This document is a contractor past performance questionnaire template to be completed for a federal project involving the remodeling of a visitor center, abandonment of a sewer system, and demolition of a comfort station. The project is solicited by the Department of the Interior National Park Service Midwest Region under solicitation number 140P6021R0005. The questionnaire evaluates a contractor's performance on factors such as adherence to schedule, plans and specifications, quality of work, communication, and responsiveness to changed requirements. Respondents are asked to provide ratings from 1-10 on these performance metrics and include any additional comments. Contact information is also requested for the person completing the questionnaire.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Solicitation_Amendments_(0001_Questions_and_Answers)_0001.pdf | ||
| B09_Solicitation_Amendments_(0001_Site_Visit_Roster)_0001.pdf | ||
| Sol_140P6021R0005_Amd_0001.pdf | ||
| Attachment 7 - Executive Order No. 13991 Notice.pdf | ||
| Attachment 3 - Specifications - NPS Cabling Standard.pdf | ||
| Attachment 5 - Technical - Previous Experience Questionnaire.docx | DOCX document | |
| Attachment 4 - DOL Wage Determination.pdf | ||
| Attachment 2 - Drawings.pdf | ||
| Attachment 1 - Specifications.pdf | ||
| Sol_140P6021R0005.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR PAST PERFORMANCE QUESTIONNAIRE
Date____________________ Contractor Name _____________________________ Project Title/Description___________________________________ Point of Contact _____________________________ Contract Type [ ] RFQ [ ] Sealed Bid [ ] Fixed Price [ ] Negotiated
Contract Period ________________________ Cost Original $_______________ Current/Final $_______________
For the scales below, 1 = Poor, 10 = Outstanding
1. Was the project completed within the allotted time? [ ] Yes [ ] No
2. How effective was the contractor with establishment
1 2 3 4 5 6 7 8 9 10 N/A and execution of the schedule?
3. Contractor’s adherence to plans and specifications
1 2 3 4 5 6 7 8 9 10 N/A
4. Submission of documents and reports (submittals)
1 2 3 4 5 6 7 8 9 10 N/A
5. Standards of workmanship/quality
1 2 3 4 5 6 7 8 9 10 N/A
6. Completion of final punch-list
1 2 3 4 5 6 7 8 9 10 N/A
7. Supervision
1 2 3 4 5 6 7 8 9 10 N/A
8. Communication, coordination, and cooperation (CO, COTR, etc.)
1 2 3 4 5 6 7 8 9 10 N/A
9. Was the contractor fair/reasonable regarding equitable
1 2 3 4 5 6 7 8 9 10 N/A adjustments and cost proposals in response to changed work requirements?