B08 - Attachment 0002 RIPD E4000-22-9-22 Timeline of Deliveries.pdf
PDF 107 KB Posted
- Attached to
- Mazak Bridge Mill Federal contract opportunity
- Solicitation number
- W9098S22Q0040
About this file
This document outlines a timeline for deliverables associated with federal contract number W9098S22Q0040 for a Mazak Bridge Mill. Key dates include a contract award date with installation documents due within 275 days, pre-shipment test results 60 days after that, equipment delivery 30 days after test results, utility connection by the government within 30 days of delivery, vendor start-up 56 days after connection, performance testing completion 7 days after start-up, training completion 28 days after testing, and final acceptance 5 days after training. The total timeframe outlined is 491 days from contract award to final acceptance. The solicitation is for the Department of the Army Materiel Command Contracting Command at Rock Island Arsenal.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08 - Attachment 0001 RIPD E4000-22-9-22 - Bridge Mill.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROCK IS LAND ARS ENAL DATE: 28 Dec 2021
PROJECT: RIPD E4000-22-9-22 TIMELINE OF DELIVERIES
CNC BRIDGE MILL
The following timeline is based upon the contract award date and the number of calendar days between events. Time allocations are maximums for each stage. It is acceptable to complete a stage in fewer days than shown on the timeline and move on to the next stage. Note: Early delivery of equipment is only allowable with RIA-JMTC prior approval with sufficient time to allow preparation of the planned equipment location.
The timeline for this project is as follows:
• Contract Award Contract Award
• Installation Documents Contract Award plus 275-days
• MSDS Sheets Delivered Contract Award plus 275-days
• Pre-Shipment Test Results Installation Documents + 60-days
• Equipment Delivery Pre-Shipment Test Results + 30-days
• RIA-JMTC Connection of Utilities Equipment Delivery + 30-days
• Vendor Start-Up Utility Connection + 56-days
• Vendor Performance Testing Start-Up Completion + 7-days
• Training Completed Performance Test Completion + 28-days
• Final Acceptance Training Completion + 5-days
Total Maximum Time from Award to Acceptance Contract Award + 491-days