Attachment 1 Statement of Work.pdf

PDF 241 KB Posted

Attached to
Concrete Slab for Containerized Lab - USDA ARS Hilo, HI Federal contract opportunity
Solicitation number
12905B23Q0197
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Pacific West Area

About this file

This statement of work outlines requirements for a construction project to build a concrete slab foundation for a containerized laboratory at the USDA Agricultural Research Service facility in Hilo, Hawaii. The project involves providing labor, materials and equipment to construct a 45' x 8' reinforced concrete slab with a 6" x 6" perimeter moat and 4' sidewalk. The slab must meet specifications for thickness, reinforcement, finishing and have a minimum compressive strength of 2,500 psi. The contractor will be responsible for site preparation including grading, excavation and installation of a 1" water supply line beneath the slab. The selected contractor must adhere to all permit, safety and code requirements and properly dispose of all waste. The performance period is 90 calendar days from notice to proceed. The solicitation is designated for small businesses under the Davis Bacon Act.

View the file

Other files for this federal contract opportunity

Other files attached to Concrete Slab for Containerized Lab - USDA ARS Hilo, HI, newest first.
File Type Posted
SF18_12905B23Q0197_RFQ.pdf PDF
Attachment 4 ARS_372_REQUEST FOR PAYMENT TRANSMITTAL.pdf PDF
Attachment 2 Wage Determination HI20230001 7_28_2023.pdf PDF
Attachment 3 ARS_371_CONSTRUCTION PROGRESS AND PAYMENT SCHEDULE.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

CONCRETE SLAB FOR CONTAINERIZED

LAB

USDA-ARS

ARS-PBARC-DKI

64 Nowelo St, Hawaii 96720

STATEMENT OF WORK

1.0 CONTRACT PROJECT:

a. Project Title:

Construct concrete slab for containerized laboratory.

b. Service Location:

USDA-ARS-DKI

Pacific Basin Agricultural Research Center

2.0 PROJECT CONTACT PERSONS:

a. CONTRACTING OFFICER (CO):

Michael Sherlock Michael.Sherlock@usda.gov (510)559-6339

RESEARCH LEADER (RL):

Tracie Matsumoto Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo Hi 96720

(808) 959-4358/4349 E-mail: tracie.matsumoto.usda.gov

b. ADMINISTRATIVE OFFICER (AO):

Carlee Wehrsig Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo, HI 96720 Phone: (808) 959-4312 E-mail: carlee.wehrsig@usda.gov

d. LOCATION CONTRACTING OFFICER REPRESENTATIVE (COR):

Pernell Hanoa

Facilities Manager Daniel K. Inouye U.S. Pacific Basin Agricultural Research Center USDA-Agricultural Research Service 64 Nowelo Street, Hilo, HI 96720 Phone: (808) 959-4356 Cell: (808) 896-4523 E-mail: pernell.hanoa@ars.usda.gov

e. SAFETY OFFICER (CDSO) Scott Geib PhD

USDA-ARS Pacific Basin Agricultural Research Center 64 Nowelo Street, Hilo, Hawaii 96720 808-959-4335 E-mail: scott.geib@ars.usda.gov

3.0 SCOPE OF WORK

The contractor shall provide all professional services necessary for the accomplishment of the contract service and such required service shall be in accordance with the requirements as described herein and on attached contract documents.

3.1 Background: The USDA/DKI-PBARC located at 64 Nowelo St in Hilo Hawaii requires the labor and materials to construct a 45’ x 8’ reinforced concrete slab with a 6” x 6” moat and a 4’ sidewalk set above grade. Note: This foundation will provide a solid foundation for the 40’ containerized laboratory. This container will be used to cultivate plants imported under an APHIS Controlled Import Permit

3.2 Contractor shall provide the labor and materials to construct reinforced concrete slab set above grade. See appendix A for details and specifications.

3.2.1 Ground will be leveled with a base coarse and high enough to avoid water run off entering the building.

o Concrete shall have a minimum thickness of 6” and level.

o Concrete shall have a reinforced wire mesh.

o Concrete shall have a minimum strength rating of 2500 PSI.

o Concrete slab will have an inner area of 45 ft x 8 ft surrounded by a

6” deep x 6” wide water moat surrounded by a 4’ wide sidewalk.

o Water moat will be made of or coated with solid, impervious, and waterproof material that can hold at least 4’ of water.

o Plumbing pipe (1”) to be installed under the concrete slab with a sand base.

Plumbing pipe with faucet to fill the moat will extend a minimum of 1 ft from the cement floor on the area inside the moat.

Other end of the pipe will extend a minimum of 6” from the end of the concrete with a temporary cap (until a water source is provided).

o Contractor shall provide all the necessary excavation/fill and compaction requirements to meet concrete construction specifications.

o Concrete surface shall have a brushed finish to prevent slipping.

o Contractor shall remove all excess material and debris from site.

4.0 PROJECT REQUIREMENTS:

mailto:scott.geib@ars.usda.gov

a. Site visit is highly recommended to verify equipment, design, project location, equipment requirements and specifications.

b. The Contractor will work with site personnel to ensure project is accomplished in a timely manner.

c. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction and services shall comply with applicable federal, state, and local code requirements as well as current industry standards, (ie: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.

d. All work to meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.

ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.

e. This project falls under the DAVIS BACON Wage Act.

4.1 Background & Site Description:

The project site is located at the Daniel K. Inouye, Pacific Basin Agricultural Research Center Hilo Hawaii. Construct concrete slab.

4.2 Bid Schedule:

Item Description

Base Item Provide equipment, labor, materials, and all associated services necessary to complete replacement project.

4.3 Description of Work:

a. The Contractor will provide a turn-key project satisfying all Local, State, and Federal requirements.

b. The Contractor will provide all the necessary materials and labor per

Section 3.0 and properly dispose of all material being replaced.

c. Contractor is responsible for any damage to adjacent equipment and miscellaneous objects that may become damaged during construction. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.

d. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ for conditions that would be visible during an on-site visit for persons experienced performing this type of work.

4.4 Government Furnished Equipment\Services

a. The Government does not anticipate the need in this project, but the Government will be available to assist with the identification/location of utilities as necessary.

b. The Government will furnish a reasonable amount of electricity and water.

5.0 GENERAL REQUIREMENTS:

5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disturbances that might jeopardize on-going operations and research. Owner reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose all any materials removed that will not be retained.

5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.

5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.

5.6 Protection of Work and Property/Safety Requirements:

a. Contractor shall furnish a Site-Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) 10 days after contract award upon request. SSSP / APP shall be reviewed by the Government before construction work commences. In addition to the usual components of a safety plan, the plan shall include specific procedures to address mold encountered during the project.

b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.

c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

d. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities.

5.7 Temporary Facilities:

a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during construction and shall repair or replace any items damaged through its own negligence.

b. Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from location staff or maintenance personnel as possible as possible.

5.8 Materials and Equipment:

a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.

b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR.

c. Government will not furnish any labor or equipment to unload or move materials or supplies.

5.9 Cleanup: The work site shall always be kept clean and free of debris. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

5.10 Warranty:

a. Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

b. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.

5.11 Final Payment/Contract Closeout: The following documents are REQUIRED

PRIOR TO FINAL PAYMENT (other documents may also be required):

a. General contractor’s minimum 30 days warranty on all work.

b. Operation and Maintenance Data

c. Release of liens.

d. Final Invoice

6.0 PROJECT SCHEDULE: The Contract time for this project is 90 calendar days from Notice to Proceed.

Appendix A Drawing not to scale

45 feet 4 ft

6” wide by 6” deep water moat

8 ft 1” plumbing conduit with water fixture

United States Department of Agriculture
Agricultural Research Service
CONCRETE SLAB FOR CONTAINERIZED LAB
USDA-ARS
ARS-PBARC-DKI
64 Nowelo St, Hawaii 96720

File details come from the government source that posted it. Updated .