Attachment 2 - Special Project Specifications.docx
DOCX document 28 KB Posted
- Attached to
- Maah Daah Hey North Trail Reconstruction Federal contract opportunity
- Solicitation number
- 1240LT22Q0106
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Wage Determination ND20220039.pdf | ||
| 1240LT22Q0106.pdf | ||
| Attachment 4 - Location Maps.pdf | ||
| Attachment 3 - Project Drawings.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 2 – 1240LT22Q0106
SPECIAL PROJECT SPECIFICATIONS
Section 906 – Measurement & Payment
906.01 General. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered incidental to and included in the payment of the pay items in the Schedule of Items. Work measured and paid for under one pay item will not be paid for under any other pay item.
906.02 Determination of Quantities. The following measurements and calculations are used to determine contract quantities for payment.
For items that are measured by the linear foot, station, or mile measurements will be made along the centerline and parallel to the specified grade or foundation, unless otherwise Shown on the Drawings.
906.03 Units of Measurement. Payment will be by units defined and determined according to U.S. standard measure and by the following.
(A) Lump Sum (LS) The quantities that denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.
(B) Linear Foot (LF) Measurement of 12 inches along a reference line.
(C) Mile 5,280 Linear feet along a reference line.
(D) Cubic Yard (CY) The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
(E) Each (EA) One complete unit which may consist of one or more parts. The quantity is the actual number or units completed and accepted.
(F) Hour (H) Measurements will be for the actual number of hours performed by the contractor.
906.04 Methods of Measurement. One of the following methods of measurement for determining payment is Designated on the Schedule of Items for each Pay Item.
(A) Actual Quantities. (AQ) these quantities are determined from measurements of completed work.
(B) Lump Sum Quantities. (LSQ) these quantities denote one complete unit of work as required by or described in the contract, including necessary material, equipment, and labor to complete the job.
(C) Contract Quantities. (CQ) These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations and drawings. Changes in the number of units Designated in the Schedule of Items maybe authorized under the following:
1. As a result of changes in the work approved by the CO.
2. As a result of the CO determining that errors exist in the original design that cause a Pay Item quantity to change by 15 percent or more.
3. As a result of the contractor submitting to the CO a written request showing evidence of errors in the original design that cause a Pay Item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
DPG SPS 906 (2/17)
Section 915-Trail Restoration/New Trail Construction
Description
915.01 Work consists of restoring the original trail template, including, removing slough and berm, borrow, filling ruts, holes and troughs, reshaping backslopes, excavation, reshaping trail tread, restoring drainage and other trail structures, constructing check dams, and removing protruding rocks, roots and stumps.
Construction
915.04 Excavation and Embankment. This work consists of the excavation and placement of excavated material, regardless of its nature, from within the trail way. Remove all duff, debris, stumps and excavation from within trailbed limits and uniformly spread 4 feet outside the trail way, on the downslope, not more than 4 inches in depth. Do not obstruct drainage or create piles, berms, or windrows of debris. Remove stumps located between the edge of the trailbed and the edge of the trailway that cannot be cut flush with the finished slope or that are not tightly rooted. Remove all roots from within the trailway. Conserve and use all suitable material for specified work. Conserve excess excavated rock suitable for specified project work. Compact embankments with suitable material free of excess moisture, frozen lumps, roots, sod or other deleterious material with maximum particle size of 4”. Compact all disturbed soil within the trail bed to provide a smooth-running surface using approved compaction methods and equipment.
915.06 Slough and Berm. Removal and Excess Material. Use suitable slough and berm material within the trailway to restore the trailbed as SHOWN ON THE DRAWINGS. Place all unsuitable and excess material beyond the downslope edge of the trailbed and uniformly spread to a depth not exceeding 4" and so as not to obstruct drainage or interfere with the drainage of outsloped tread. Remove berm when daylight can be obtained within 5’ from the outslope edge of finished tread unless otherwise DESIGNATED ON THE GROUND or SHOWN ON THE DRAWINGS.
915.07 Fill Material and Borrow. Obtain suitable borrow material from approved local sources to fill ruts, troughs, gullies and holes in the tread that cannot be leveled and outsloped through performance of work. Compact all fill areas using approved compaction methods and equipment.
915.08 Drainage. Restore drainage dips and ditches to reestablish drainage as SHOWN ON THE DRAWINGS by removing obstructions such as soil, rocks, roots, and sticks to make ditches and culverts free draining.
915.10 Check Dams. Construct Earthen Check Dams for gullies with the top of the dam level with surrounding ground and spillway 6” below top of dam. Firmly compact using approved methods and equipment at locations SHOWN ON THE MAPS.
915.11 Switchbacks. This work consists of restoration of switchbacks including excavation, ditches and approach sections at locations SHOWN ON THE MAP or DESIGNATED ON THE GROUND.
915.12 Rolling Dips. This work consists of Constructing or Maintaining rolling dips, including excavation, backfill and compaction. The length of the dips varies. Construct the rolling dips to drain. Install rolling dips of the type and at the locations SHOWN ON THE DRAWINGS and as DESIGNATED ON THE GROUND.
915.14 Trail Structures. Restore all trail structures at locations SHOWN ON THE DRAWINGS or DESIGNATED ON THE GROUND.
915.15 Reshaping and Finishing Trailbed and Backslopes. Provide a firm and uniformly finished trailbed as SHOWN ON THE DRAWINGS. Leave the finished slope in a uniform and roughened condition. Cut all roots flush and leave no vertical cut slopes
Measurement
915.13 Method. Measure the quantities in accordance with Section 906. Quantities for switchbacks and rolling dips are estimates and are provided for information only.
Payment
915.14 Basis. Pay for the accepted quantities in accordance with Section 906 at the contract unit price for each PAY ITEM SHOWN IN THE SCHEDULE OF ITEMS. All items listed in 915.01 Work are considered Incidental to Pay Items 915 and 912. Rolling Dips and Switchbacks are separate pay items.
Make payment under:
PAY ITEM
915 Trail Restoration............................................................ L.F.
912 New Trail Construction…………………………….… L.F.
DPG SPS 915 (2/22)
Section 951 – Mobilization Description
951.01 Work consists of moving personnel, equipment, material and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the costs associated with obtaining permits, insurance, and bonds. Mobilization is not intended to pay the costs of materials before they are used on the project site. Work also includes cleaning of all equipment used at the project site. Clean all construction equipment prior to entry on the project site. Remove all dirt, plant parts and material that may carry noxious weed seeds into the area. Only construction equipment inspected by the Forest Service will be allowed to operate within the project area. Treat subsequent move-ins of equipment the same as the initial move-in. Clean truck beds and dump boxes hauling to the project site prior to entering the work area.
Payment
951.02 Basis. Pay for the accepted work at the contract unit price for the PAY ITEM SHOWN IN THE SCHEDULE OF ITEMS.
(a) Reimburse for bond premiums before issuing the Notice to Proceed if evidence of payment is received.
(b) When 5 percent or more of the original contract amount is earned from other PAY ITEMS, pay mobilization at the rate of 50 percent, or up to 5 percent of the original contract amount, whichever is less.
(c) When 10 percent or more of the original contract amount is earned from other PAY ITEMS, pay mobilization at the rate of 100 percent, or up to 10 percent of the original contract amount, whichever is less.
(d) Pay any unpaid amount for mobilization upon final acceptance of all work items.
Make payment under:
PAY ITEM PAY UNIT
951 Mobilization …………………………………………………………...LS
DPG SPS 951 (4/12)
Section 622 – Rental Equipment
Description This work consists of furnishing and operating equipment for construction work ordered by the CO and not otherwise provided for under the contract.
Construction Requirements
Rental Equipment. The CO will order in writing rental equipment for use on the project. Contractor shall make equipment available for inspection and approval before use. Contractor shall furnish and operate equipment with such auxiliary attachments as are usually needed for efficient operation of the equipment. Keep the equipment in good repair. Operators shall be competent and experienced in the work.
Equipment Description A mini excavator equipped with Roll over Protection and capable of a track width adjustment to 39”, outside-to-outside or less. 14 HP minimum rating. Minimum operating weight 3500lbs. Equipped with a front dozer blade and a back-hoe bucket at least 18” wide.
Acceptance is based on visual inspection of the work for compliance with the contract and prevailing industry standards.
Measurement
Measure the Section 622 items listed in the bid schedule according to the following.
An hour consists of 60 minutes of actual operation of equipment on authorized Government work. Moving of equipment under its own power, when so ordered by the CO will constitute authorized work. Nonproductive time such as, but not restricted to, lack of operating supplies or qualified operator, service time, time lost by reason of breakdown or being stuck or loading time of specified accessories shall not constitute “actual operation”. Hours of actual operation will be maintained by the CO. Moving of equipment, accessories, support equipment and personnel to and from the project shall be paid under Section 951 Mobilization. Moving of equipment and specified accessories between job locations shall be at Government expense. The CO shall determine the method of moving equipment. Moving of support equipment and personnel between job locations shall be at the Contractors’ expense.
Payment
Basis. The accepted quantities will be paid at the contract unit price of measurement for each pay item listed in the schedule of items.
Payment will be made under:
Pay Item Pay Unit
622 Rental Equipment (Mini Excavator)……………………………………. Hour