This document is a Price Schedule for Vegetation Removal Services at Conchas Dam Project by the U.S. Army Corps of Engineers. The solicitation (W912PP25QA001) covers a base year (2025) with four additional option years (2026-2029), requiring vegetation removal services twice per calendar year - once during the growing season (April 1-August 30) and once during the dormant season (October 1-December 31). The price schedule details 19 specific locations totaling 116.79 acres, including areas such as Emergency Spillways, Dam Road Shoulders, Guardrails, Drainage Ditches, and various facility areas.
The contract requires the contractor to provide all labor, management, equipment, supplies, and materials for vegetation removal via pesticide application, with services to be performed in strict accordance with the Performance Work Statement and U.S. Department of Labor Wage Determination. The point of contact is Jonathan T. Hicks, Lake Manager, reachable at (575) 868-2221. A site visit is scheduled for 26MAR25 at 1300 MDT, and quotes must be submitted using the attached Offeror Price Schedule. The contract is classified as a non-personal services contract, with contractors accountable solely to the primary contractor, who is responsible to the Government.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 Approximate Acreage Maps and Descriptions.pdf | ||
| Wage Determination.pdf | ||
| PWS Conchas Vegetation Contract FY25_18MAR2025.pdf | ||
| Solicitation - W912PP25QA001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 - Price Schedule
| Fill in Yellow Fields Only |
| PRICE SCHEDULE |
Conchas Dam Vegetation Removal
| Location | Acreage | Base Year | ||
| Price/Acre | Extended | |||
| Base Price | Option Year 1 Price/Acre | Extended | ||
| OY1 Price | Option Year 2 | |||
| Price/Acre | Extended | |||
| OY2 Price | Option Year 3 | |||
| Price/Acre | Extended | |||
| OY 3 Price | Option Year 4 | |||
| Price/AC | Extended |
OY4 Price
| Emergency Spillway - North | 2.82 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Emergency Spillway | 5.25 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Emergency Spillway - South | 4.63 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Administration Area | 0.63 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Maintenance Yard | 1.91 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| North Wing Dam, Road Shoulders, and Guardrail | 8.75 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Dam Entrance Area | 0.62 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| South Wing Dam, Road Shoulders, and Guardrail | 22.54 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| South Dike, Road Shoulders, and Guardrail | 42.02 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| South Drainage Ditch | 4.63 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Headworks | 6.01 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Ranger Station | 0.41 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Pump House | 0.05 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Juniper Day Use Area | 0.71 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Boat Ramp | 4.47 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Lagoons | 4.95 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Storage Area | 2.33 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Saddle Dam | 4.06 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other (Please Identify): ________________________ | 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other (Please Identify): ________________________ | 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other (Please Identify): ________________________ | 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Per Service: | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Quantity - Services / Year | 1 | 1 | 1 | 1 | 1 | ||||||
| Subtotals | 116.79 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Grand Total | $ - 0 |
| The Contractor shall furnish all labor, management, equipment, supplies, and materials needed for Vegetation Removal Services to be performed at the Conchas Dam Project, in strict accordance with the attached Performance Work Statement and US Department of Labor Wage Determination. Price includes all applicable Federal, State, and Local Taxes. Point of contact for this project is Jonathan T. Hicks, Lake Manager, at (575) 868-2221. |
| The Contractor shall provide vegetation removal services twice per calendar year – once in the growing season (between April 1 and August 30) and once in the dormant season (after the first hard freeze between October 1 and December 31) for the Base Year (2025), Option Year 1 (2026), Option Year 2 (2027), Option Year 3 (2028), and Option Year 4 (2029). A list of locations and estimated acreage per location is located on Tab 2. |
File details come from the government source that posted it. Updated .