Attachment 4 - MAHG201091 AF66_B412 Reno_13 July 2020.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- Renovate Building 412 for DCSA Federal contract opportunity
- Solicitation number
- FA301020R0038
About this file
This submittal register and statement of work outline the requirements for renovating Building 412 at Keesler Air Force Base for the Defense Counterintelligence and Security Agency. The contractor will be required to submit shop drawings, samples, warranties and other documentation within 10 days of notice to proceed. Key work includes finish carpentry, interior woodwork, solid surface fabrication, insulation, sealants, doors, hardware, framing and board, flooring, paint, plumbing fixtures, ductwork, HVAC controls, air balancing, electrical and communications systems. The contractor must also provide refrigerant testing, duct cleaning reports, equipment specifications, an execution schedule and closeout documentation. The solicitation is set aside for Service Disable Veteran Owned Small Businesses, with pricing due by August 6, 2020 and work expected to be between $250,000 and $500,000.
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF 66 Sheet 1-16
SUBMITTAL REGISTER MAHG20-1091 RENOVATE 412 FOR DCSA
| TO BE COMPLETED BY PROJECT MANAGER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||
| ITEM NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NO. OF COPIES REQUIRED | REQUIRED SUBMISSION DATE | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |||||||||
| CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | DATA | DOCUMENT \ REPORT |
APPROVED DIS-APPROVED
| 1 | HazMat Questionnaire | 3 | 3 | 5 Days Prior to Start Date | ||||||||||
| 2 | HazMat MSDS | 3 | 5 Days Prior to Start Date | Must be filled out if contractor answers YES to the Hazmat Questionnaire | ||||||||||
| 3 | Hazmat Reporting Entry Form | 3 | 3 | 5 Days Prior to Start Date | Submit Final Quantities | |||||||||
| 4 | Hazmat Reporting Entry Form | 3 | 3 | End of Contract | ||||||||||
| 5 | Recycling and Landfill Report | 3 | 3 | End of Contract | ||||||||||
| 6 | Warranty (Manufacturer's) | 3 | End of Contract | |||||||||||
| 7 | 1-Year Warranty (Contractor) | 3 | End of Contract | |||||||||||
| 8 | Section 062000-Finish Carpentry (Cabinets/Hardware) | 1 | 1 | 10 days following NTP | ||||||||||
| 9 | Section 064020 - Interior Architectural Woodwork | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||||
| 10 | Section 066500-Solid Surface Fabrication | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||||
| 11 | Section 072000-Insulation (Sound attenuation insulation, sealant) | 1 | 1 | 1 | 10 days following NTP | |||||||||
| 12 | Section 079200- Joint Sealants | 1 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 13 | Section 081113-Steel Door and Frames | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||||
| 14 | Section 082000-Wood Doors | 1 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 15 | Section 087100-Door Hardware | 1 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 16 | 087200-Thresholds | 1 | 1 | 1 | 10 days following NTP | |||||||||
| 16 | 092216-Non-Structural Metal Framing | 1 | 1 | 1 | 10 days following NTP | |||||||||
| 17 | Section 092550-Gypsum Board Assemblies | 1 | 1 | 1 | 10 days following NTP | |||||||||
| 18 | Section 095110-Acoustical Panel Ceilings | 1 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 19 | Section 096500-Luxury Vinyl Tile | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||||
| 20 | Section 096513-Rubber Wall Base | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||||
| 21 | Section 096813- Tile Carpeting | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||||
| 22 | Section 099100-Paint | 1 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 23 | Section 099323-Stains and Transparent Finishes | 1 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 24 | Plumbing (See Specifications) | 1 | 1 | 30 days following NTP | ||||||||||
| 25 | Toilet Fixtures, Flush Valves | |||||||||||||
| (See SOW, Mechanical Installation, pp10of24; See Plumbing & Piping Specifications, pp1-6) | 1 | 3 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 26 | Urinals, Flush Valves | |||||||||||||
| (See SOW, Mechanical Installation, pp10of24; See Plumbing & Piping Specifications, pp1-6) | 1 | 3 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 27 | Sinks, Faucets, Temp Reg Valves | |||||||||||||
| (See SOW, Mechanical Installation, pp10of24; See Plumbing & Piping Specifications, pp1-6) | 1 | 3 | 1 | 1 | 1 | 10 days following NTP | ||||||||
| 28 | Duct Construction (See SOW, Mechanical Installation, pp8of24; See Duct Construction & Accessories Specification, pp1-6) | 1 | 1 | 3 | 1 | 1 | 30 days following NTP | |||||||
| 29 | Fire Dampers (See SOW, Mechanical Installation, pp8of24; See Duct Construction & Accessories Specification, Fire Dampers, pp3of6) | 1 | 1 | 10 days following NTP | ||||||||||
| 30 | Balancing Dampers (See SOW, Mechanical Installation, pp8of24; See Duct Construction & Accessories Specification, Manual Balancing Dampers, pp4of6) | 1 | 1 | 10 days following NTP | ||||||||||
| 31 | Supply Diffusers | |||||||||||||
| (See SOW, Mechanical Installation, pp8of24; See Duct Construction & Accessories Specification, Supply Air Diffusers, pp3of6) | 1 | 1 | 10 days following NTP | |||||||||||
| 32 | Return, Exhaust Grilles | |||||||||||||
| (See SOW, Mechanical Installation, pp8of24; See Duct Construction & Accessories Specification, Return Air Grilles, pp3of6) | 1 | 1 | 10 days following NTP | |||||||||||
| 33 | Air Filters (See SOW, Mechanical Installation, pp8of24; See Duct Construction & Accessories Specification, Disposable Air Filters, pp4of6) | 1 | 1 | 10 days following NTP | ||||||||||
| 34 | HVAC Controls OP Test (See SOW, Mechanical Installation, pp9of24) | 1 | 1 | 1 | 10 days following NTP | |||||||||
| 35 | Natural Gas OP/Leak Test | |||||||||||||
| (See Plumbing & Piping Specification, Natural Gas Testing, pp9of11) | 1 | 1 | 1 | 10 days following Test | ||||||||||
| 36 | HFW OP/Leak Test | |||||||||||||
| (See Plumbing & Piping Specification, CFW & HFW Piping System Testing, pp9of11) | 1 | 1 | 1 | 10 days following Test | ||||||||||
| 37 | CFW OP/Leak Test | |||||||||||||
| (See Plumbing & Piping Specification, Refrigerant Piping System Testing, pp9of11) | 1 | 1 | 1 | 10 days following Test | ||||||||||
| 38 | Drain OP/Leak Test | |||||||||||||
| (See Plumbing & Piping Specification, Waste Drain and Condensate Drain Testing, pp9of11) | 1 | 1 | 1 | 10 days following Test | ||||||||||
| 39 | Refrigerant Pneumatic Test |
AHU 1 DX piping
| (See Plumbing & Piping Specification, Refrigerant Piping System Testing, pp7of11) | 10 days following Test | ||
| 40 | Refrigerant Evacuation Test |
AHU 1 DX piping
| (See Plumbing & Piping Specification, Refrigerant Piping System Testing, pp7of11) | 10 days following Test | ||
| 41 | Refrigerant Pneumatic Test |
LAN RM cooler DX piping
| (See Plumbing & Piping Specification, Refrigerant Piping System Testing, pp7of11) | 10 days following Test | ||
| 42 | Refrigerant Evacuation Test |
LAN RM cooler DX piping
| (See Plumbing & Piping Specification, Refrigerant Piping System Testing, pp7of11) | 10 days following Test | |||||||||||
| 43 | Duct Cleaning Report AHU1 | |||||||||||
| (See SOW, Mechanical Demolition pp4of24; and Duct Cleaning Specification pp12of24) | 1 | 1 | 3 | 10 days following Test | ||||||||
| 44 | Duct Cleaning Report AHU2 | |||||||||||
| (See SOW, Mechanical Demolition pp4of24; and Duct Cleaning Specification pp12of24) | 1 | 1 | 3 | 10 days following Test | ||||||||
| 45 | Duct Leak Test AHU1 | |||||||||||
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 3 | 10 days following Test | ||||||||
| 46 | Duct Leak Test AHU2 | |||||||||||
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 3 | 10 days following Test | ||||||||
| 47 | AHU1 Air Balance Test | |||||||||||
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 3 | 10 days following Test | ||||||||
| 48 | AHU2 Air Balance Test | |||||||||||
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 3 | 10 days following Test | ||||||||
| 49 | Electrical/Communications (See Electrical Drawings) | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||
| 50 | LED Fixtures (See Electrical Drawings and SOW 'Electrical Provide new') | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||
| 49 | Fire Alarm (See Electrical Drawings and SOW 'Electrical Provide new') | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | |||||
| 50 | Access Control (See Electrical Drawings and SOW 'Electrical Provide new') | 1 | 1 | 1 | 1 | 1 | 1 | 10 days following NTP | ||||
| 51 | AHU 1, Evaporator Unit | |||||||||||
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 1 | 3 | 1 | 1 | 3 | 3 | 14 days following NTP | |||
| 52 | AHU 1, Condensing Unit | |||||||||||
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 1 | 3 | 1 | 1 | 3 | 3 | 14 days following NTP | |||
| 53 | AHU 1, Gas Duct Furnace | |||||||||||
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 1 | 3 | 1 | 1 | 3 | 3 | 14 days following NTP | |||
| 54 | LAN/COMM RM Cooler |
Mini-Split Cooling Unit
| (See SOW, Mechanical Installation pp10of24) | 1 | 1 | 1 | 3 | 1 | 1 | 3 | 3 | 14 days following NTP | ||||||
| 55 | Work Execution Schedule (See Section 23 01 30, Page 2) | 1 | 10 days following NTP | ||||||||||||
| 56 | Operations and Maintenance Manuals | 1 | 1 | 1 | 3 | 1 | 1 | 3 | 3 | Project Close Out | (2 hard copy, in binder, and 1 digital copy of each) | ||||
| 57 | CABLE TEST REPORT | 3 | Project Close Out | 2 hard copies/1 Electronic |