ATTACHMENT I Statement of Work.pdf
PDF 630 KB Posted
- Attached to
- Bent Boiler Tubes Federal contract opportunity
- Solicitation number
- N5005424Q0065
About this file
This statement of work and related solicitation document outline requirements for bent boiler tubes to be supplied to the Naval Sea Systems Command. The statement of work specifies the delivery of 54 rearwall tubes, 9 screen wall tubes, and 324 generating tubes fabricated in accordance with technical drawings and MIL specifications. Tubes must have ovality not exceeding 10% and wall thinning not exceeding 10%. Delivery is required by January 24, 2025 to Norfolk, Virginia. The combined synopsis/solicitation was issued by the Mid-Atlantic Regional Maintenance Center to procure these bent boiler tubes from qualified sources. Responses are requested in accordance with simplified acquisition procedures for commercial items outlined in FAR 13. Interested parties should reference solicitation N5005424Q0065 posted on SAM.gov and PIEE.gov.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Combined Synopsis Solicitation.docx | DOCX document | |
| ATTACHMENT III Instructions for the DD2345.pdf | ||
| ATTACHMENT V FAR 52.212-3 Offeror Representations and Certifications - Commercial Products and Commerc.rtf | RTF text file | |
| Combined Synopsis Solicitation.docx | DOCX document | |
| ATTACHMENT IV FAR 52.212-5 Contract Terms and Conditions Required To Implement Statutes or Executive Orders-Commercial.pdf | ||
| ATTACHMENT II DD2345 Form for Requesting Technical Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
Statement of Work
USS WASP (LHD-1)
Number One Main Propulsion Boiler Tubes
1.0. INTRODUCTION.
1.1. Background and Objective. This Statement of Work (SOW) defines the requirements for the supply and delivery of the parts listed in 2.1 be delivered to DLA Distribution Norfolk RMC PROJ, Bunker Hill Towaway Bldg. X136, and Norfolk, VA 23511.
2.0. GENERAL REQUIREMENTS
2.1. The Contractor shall supply and deliver the material listed in 2.1.1 through 2.1.3 complying with the following specifications:
SOW
Para no.
QTY NAME OF PART TECH MANUAL
Part Number
NSN
2.1.1 54 EA Bent Rearwall Tubes with plain ends, 2 Inch OD by 0.134 Inch MW, MIL-T-16286 Class A.
Ovality not to exceed 10%. Wall thinning not to exceed 10%.
S9221-A3-MMO-A20
REV 10. Plan A-14-1
4710-00-190-4931
2.1.2 9 EA Bent Screen Wall Tube with square cut ends, 2 Inch OD by
0.134 Inch MW, MIL-T-16286
Class A. Ovality not to exceed 10%. Wall thinning not to exceed 10%.
S9221-A3-MMO-A20
REV 10. Figure Plan A-
12-1
4710-00-192-7271
2.1.3 324 EA Bent Generating Tubes with square cut ends, One Inch OD by
0.085 Inch MW, MIL-T-16286
Class A. Ovality not to exceed 10%. Wall thinning not to exceed 10%.
S9221-A3-MMO-A20
REV 10. Figure Plan A-
12-1
4710-00-262-7849
2.2 All material to be in accordance with Reference 2.6 of work items 221-80-001 and 221-80-
002. Ovality not to exceed 10%. Wall thinning on bent tubes are not exceed 10%. Package with wood and banding. All ends to be capped with plastic Caps. All Caps to be taped and secured for shipment Shrink wrap the tube ends. See attached spread sheet for detailed list of bent tubes for both NR1 and NR2 boilers.
2.3 All fabrication shall be In Accordance with drawings E-174-600 and E-174-601.
2 | P a g e
2.3 Required Date of Delivery: 01/24/2025
3.0. DELIVERY / ACCEPTANCE
3.1. Delivery shall be made to the following address:
DLA Distribution Norfolk RMC PROJ Bunker Hill Towaway Bldg. X136 Norfolk, VA 23511
3.2. Shipping terms shall be FOB Destination. The product shall be accepted and inspected at FOB Destination. Shipping cost shall be included in the quote.
File details come from the government source that posted it. Updated .