B.08.02 W9123722Q0078.pdf
PDF 997 KB Posted
- Attached to
- SUT Roof Replacement Federal contract opportunity
- Solicitation number
- W91237-22-Q-0078
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B.08.03 W9123722Q0078 001_Amendment.pdf | ||
| A.03.09 Exhibit A Photos_SUT Roof.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUTTON LAKE
BRANDY L. ACORD
810 EDGAR GIVEN PARKWAY
SUTTON WV 26601
TEL: 304-765-2816 FAX:
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W9123722Q0078 29-Apr-2022 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
USACE, CONTRACTING DIVISION
AMY B. ORWIG, 502 8TH STREET
HUNTINGTON WV 25701
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
20-May-2022(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
304.399.5183AMY B ORWIG
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
W9123722Q0078
Section B - Supplies or Services and Prices
ADDITIONAL INFORMATION
ADDITIONAL INFORMATION
SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A
QUOTE. SEE CLAUSE 52.236-27 FOR ADDITIONAL INFORMATION.
PLEASE DIRECT ALL QUESTIONS TO AMY ORWIG AT (304) 399-5664 or amy.b.orwig@usace.army.mil. ANY INFORMATION RECEIVED AT THE SITE
VISIT WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE
BROUGHT TO THE ATTENTION OF MRS. ORWIG. THE SOLICITATION AND
RESULTING CONTRACT SHALL BE THE GOVERNING DOCUMENT IN ALL
CASES.
QUOTES CAN ONLY BE E-MAILED TO AMY ORWIG AT amy.b.orwig@usace.army.mil by the date referenced on page one of the SF18.
Per FAR 36.204 the estimated price range for this project is between $25,000 and $100,000.
NOTE: Award will be made to the lowest price offeror who meets the technical requirements of the solicitation and is deemed responsible by the contracting officer.
The intent is to award without discussions.
NOTE: this procurement is 100% Total Set-Aside for Small Business. For more information see FAR Clause 52.219-6 (Dev).
QUOTATION INSTRUCTIONS (Provide the following with your quote):
Company Name and Address:
Phone Number: Fax Number:
Email Address:
Business Size (select all that apply):
Large Business Small Business HUBZone Business 8A
Woman-Owned Service-Disabled Veteran-Owned
If subcontractor will be used for this work, please provide company name and credentials/qualifications:
IMPORTANT NOTICE: Effective September 26, 2018 and in accordance with FAR Clause 52.204- 7, “an Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.” Vendors are highly encouraged to check their registration status and plan accordingly prior to submitting an offer.
Please note, as of April 2018, GSA's System for Award Management (SAM) system is requiring new registrations and renewals of existing registrations to submit an original signed notarized letter identifying the authorized Entity Administrator. Vendors are encouraged to check their entity's status in SAM.gov and plan accordingly. If the prospective contractor is not registered in the SAM database, the Contracting Officer will following the procedures at FAR 4.1103. Contact the supporting Federal Service Desk at www.fsd.gov, or by telephone at 866- 606-8220 (toll free) or 334-206-7828 (internationally) Monday through Friday from 8 a.m. to 8 p.m. (EDT), for FREE assistance.
Contractor is registered with SAM:
YES NO (See FAR 52.204-7)
Provide business Unique Entity Identifier number:
(phone 800-333-0505 for Unique Entity Identifier number).
Provide business CAGE code:
Provide Tax Identification Number:
All work under this contract shall be in performance with all local, state, and federal laws, regulations, and codes.
Only the awarded contractor shall provide a copy of their insurance certificate required by State and Local Governments that has been acquired for the time period covered under this contract to the Contracting Officer within 10 business days after award. No further insurance requirements will be imposed by the Corps of Engineers for this contract.
Contractors are not required to submit an Accident Prevention Plan (APP) with their quote.
The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference. The contractor that receives this award will have 10 calendar days to provide an Accident Prevention Plan (APP). If this deadline is not met, the contractor will be given a cure notice stating that they will have 10 calendar days to submit an APP, otherwise the contract may be terminated for default.
Only the awarded contractor shall is required to submit back FAR Clause 52.204-24 with signed award. Please answer the two questions that are within the clause by placing an X in the box for does or does not OR will or will not, whichever applies to you as the contractor.
Please submit back within 10 business days after award.
PRICE BREAKOUT SCHEDULE
Line Item No. Description of Requirement Qty/Unit of Measure Extended Price
0001 Reimbursement of actual cost of payment bond for quotes in excess of $35,000.00
JOB $__________
0002 Mobilization & de-mobilization of equipment required in accordance with the attached Scope of Work.
0003 Roofing Labor at Sutton Lake in accordance with the attached Scope of Work.
0004 Materials and Supplies for Roofing at Sutton Lake in accordance with the attached Scope of Work.
Quote Total $__________
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job SUT FY22 DAM Roof Replacement
FFP
Contractor shall provide all necessary labor, equipment, and materials to SUT DAM Roof Replacement located at Sutton Lake, Sutton, WV in accordance with the attached Statement of Work FOB: Destination
PSC CD: Y1PZ
NET AMT
Section C - Descriptions and Specifications
SCOPE OF WORK
Specifications for Replacement of Dam Pylon Roof Sutton Lake Sutton, WV
Remove and replace rubber roofing system on the Pylon roof of Sutton Dam, approximately 1,400 square feet.
1. General:
Contractor shall furnish all equipment and labor to necessary to properly remove/dispose of current Ethylene Propylene Diene Monomer (EPDM) roof and underlayment. Contractor shall prepare concrete roof surface for replacement and install new EPDM roofing system with proper grade and drainage to existing center drain on roof, approximately 1,400 square feet. Asbestos removal was conducted during previous roof installation. Access to roof is via ladder and hatch in center of roof. U.S. Army Corps will supply crane for lifting/lowering supplies to top of roof from dam roadway surface. Photos of roof provided in Exhibit A.
2. Scope of Work and Information:
A. Contractor shall remove current EPDM rubber material as well as underlayment materials to the bare concrete.
Contractor shall dispose of materials properly and prepare site for installation.
B. Contractor shall install EPDM rubber roofing that meets ASTMD4637/D463M-10 Standard Specifications for single ply roof membrane. All materials shall be of high quality and free from defect at time of install and come with a 20 year manufacturers warranty.
C. Contractor shall install 90 mil EPDM type roof membrane according to manufacturer’s recommendations.
i. Concrete/drain shall be inspected and repaired if necessary prior to installation.
ii. Concrete must be completely dry at time of installation.
iii. Care shall be taken to ensure HVAC components on roof are not damaged during installation and are properly functioning when finished.
D. Contractor shall install new tapered, rigid insulation underlayment with a minimum of ½ inch thickness to provide proper base for new roof and correct drainage, following all manufacturer’s specifications.
i. Base insulation shall be secured to concrete surface by hot asphalt mopping method or similar compatible, manufacturer’s recommended method with roofing system.
ii. Contractor shall ensure underlayment system is compatible with EPDM membrane and adhesive method used.
iii. Contractor shall secure roof membrane to underlayment insulation system with proper adhesive or add additional substrate layer to ensure roof material will be secured properly with nothing touching the roof membrane that will cause leaks.
iv. Contractor shall install roof membrane that is properly attached with minimal wrinkles and proper drainage with no areas where water will stand or pool.
v. Contractor shall ensure roof membrane is one solid piece and no seams are used.
E. Contractor shall install termination bars on parapet walls, chimney and roof hatch.
i. Flashing shall be properly installed in areas where termination bars cannot be mounted.
ii. Splash guards shall be installed with the termination bars to deflect water onto roof membrane.
iii. Counter flashing shall be installed in areas where needed according to manufacturer’s recommendations.
iv. Contractor shall install flashing around vents, drain pipes etc. to ensure no leaks around protrusions through membrane.
3. Site Inspection:
A. A site inspection by the offeror prior to the submission of quotes is strongly recommended. Appointments for site inspections should be made with the Resource Manager, Joseph Swiney, 304-765-2816, Monday- Friday 0700-1500.
B. US Army Corps of Engineers Sutton Lake 810 Edgar Given Parkway Sutton, WV 26601 Phone: 304-765-2816 Fax: 304-767-7358
4. WORKING HOURS:
Normal working hours are Monday through Friday, 7:00 a.m. to 3:30 p.m. Work inside Government buildings or other secured areas shall be performed during the above referenced work hours. Unless other times and days are approved by the Contracting Officer. The normal work week will run from Monday through Friday, excluding holidays. The eleven (11) Federal Holidays observed are:
New Year's Day (January 1st) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Juneteenth (July 19th) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veteran's Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th) When one of the above designated holidays falls on a Sunday, the following Monday is observed as a legal holiday.
When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday Work that interferes with other ongoing functions at the project shall be scheduled around normal working hours.
Work shall be scheduled around the above listed Federal holidays unless approved in advance.
***Work shall begin within 10 calendar days of when Notice to Proceed is issued to the Contractor.****
5. Completion Date:
All work is to be completed within 30 calendar days of Notice to Proceed.
6. Payments:
Upon completion the contractor shall submit an invoice within 3-days to the Resource Manager for the total amount due. The Resource Manager contact information is as follows:
Joseph Swiney 810 Edgar Given Parkway Sutton, WV 26601 304-765-2816 Joseph.a.swiney@usace.army.mil
7. Contractor Safety Requirements:
Contractor Safety Requirements:
All work must be completed safely and in accordance with the USACE provided safety manual – EM 385-1-1. The following sections will be referenced:
Section 2 – Sanitation Section 5 – Personal Protective Equipment (PPE) Section 7 – Lighting Section 8 – Accident Prevention Signs, Tags, Labels, Signals, Piping System Identification, and Traffic Control Section 11 – Electrical Section – Control of Hazardous Energy Section 13 – Hand and Power Tools Section 14 – Material Handling, Storage and Disposal Section 18 – Motor Vehicles (for Public Roadway Use) Section 23 – Demolition, Renovation
Contractors shall comply with all current health and safety guidelines from the Centers for Disease Control and Prevention (CDC) and Occupational Safety and Health Administration (OSHA) in order to reduce the risk of spreading any community-based illnesses in the workplace
All PPE is required at all times while on work site. Open communication required at all times.
If the Contractor fails or refuses to promptly comply with safety and security requirements as specified herein, any project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage shall be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.
All employees involved in providing services shall read and review the applicable AHA for that job. All employees performing work under this contract shall wear personal protective equipment as specified in EM 385-1-1 including as a minimum steel-toed safety boots, hard hat, safety glasses, hearing protection, sleeved shirts, long pants, and gloves and other equipment common to trade as specified in EM 385-1-1.
Activity Hazard Analysis. The Contractor shall prepare and use an Activity Hazard Analysis (AHA) as one of many tools to insure safe performance of work. It is the Contractor’s responsibility to prepare the AHA. For re-occurring jobs, sample or previously prepared AHA’s may be provided by the Government for the Contractor’s information and to assist the Contractor in the development of site specific AHA’s pertinent to performing the work. The contractor is encouraged to revise or add to these AHA’s as necessary to address changing conditions.
The EM 385-1-1 can be access online via the following web address:
http://usace.army.mil/CESO/Documents/EM385-1-1FINAL.pdf Contractor Accident Prevention Plan (APP).
A. General. Contractor shall comply with all Federal, State and Local safety requirements including those specified by the Occupational Safety and Health Act (OSHA) in 29 CRF 1910 General Industry Standard, 1926 Construction Standard and the U.S. Army Corps of Engineers Safety & Health Requirements Manual EM 385-1-1 as currently revised. Where a conflict exists between safety standards/requirements the contractor shall comply with the more stringent requirement. If the Contractor fails or refuses to promptly comply with safety requirements as specified herein, any project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage shall be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.
B. Contractor Accident Prevention Plan (APP). The Contractor shall prepare a site-specific Accident Prevention Plan following the outline provided in EM 385-1-1, Appendix A as a minimum. The contractor shall address each element and sub-element in the outline in the order they appear in Appendix A. Any item from the outline that does not apply must be listed, in its assigned place and a brief explanation of the reason it is not required provided. The APP shall address any unusual or unique aspects of the project or activity. This plan must be accepted by the Contracting Officer prior to commencement of any work. Contractors are encouraged to contact the
USACE Safety & Occupational Health Office for questions or information regarding the development of contract Accident Prevention Plans. Office hours are Monday through Friday 8:00 AM to 3:00 PM at (304)399- 5032/5326/6961.
The web address for EM 385-1-1 is:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM _385-1-1.pdf
(1) The contractor shall have on site an employee designated as a Site Safety and Health Officer (SSHO) who has completed the OSHA 30-hour Construction Safety training or its equivalent as specified in EM 385-1-1, 01.A.17 and has at least five years safety management experience relative to the work to be performed. No work will be permitted unless the SSHO is present at the work site.
(2) Work crews of two or more must have two people holding current certification in First Aid and CPR from the American Red Cross, American Heart Association or a licensed physician.
Training must include a hands-on component that cannot be taken online and the contractor must maintain appropriate First Aid kit on site. Single individuals working alone must have current certification in First Aid as a minimum.
(3) All work that potentially exposes the worker to falls of six feet or more will require the contractor to submit a Site Specific Fall Protection & Prevention Plan in accordance with EM 385-1-1, Section 21.D.
(4) Cranes and hoisting equipment shall be operated only by qualified personnel (operators licensing, physical and drug testing in accordance with EM 385-1-1 Section 16.B). Note: CDL Medical Clearance is not acceptable. Please see attached medical clearance requirements.
(5) Effective November 8, 2010 all “Signalpersons” and “Riggers” shall be qualified. This is a mandatory requirement in accordance with 29 CFR 1926.1400 Regulations. Riggers must be a qualified person for the performance of specified hoisting activities such as during assembly/disassembly, in accordance with OSHA 1926.1404(r)(1) and 1926.1425(c)(3).
(6) Work orders involving potential exposure to Hazardous, Toxic or Radiological Waste shall require development of Site Specific Safety and Health Plan (SSHP) by qualified personnel as specified in EM 385-1-1 Sections 6 and 33.
C. Risk Management Process. The Contractor shall utilize risk management tools such as Activity Hazard Analysis (AHA), Job Hazard Analyses (JSAs) or similar tools to identify, assess, prioritize risks and develop controls to minimize, monitor and control the probability and/or impact of unfortunate events to an acceptable level.
Within each major phase, all activities, tasks or Definable Features of Work (DFOWs) shall be identified that will require an AHA/JSA. For each work activity, task or DFOW contractor shall prepare the initial AHA/JSA. A Risk Assessment Code (RAC) is assigned to each step, to the risk that remains after controls have been applied (residual risk) a final RAC (cannot be lower than the highest step RAC) shall be assigned. See EM 385-1-1 Section 01.A.14.b. for further guidance or contact the SOHO for assistance. The AHA/JSA shall be reviewed and accepted by the proper authority in order to proceed with the activity. All on-site employees shall review the accepted AHA/JSA prior to performing work and during weekly and “Tool Box” safety meetings as appropriate.
(1) AHA/JSA shall define the activities being performed and identify the work sequences, the specific anticipated hazards, site conditions, equipment, materials, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk. AHA/JSA should indicate compliance with EM 385-1-1 personal protective equipment requirements (safety-toed work boots, safety glasses, gloves, hard hats, etc.), work crews of two or more must have two people currently qualified in first aid and CPR and the appropriate first aid kit on site. Single individuals working alone must have current certification in First Aid only.
(2) The names of the Competent Person(s) and Qualified Person(s) required for a particular activity (e.g., excavation, scaffolding, fall protection, or other activities as specified by OSHA and this manual) shall be identified and included in the AHA, as well as proof of their competency/qualification.
D. Accident/Mishap Reporting. The Contractor shall report all recordable mishaps to the GDA within 24-hours in accordance with EM 385-1-1 Section 01.D. Accidents shall be investigated to determine causal factors and corrective actions shall be implemented. Accidents resulting in: days away injuries, days away illnesses, restricted/transfer injuries, property damage of $5,000.00 or more shall be investigated and reported to the GDA using the USACE Accident Investigation Report Form ENG 3394 within 24 hours of the occurrence.
(1) Immediate notification to the GDA is required for all serious accidents:
a. Fatal Injury/illness;
b. Permanent totally disabling injury/illness;
c. Permanent partial disabling injury/illness;
d. One (1) or more persons hospitalized as inpatients as a result of a single occurrence;
e. $500,000 or greater accidental property damage;
f. Three (3) or more individuals become ill or have a medical condition suspected to be related to a site condition, or a hazardous or toxic agent on the site;
g. USACE aircraft destroyed or missing;
The Contractor shall maintain an OSHA Log of Work Related Injuries and Illnesses, OSHA Form 300 and comply with all accident reporting and recordkeeping requirements specified in 29 CFR 1904.39.
(2) In addition to the above, any mishap occurring in any of the following high hazard areas shall be reported immediately to the GDA, investigated and corrective actions implemented.
a. Electrical (includes Arc Flash, electrical shock, etc.);
b. Uncontrolled Release of Hazardous Energy (includes electrical and non-electrical);
c. Load Handling Equipment (LHE) or Rigging;
d. Fall-from-Height (any level or other than same surface);
e. Underwater Diving
E. Activity Hazard Analysis (AHA): The Contractor shall prepare and use an AHA outlining specific job steps and the hazards associated with those steps and steps to eliminate or reduce those hazards. It is the Contractor's responsibility to prepare the AHA. The AHA shall be accepted by the GDA and/or on-site government representative prior to commencement of work. All on-site employees shall review the accepted AHA prior to performing work and during weekly and “Tool Box” safety meetings as appropriate. 1. All employees involved in providing services shall read and review the applicable AHA for that job. All employees performing work under this contract shall wear personal protective equipment as specified in EM 385-1-1 including as a minimum safety-toed boots, hard hat, safety glasses, hearing protection, sleeved shirts, long pants, and gloves and other equipment common to the trade as specified in EM 385-1-1. Contractor work crews of two or more employees must have at least two people currently certified in First Aid and CPR, if working alone must be certified in First Aid.
2. AHA shall define the activities being performed and identify the work sequences, the specific anticipated hazards, site conditions, equipment, materials, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk. AHA should indicate compliance with EM 385-1-1 personal protective equipment requirements (safety-toed work boots, safety glasses, gloves, hard hats, etc.), work crews of two or more must have two people currently qualified in first aid and CPR and the appropriate first aid kit on site. Single individuals working alone must have current certification in First Aid only.
3. The names of the Competent/Qualified Person(s) required for a particular activity (for example, electrician, excavations, scaffolding, fall protection, other activities as specified by OSHA and this manual) shall be identified and included in the AHA. Proof of their competency / qualification shall be submitted to the GDA for acceptance prior to the start of that work activity.
F. On-site Public Safety: The Contractor shall ensure that reasonable precautions are taken to protect the public at all times where work is being performed. The Contractor shall immediately report to the Resource Manager any potential hazards found by his employees on the project. The Contractor Safety Plan shall include procedures to be taken to provide for public safety. Additionally, the Contractor shall not allow any persons, except employees, into work areas that are not otherwise open to the public; nor shall the Contractor transport in Contractor work vehicles any persons, except employees, during times the Contractor is on the project performing work.
G. Service Equipment: The Contractor shall furnish the equipment appropriate to perform the work required for fulfillment of the work specified in this contract. All equipment used in the performance of work under this contract will be inspected and approved by the Government prior to use.
H. Damage Reports: All instances where Government materials, supplies, property, and/or equipment are damaged shall be reported immediately to the Resource Manager at Sutton Lake. When the damage is caused by contract employees, a written report of the incident and extent of such damage shall be submitted to the Resource Manager, within 1 working day of occurrence. For property damage accidents of $2,000 or more, the Contractor will complete and submit to the Resource Manager a copy of ENG 3394.
I. Accident Reporting: The Contractor shall maintain an accurate record of, and report to the Resource Manager, on ENG Form 3394, all accidents within 24 hours of the occurrence. All serious accidents (those resulting in death or injury requiring medical attention) shall be reported immediately. The Contractor shall maintain an OSHA Log of Work Related Injuries and Illnesses, OSHA Form 300.
J. Contract Employees’ Conduct and Competency: All contract employees shall conduct themselves in a proper manner at all times. Since the majority of work shall be performed in the presence of the general public, the conduct of all employees is critical and will be closely monitored. Use of controlled substances or consumption of beer or alcoholic beverages by contract employees is strictly prohibited. The contractor may be required to immediately remove from the work site any employee of the Contractor who is incompetent or who endangers persons or property or whose physical or mental condition is such that it would impair the employee's ability to safely and satisfactorily perform the work.
H. Deficiencies If the Contractor fails to perform, or if performance is any area is judged unsatisfactory, the Government will take corrective action. If any of the work does not conform to contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements, at no cost to the Government.
I. Pre-Construction Conference The Contractor representative shall attend a pre-construction work conference, prior to the initiation of work under this contract. The Contractor's Safety (APP) Plan must be approved prior to this meeting.
J. Contractor Submittals:
The successful offeror shall provide as a minimum the following documentation:
A. Accident Prevention Plan (APP) – In accordance with EM 385-1-1 Appendix A. (See Attachment 1) B. Activity Hazard Analysis – In accordance with EM 385-1-1 Section 01.A.12.
C. Invoice as stated on the contract award upon completion of work.
K. Supplies to be furnished by the Contractor:
The Contractor shall provide Personal Protection Equipment to include steel-toed safety boots, hard hat, safety glasses, hearing protection, sleeved shirts, long pants, gloves.
8. Contractor Security Requirements:
SECURITY REQUIREMENTS
All Contractors and subcontractor employee(s) working on this contract who require access in and/or around any Huntington District facilities shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12). The Huntington District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Huntington District Security Management Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.
FOR ALL CONTRACTS 1-YEAR AND SUBSEQUENT OPTION YEARS:
Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities.
The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working,
(2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) Security Information sheet on each employee working on site must be submitted directly to the Huntington District Security Office.
The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.
Contractors shall have background checks completed for their employees annually in the case of Contracts with option periods. For instance, if the employee was cleared in May of 2018, they shall be cleared again in May of 2019. It is the Contractor’s responsibility to ensure that each employee’s security is up to date. Failure to comply may lead to possible removal from the project/jobsite.
The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they must process the employee through the Huntington District USACE Security Management Office for background purposes.
FOR CONTRACTORS REQUIRING DOD COMMON ACCESS CARDS (CAC)
The documents listed below are required:
SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual must take prints, ORI block on the FD 258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management Office).
Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.
Following submission of paperwork, the Huntington District Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Huntington District Security Management Office will make recommendations to the PCO or their Designated Representative. The Huntington District Security Management Office cannot give approval due to unfavorable report(s). The Huntington District Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.
FOREIGN NATIONALS
The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.
In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Huntington District Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Huntington District Security Management Office by phone, letter, or email at the following numbers/addresses:
CELRH-SM
502 Eighth Street Huntington, WV 25701
Stephen R. Curry, phone (304) 399-5695; email stephen.r.curry@usace.army.mil Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil Scott E. Grandon, phone (304) 399-5661; email scott.e.grandon@usace.army.mil
AT/OPSEC Requirements. The following shall be accomplished by the contractor before any work will be ordered:
For contractors who do not require CAC, but require access to a DoD facility or installation. Proposed language: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
ATTACHMENT 1
APPENDIX A
MINIMUM BASIC OUTLINE FOR ACCIDENT PREVENTION PLANS
An Accident Prevention Plan (APP) is a safety and health policy and program document. The following areas are typically addressed in an APP, but an APP shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written.
The APP shall interface with the employer’s overall safety and health program, and a copy shall be available on the work site. Any portions of the overall safety and health program that are referenced in the APP shall be included as appropriate. ANSI/ASSE A10.38 should be referenced for Programmatic Issues.
> For LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS, for example, mowing (only), park attendant, rest room cleaning, the Contracting Officer and SOHO may allow an ABBREVIATED APP (customized APP requirements and waive the more stringent elements of this section). > See 01.A.11, and Appendix A, paragraph 11.
1. SIGNATURE SHEET. Title, signature, and phone number of the following:
a. Plan preparer (Qualified Person, Competent Person, such as corporate safety staff person, QC);
b. Plan must be approved, by company/corporate officers authorized to obligate the company;
c. Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project QC). Provide concurrence of other applicable corporate and project personnel (Contractor).
2. BACKGROUND INFORMATION. List the following:
a. Contractor;
b. Contract number;
c. Project name; d. Brief project description, description of work to be performed, and location; phases of work anticipated (these will require an AHA).
3. STATEMENT OF SAFETY AND HEALTH POLICY. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees.
The Contractor’s written safety program goals, objectives, and accident experience goals for this contract should be provided.
4. RESPONSIBILITIES AND LINES OF AUTHORITIES. Provide the following:
a. A statement of the employer’s ultimate responsibility for the implementation of his SOH program;
b. Identification and accountability of personnel responsible for safety at both corporate and project level. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes. Qualifications shall include the OSHA 30-hour course or equivalent course areas as listed here:
(1) OSH Act/General Duty Clause;
(2) 29 CFR 1904, Recordkeeping;
(3) Subpart C: General Safety and Health Provisions, Competent Person;
(4) Subpart D: Occupational Health and Environmental Controls, Citations and Safety Programs;
(5) Subpart E: PPE, types and requirements for use;
(6) Subpart F: understanding fire protection in the workplace;
(7) Subpart K: Electrical;
(8) Subpart M: Fall Protection;
(9) Rigging, welding and cutting, scaffolding, excavations, concrete and masonry, demolition; health hazards in construction, materials handling, storage and disposal, hand and power tools, motor vehicles, mechanized equipment, marine operations, steel erection, stairways and ladders, confined spaces or any others that are applicable to the work being performed.
c. The names of Competent and/or Qualified Person(s) and proof of competency/qualification to meet specific OSHA Competent/Qualified Person(s) requirements must be attached. The District SOHO will review the qualifications for acceptance;
d. Requirements that no work shall be performed unless a designated competent person is present on the job site;
e. Requirements for pre-task safety and health analysis;
f. Lines of authority; g. Policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;
h. Provide written company procedures for holding managers and supervisors accountable for safety.
4. SUBCONTRACTORS AND SUPPLIERS. If applicable, provide procedures for coordinating SOH activities with other employers on the job site:
a. Identification of subcontractors and suppliers (if known);
b. Safety responsibilities of subcontractors and suppliers.
5. TRAINING. a. Requirements for new hire SOH orientation training at the time of initial hire of each new employee.
b. Requirements for mandatory training and certifications that are applicable to this project (e.g., explosive actuated tools, confined space entry, crane operator, diver, vehicle operator, HAZWOPER training and certification, PPE) and any requirements for periodic retraining/recertification.
c. Procedures for periodic safety and health training for supervisors and employees.
d. Requirements for emergency response training. > See paragraph 9.b. below for a list of requirements that may require emergency response training.
6. SAFETY AND HEALTH INSPECTIONS.
a. Specific assignment of responsibilities for a minimum daily job site safety and health inspection during periods of work activity: Who will conduct (e.g., SSHO, PM, safety professional, QC, supervisors, employees – depends on level of technical proficiency needed to perform said inspections), proof of inspector’s training/qualifications, when inspections will be conducted, procedures for documentation, deficiency tracking system, and follow-up procedures.
b. Any external inspections/certifications that may be required (e.g., USCG).
7. ACCIDENT REPORTING. The Contractor shall identify person(s) responsible to provide the following:
a. Exposure data (man-hours worked); b. Accident investigations, reports, and logs: Report all accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative (CO/COR). The contractor shall thoroughly investigate the accident and submit the findings of the investigation along with appropriate corrective actions to the CO/COR in the prescribed format as soon as possible but no later than five (5) working days following the accident. Implement corrective actions as soon as reasonably possible;
b. The following require immediate accident notification:
(1) A fatal injury;
(2) A permanent total disability;
(3) A permanent partial disability;
(4) The hospitalization of three or more people resulting from a single occurrence;
(5) Property damage of $1,000 or more.
8. PLANS (PROGRAMS, PROCEDURES) REQUIRED BY THE SAFETY MANUAL.
Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational risks and compliance plans. Using the EM 385-1-1 as a guide, plans may include but not be limited to:
a. Layout plans (04.A.01);
b. Emergency response plans:
(1) Procedures and tests (01.E.01);
(2) Spill plans (01.E.01, 06.A.02);
(3) Firefighting plan (01.E.01, Section 19);
(4) Posting of emergency telephone numbers (01.E.05);
(5) Man overboard/abandon ship (Section19.A.04);
(6) Medical Support. Outline on-site medical support and off-site medical arrangements including rescue and medical duties for those employees who are to perform them, and the name(s) of on-site Contractor personnel trained in first aid and CPR. A minimum of two employees shall be certified in CPR and first-aid per shift/site (Section 03.A.02; 03.D);
c. Plan for prevention of alcohol and drug abuse (01.C.02);
d Site sanitation plan (Section 02); e Access and haul road plan (4.B);
f. Respiratory protection plan (05.G);
g. Health hazard control program (06.A);
h. Hazard communication program (06.B.01);
i. Process Safety Management Plan (06.B.04);
j. Lead abatement plan (06.B.05 & specifications);
k. Asbestos abatement plan (06.B.05 & specifications);
l. Radiation Safety Program (06.E.03.a);
m. Abrasive blasting (06.H.01);
n. Heat/Cold Stress Monitoring Plan (06.I.02)
o. Crystalline Silica Monitoring Plan (Assessment) (06.M) ;
p. Night operations lighting plan (07.A.08);
q. Fire Prevention Plan (09.A);
r. Wild Land Fire Management Plan (09.K);
s. Hazardous energy control plan (12.A.01);
t. Critical lift Plan (16.H);
u. Contingency plan for severe weather (19.A.03);
v. Float Plan (19.F.04);
w. Site-Specific Fall Protection & Prevention Plan (21.C);
x. Demolition plan (to include engineering survey) (23.A.01);
y. Excavation/trenching plan (25.A.01);
z. Emergency rescue (tunneling) (26.A.);
aa. Underground construction fire prevention and protection plan (26.D.01); bb. Compressed air plan (26.I.01);
cc. Formwork and shoring erection and removal plans (27.C);
dd. PreCast Concrete Plan (27.D);
ee. Lift slab plans (27.E);
ff. Steel erection plan (27.F.01);
gg. Site Safety and Health Plan for HTRW work (28.B);
hh. Blasting Safety Plan (29.A.01);
ii. Diving plan (30.A.13);
jj. Confined space Program (34.A).
9. RISK MANAGEMENT PROCESSES. Detailed project-specific hazards and controls shall be provided by an Activity Hazard Analysis (0I.A.13) for each major phase/activity of work.
10. ABBREVIATED APP for LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS. If service, supply and R&D contracts with limited scopes are awarded, the contractor may submit an abbreviated Accident Prevention Plan. This APP shall address the following areas at a minimum. If other areas of the EM 385-1-1 are pertinent to the contract, the contractor must assure these areas are addressed as well.
a. Title, signature, and phone number of the plan preparer.
b. Background Information to include: Contractor; Contract number; Project name; Brief project description, description of work to be performed, and location (map); The project description shall provide a means to evaluate the work being done (see AHA requirements in 01.A.13) and associated hazards involved. Contractor’s APP shall address the identified hazards involved and the control measures to be taken.
c. Statement of Safety and Health Policy detailing their commitment to providing a safe and healthful workplace for all employees.
d. Responsibilities and Lines of Authorities – to include a statement of the employer’s ultimate responsibility for the implementation of his SOH program; Identification and accountability of personnel responsible for safety at all levels to include designated site safety and health officer (SSHO) and associated qualifications. The District SOHO will review the qualifications for acceptance. e. Training - new hire SOH orientation training at the time of initial hire of each new employee and any periodic retraining/recertification requirements.
f. Procedures for job site inspections - assignment of responsibilities and frequency.
g. Procedures for reporting man-hours worked and reporting and investigating any accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative (CO/COR). An accident that results in a fatal injury, permanent partial or permanent total disability shall be immediately reported to the Contracting Officer.
h. Emergency Planning. Employees working alone shall be provided an effective means of emergency communication. This may be cellular phone, two-way radio or other acceptable means. The selected means of communication must be readily available and must be in working condition.
i. Drinking Water provisions, toilet and washing facilities.
j. First Aid and CPR training (at least two employees on each shift shall be qualified/certified to administer first aid and CPR) and provision of first aid kit (types/size).
k. Personal Protective Equipment.
(1) Work Clothing - Minimum Requirements. Employees shall wear clothing suitable for the weather however minimum requirements for work shall be short-sleeve shirt, long pants (excessively long or baggy pants are prohibited) and leather work shoes. If analysis determines that safety-toed (or other protective) footwear is necessary (i.e., mowing, weed eating, chain saw use, etc), they shall be worn
(2) Eye and Face Protection. Eye and face protection shall be worn as determined by an analysis of the operations being performed HOWEVER, all involved in chain saw use, chipping, stump grinding, pruning operations, grass mowing, weed eating and blowing operations shall be provided safety eyewear (Z87.1) as a minimum.
(3) Hearing Protection. Hearing protection must be worn by all those exposed to high noise activities (to include grass mowing and trimming, chainsaw operations, tree chipping, stump grinding and pruning).
(4) Head Protection. Hard hats shall comply with ANSI Z89.1 and shall be worn by all workers when a head hazard exists. At a minimum, hard hats shall be worn when performing activities identified in (2) above.
(5) High Visibility Apparel shall comply with ANSI/ISEA 107, Class 2 requirements at a minimum and shall be worn by all workers exposed to vehicular or equipment traffic.
(6) Protective Leg chaps shall be worn by all chainsaw operators.
(7) Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts, abrasions, punctures, burns and chemical irritants.
(8) If work is being performed around water and drowning is a hazard, PFDs must be provided and worn as appropriate.
l. Machine Guards and safety devices. Lawn maintenance equipment must have…