEP form)

3. A Well Driller’s Pumping Test Report, signed and dated by the Massachusetts-licensed well driller, indicating:

a. Start and end time of test

b. Static and dynamic water levels

c. Pumping rate and drawdown data

d. Flow measurement method (e.g., calibrated flow meter or weir)

Site Examination:

It is the responsibility of the Contractor to examine the work site to confirm existing conditions and required quantities prior to submitting a proposal on this project.

Utilities and Services:

Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government. Notify Contracting Officer and utility companies of proposed locations and times for excavation. If damage occurs to an unknown utility, repair utility immediately and notify Contracting Officer.

Water Service: Water from the existing water system will be available only while the existing well is in service and once the new well is in service. The contractor shall provide its own water outside this window. Provide connections and extensions of services as required for construction operations without any additional permit costs.

Electric Power Service: Electric power from the existing system is normally available for use during construction without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs.

Arrange with the utility company and government for time when service can be interrupted, if necessary, to make connections for temporary services. If electric power is not available, contractor shall provide temporary power for project use at no additional cost to the contract.

Submittals:

Submit for approval all product data for materials and equipment to be installed for each system.

Submit proposed well location for approval by NPS.

Submit copies of well driller’s report and water quality analysis in both electronic and paper form.

Submit for record a copy of the permit application and stamped shop drawing.

Provide products that meet industry standards and all applicable codes. Deliver, handle and store materials in accordance with manufacturer’s instructions.

- Well Screen: 4” x 48” AISI Type 304 stainless steel, continuous slot type (or similar).

- Water line: 1” 200 psi NSF poly pipe.

- Well Pump: Submersible 1-1/2 HP Composite Pump, Drop Pipe, Pitless Adapter, Franklin 25 GPM series or approved equal. Motor shall operate on 230 volt, 1-phase power to meet all applicable codes and power requirements.

- Submersible wire: sized to meet requirements, minimum 12-2 ground, underground feeder wire 12-2 with ground.

- Well casing: 4” PVC schedule 40.

Installation:

Truck access to well site is possible. Well shall be sited greater than 100’ from existing septic system within limits of work area shown on attached drawing.

Contractor shall install all components with the required trenching and excavation. Install materials and system in accordance with manufacturer’s instructions and approved submittals.

Test for proper operation and flow, according to Commonwealth of Massachusetts Private Well Guidelines, latest edition. New well must achieve a minimum of 29 gallons per minute.

Install new well with well cap, pitless adapter, piping, valves, fittings, and all necessary electrical supply and connections. Install drain valve at outdoor water feed. Ensure well water is within state standards for iron, manganese, sulfur, and total coliform prior to completing installation activities at site.

Disconnect electrical connection in a manner that retains operability of well for adjacent houses.

Well cap must be securely affixed, 18” above grade.

Disinfect well prior to completion of work.

Remove and legally dispose of extraneous related water line and well materials.

The Contractor is responsible for contacting Dig Safe (#811) or other approved utility marking entity for pre-marking of all underground utility locations within project area prior to any ground disturbance. Prior to commencement of any on-site work, provide Contracting Officer with copies of proof of pre-marking from utility marking entity.

Contractor shall obtain all required permits for the performance of the work specified in Contract Documents at no additional cost to the contract. The Contractor is responsible for obtaining and displaying any necessary state or local permits at no additional cost to the contract. All work performed under this contract shall be done in accordance with applicable local, State, and Federal Codes and ordinances in effect at the time of this work. Follow Park Safety guidelines.

The Contractor shall clearly mark and delineate the limits of work activities, access routes, staging areas for approval prior to starting any on-site activities. Equipment shall not be allowed to operate outside the limits of work or to disturb existing vegetation.

The Contractor shall maintain project areas in neat, orderly, and safe condition at all times.

Contractor shall provide containers for collection and disposal of waste and trash resulting from work. Contractor shall keep dust and dirt pollution to a minimum. Contractor shall be responsible for storage of all materials and equipment; the Park COR and/or Project Inspector must approve contractor’s use of any space on the site in advance.

--END--