Attachment 1 - Statement of Work.pdf

PDF 821 KB Posted

Attached to
Repair Pavement Apron Forxtrot Federal contract opportunity
Solicitation number
FA448620PM002
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

This document is a Sources Sought notice issued by the 65th Contracting Flight at Lajes Field, Azores, Portugal. The notice seeks feedback from companies capable of providing construction services to repair cracks in asphalt pavements on Apron Foxtrot at Lajes Field. Interested sources are requested to provide a capability statement briefly describing previous and/or current relevant work experience. The response due date is 13 March 2020. Requested information includes indication of ability to provide the services, description of infrastructure and capacity, SAM or NCAGE/DUNS information, required commercial practices, and need for a pre-solicitation site visit. The document represents the government's only official notice of this potential procurement for repair and maintenance services at Lajes Field, Azores, Portugal.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Pavement Apron Forxtrot, newest first.
File Type Posted
FA448620PM002 Sources Sought.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FOR

REPAIR PAVEMENT ON APRON

FOX

MQNA 19-1508

Portfolio Optimization Office, 65th Civil Engineer Squadron

25 November 2019

USAFE

Lajes Field, Azores, Portugal 65th Civil Engineer Squadron

APO AE 09720

SUMMARY OF WORK

Project title: Repair Pavement on Apron Fox Location: Lajes Field, Azores, Portugal Project number: MQNA 19-1508 Facility: Apron Foxtrot (11019)

1. General:

The contractor shall provide all plant labor, materials, tools, equipment, transportation, supervision and personnel necessary to repair all the cracks in asphalt pavements in the Foxtrot Pavement. The Contractor shall also apply an asphalt rejuvenator as described in the below specifications. Finally, the Contractor shall also paint all apron Markings as previously existing to the repair. The work is located at the East area of Airfield, Lajes Field, Azores, Portugal and shall be performed in accordance with this Statement of Work (SOW), Project Drawings, the Technical Specifications and in accordance with the latest versions of “Lajes Field Construction Site Standards” and “Lajes Field Facilities Excellence Standards”.

2. Scope of work:

The following list of principal features is intended as a guide only and should in no way be considered an all-inclusive description of the work and does not relieve the contractor from the responsibility to complete the work in accordance with the applicable construction drawings, schedules, regulations and specifications.

2.1 Demolition work

2.1.1 Perform the full cleaning of all existing medium (and above) severity cracks (as defined by the Army Core of Engineers and the Specifications Below) and joints in the asphalt pavement on Apron Foxtrot in an extension of approximately (but no less than) 55,000.00 m (meters), in the areas defined in the Government Drawings in accordance with the Specifications of this Statement of Work.

The cracks and joint cleaning shall be performed by a hotlance blaster (capable of burning weeds and drying the cracks, deep down) at a pressure of 8bar through a maximum dimension 6.00 mm (millimeter) pipe.

2.1.2 Perform high pressurized water cleaning of all the asphalt area of Foxtrot Apron in an area of approximately (but no less than) 220,000.00 m2 (square meters), in the areas defined in the Government Drawings in accordance with the Specifications of this Statement of Work.

2.1.3 High Pressurized cleaning shall include full rubber removal and sweeping in accordance with the below Specifications.

2.1.4 Remove all airfield line markings paint in the asphalt pavement on Apron Foxtrot in an extent of approximately 2,500.00 m, in the areas defined in the Government Drawings in accordance with the Specifications of this Statement of Work.

2.1.5 Before demolition work takes place, the contractor shall survey and precisely register all existing painted markings.

Demolition - General notes

Use appropriate equipment and techniques for demolition or removal work in order to avoid damages on surrounding area.

All materials from demolition shall be properly handled and disposed by the contractor, according with section 6 of this document.

All measurements stated in these Specifications are approximate, it’s the contractor’s responsibility to field verify all measurements.

In all demolition work, the Contractor shall comply with all Specifications in this Statement of Work.

2.2 New Work

2.2.1 Civil

2.2.1.1 The Contractor shall seal all cracks and joints of medium or higher severity in an extension of approximately (but no less than) 55,000.00 m. Priming is required before sealing.

A ready mixed emulsion primer shall be used, one that is that assures deep penetration and that softens the old bitumen to secure proper adhesion.

Cracks shall be cleaned and dry before priming.

2.2.1.2 All cracks shall be filled with a modified crack filling emulsion that allows it to run all the way to the bottom of the crack. To avoid over height on the cracks, the excess of emulsion shall be removed by a “V” shaped scraper.

Depending on the depth of the crack, this process may have to be repeated several times using the scraper in every time is needed.

2.2.1.3 After the sealant crack treatment is performed, but still sticky, a small spreading unit shall dust off the joint. The dust shall be graded from 0 to 1.2 mm in a manner that the filling doesn’t become sticky and provides initial friction to the section.

The dust shall consist of crushed granite.

2.2.1.4 The Contractor shall treat all area of Foxtrot Pavement with a sealant as identified in the Government Specifications and located in the Government Drawings. The treatment shall be performed in accordance with these Specifications with a cold applied bitumen emulsion system such as Pentack by COLAS Denmark, or equivalent. The Area to be applied is of approximately (but no less than) 220,000.00 m2.

The sealant shall be three component, consisting of a regenerating emulsion, a modified bitumen emulsion and water for viscosity control.

Asphalt Surface Treatment shall conform to SECTION 32 01 17.61, including equipment characteristics.

2.2.1.5 The three component mix shall be performed by specialized spraying equipment (truck) with the capability to automatically adjust the three components of the sealant. Due to possible contamination of the sealant, the spraying truck must be specific for this sort of treatment, therefore Contractors are not allowed to use prime/tack coat spraying equipment as nozzles may not be adequate and the reservoir may be contaminated by remains of undesirable prime/tack coat or other agents.

2.2.1.6 The contractor shall be aware that the work is being performed in the airfield.

Any damages caused to the pavement by the contractor are of its own responsibility as well as any necessary repairs. In this case, any Airfield pavement repair procedures must be submitted by the contractor and approved by the Contracting Officer previously to its execution.

2.2.1.7 Contractor shall paint all areas were markings were removed. The contractor shall submit the painting plan for approval including the type of paint, beads and equipment to be used.

Airfield Markings shall be heat applied in complete accordance with SECTION 32 17 24, including equipment characteristics.

2.2.1.8 Clean up the entire area at the end of each work period and before final inspection.

2.2.1.9 Due to the importance of the area where the Apron is located, the applicator (Contractor or sub-contractor) must have experience in rehabilitation of Airfield Pavements and must be OHSAS 18001 accredited.

2.2.1.10 The Contractor shall paint the Airfield Marking as previously existing in accordance with these Specifications.

2.2.1.11 Contractor must implement barricades in all areas were work is being performed in accordance with “ETL 04-2 Barricades” extract, included in this Statement of Work. The location of the barricades is defined in the Government Drawings, i.e. in the outside peripheral area of the “yellow zone”. The implementation of these barriers will require coordination with the Contracting Officer and Airfield Management. These barriers will cut off any Aircraft traffic in a buffer zone of a minimum of 25 meters away from the working Area.

2.2.1.12 Contractor shall protect all Tie-Downs existing on the Apron. After all work is finished the tie-downs must be in the previously existing condition.

2.2.1.13 All aforementioned work shall be performed in accordance with the Specifications below.

Civil - General notes

All measurements stated in these Specifications are approximate, it’s the contractor’s responsibility to field verify all measurements.

Cracks must be treated and sealed before the surface treatment takes place.

The treated pavement, shall not require rollers of any kind to finish the job. The product shall be able to impregnate the asphalt at least 10 centimeters, by gravity and run down the voids of the previously cleaned asphalt without additional equipment.

Phasing notes

All the work shall be performed in five phases, as designated in the Government Drawings. In each designated phase, the Contractor shall close the adjacent Taxiway and/or Taxi lane. Only after completion of one phase, including paintings, and acceptance by Government Supervision through the Contracting Officer, may the Contractor start work in the next stage.

A work phase will only be consider completed after all repair work, painting, cleaning and barrier removal is completed.

3. Submittals:

3.1 The Contractor shall submit requested data for all items listed in the included Submittal

Register. All submittal items must be approved prior to beginning any work. Documents to be submitted may include lists of materials, operating and maintenance instructions, manufacturer’s descriptive and technical literature, brochures, catalog cuts, performance data, spare parts data, shop drawings, diagrams, color samples, and other materials as appropriate.

Submittal related data shall conform to both Specifications and items designated in the Submittal Register document.

According to SAF/AQC Memorandum from 1 April 2016, all submittals must be provided in electronic form starting 1st October of 2016. Furthermore, all contract actions shall be signed digitally.

3.2 Materials will be approved based on the manufacturer’s published data meeting the requirements listed in the SOW and Specifications.

3.3 Underwriters Laboratories Inc.: Labels or printed documentation will be accepted as evidence that the materials conform to the applicable standards of the agency. In lieu of the labels or listing, the contractor may submit a statement from a recognized, adequately equipped testing agency indicating that the materials comply with all contract requirements.

3.4 Non-Underwriter’s Laboratories Inc. Requirements: For other materials specified to conform to Non UL publications, manufacturer’s statement indicating complete compliance with the applicable specifications or standard (Fed. Spec. Military Spec., or standard of the American Society for Testing and Materials, National Electrical Manufacturers, etc.) are acceptable.

3.5 Contractor is responsible for completing DD Form 1354 (Transfer and Acceptance of Military Real Property) and submitting it to the 65th Contracting Flight as a submittal item prior to the final inspection.

3.6 Number sequence of the submittal is stated in each Specification.

4. Coordination with government activities:

4.1 If it becomes necessary to interrupt work activities due to construction, permission to do so must be requested in writing to the CO twenty-one (21) days in advance.

4.2 The contractor shall request street closings, both partial and/or total, twenty-one (21) days prior to the closing.

4.3 Work in conjunction with this contract which requires utility outages which will affect (as determined by the CO) normal activities in the building, construction area, or other work areas, shall be performed by the contractor at a time other than regular work periods of the organization occupying the facility or area.

4.4 Temporary construction for facilities used by the contractor for preventing interruption of normal work activity or loss of utilities shall be subject to approval of 65 CES/CEN through the

CO.

4.5 Utility Outages:

4.5.1 The contractor shall coordinate all utility outages with the using agency through the CO or his representative prior to the outage. Services shall not be interrupted until receipt of approval of proposed hours and dates from the 65 CES/CEN through the CO. All work shall be arranged to ensure that the outage will be of minimum duration. The contractor will provide notice to the CO, in writing, not less than twenty-one (21) working days prior to the required outage or as determined by the CO. No response to the outage/interruption request shall be considered as disapproval for the outage/interruption. In the event of scheduled utility outage being canceled by the Government, notification shall be given to the contractor at least 24 hours in advance of the time for the outage to start and the contractor waives his right to any claim for equitable adjustment or increased cost of performance under this contract as a result of this cancellation. Once an utility outage is arranged and work as begun, it must go on continuously until the affected utilities are restored to the affected facility.

4.5.2 The contractor’s Interruption and Outage Requests shall include specific location of interruption/outage, hours and dates of interruption/outage, services affected by the interruption/outage.

4.5.3 Water Mains. Operation of valves on water mains will be by government personnel only.

Where shut-off of water lines interrupts service to fire hydrants or fire sprinkler systems, the contractor shall contact the CO and arrange his operations to have sufficient personnel available to restore service without delay in the event of an emergency as determined by the 65 CES/CEFP Fire Prevention Office.

4.5.4 Fire Protection System. Where interruption of electrical power affects a fire protection system service, the contractor shall notify the CO twenty-one (21) working days before making such interruptions and shall restore service prior to leaving the job site each day

5. Government furnished materials:

Not applicable.

6. General Information:

6.1 Hauling. All demolition debris becomes the property of the contrator, unless otherwise stated in the scope of work, and must be disposed of by the contrator in accordance with local and US regulations. All material hauled by the contractor shall be contained, tied, or enclosed to prevent leaking, spilling, or blowing.

6.2 Transportation routes. The contractor shall ensure all debris or dirt is promptly removed from any transportation route if such debris is spilled, blown, or leaked from hauling equipment and vehicles. All dirt and mud caused by tracks of hauling equipment will be removed by the contractor within one hour of notification by the government.

6.3 Disposal. All demolition collected by the contractor shall be disposed of in an authorized landfill or transfer station. No disposal is allowed on the sites. Materials to be turned over to Defense Logistics Agency – Disposition (DLA-DS) will be transported and dropped by contractor upon coordination with Construction Management and Contracting Office.

6.4 Workmanship. Materials shall be installed in accordance with recommendations of the manufacturer to conform to the contract document. The installation shall be done in accordance with manufacturer’s recommendations by personnel qualified to perform the work.

6.5 Warranty. The contractor shall provide a written warranty agreeing to repair or replace materials and services when damages resulted from poor workmanship within one (1) calendar year to begin at Government acceptance of work.

6.6 Safety. The contractor shall be responsible for all means and methods as they relate to safety and shall comply with all saftey requirements as outlined in the EM-385-1-1 Safety and Health Requirements manual. The contractor shall also abide by any local Portuguese safety requirements if more stringent than the EM-385-1-1.

7. Miscellaneous:

7.1 Distances, dimensions, exact location and other details must be field verified in order to assure proper installation and conformity with applicable standards, prior to the order of materials and/or execute the project;

7.2 Work shall be conducted with minimum disruption to operations and occupants of existing facility and/or property;

7.3 Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain;

7.4 Site restoration. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

7.5 Requests for power or water outages must be made to the government at least twenty-one (21) calendar days in advance

8. PERIOD OF PERFORMANCE:

8.1 Contractor is required to complete project within 240 (two hundred and forty days) calendar days including material acquisition after issue of Notice to Proceed.

9. References:

9.1 Government Drawings: As supplied in attachment 2.

9.2 Lajes Field Facilities Excellence Standards (LFFES).

9.3 Submittal Register.

10. Working Hours:

10.1 Regular working hours must consist of an 8 hour period, between 08:00 a.m. and 05:00 p.m., Monday through Friday.

Work outside regular working hours requires Contracting Officer approval.

11. Quality Control:

11.1 Site safety and Health Officer/Quality control shall be provided at the work site at all times to perform safety and occupational health and quality management, surveillance and inspections for contractor.

12. Specifications:

Document 00 73 03 Page 1

DOCUMENT 00 73 03

SUPPLEMENTARY CONDITIONS FOR AZORES PROJECTS

08/08

PART 1 GENERAL

1.1 SUBMITTALS

Submit

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only.

the following in accordance with paragraph "3. Submittals".

1 Preconstruction Submittals

AF Form 103; G

1.2 PHYSICAL DATA

Data referred to below is furnished for the Contractor's information.

However, it is expressly understood that the Government will not be responsible for interpretation or conclusion drawn therefrom by the

Contractor.

a. The physical conditions indicated on the drawings and in the specifications are the result of site investigations.

b. Geographic Conditions

(1) The Azores are comprised of a group of nine small islands, politically an integral part of Portugal, lying in the North

Atlantic, about 2,300 miles east of New York and about 980 miles west of Lisbon, Portugal.

(2) The climate is mild and the humidity high. Average annual temperature is 63 degrees F. Diuranal fluctuation in temperature is approximately 10 degrees. Highest recorded temperature, 80 degrees F, lowest recorded temperature, 40 degrees F. The yearly average rainfall is 44.80 inches; the monthly average rainfall and probability of rain is as follows:

Month Average

(in.)

Probability

January 6.00 65 percent

February 5.40 64 percent

March 5.00 61 percent

April 3.10 43 percent

May 1.80 39 percent

../Word/01%2033%2000.doc

Document 00 73 03 Page 2

Month Average

(in.)

Probability

June 1.80 33 percent

July 7.70 29 percent

August 1.80 35 percent

September 3.20 40 percent

October 5.20 55 percent

November 5.10 57 percent

December 5.30 58 percent

High winds occur from December through March. Average winds during this period are 11.6 knots. The recorded high winds are: November 90 knots, December 72 knots, January 90 knots, February 128 knots, March 106 knots, April 89 knots.

(3) Terceira Island measures roughly 11 by 18 miles, almost entirely bordered by high cliffs. The terrain is hilly and dominated by volcanic ranges, including two extinct craters. The airfield is located on the northeast side of the island. The total population of Terceira Island is approximately 60,000. The city of Angra do

Heroismo, capitol of the district, has a population of about

30,000; and the nearest town to the airfield, Praia da Vitoria, has a population of about 11,000.

c. Transportation Facilities for Lajes Field. Lajes Field is defined as the U.S. Forces Azores operational area on Terceira Island.

(1) Railroads: There are no railroads on the island.

(2) Highways and Roads: The majority of the roads are paved. A cobblestone and asphalt highway links Praia da Vitoria and Angra do

Heroismo. The use or construction of haul roads and bridges shall be subject to prior approval of the Contracting Officer.

(3) Ports: The island has two ports capable of handling deep draft ocean freighters, Praia da Vitoria and Angra do Heroismo.

(4) Air: Lajes Field is served by the commercial Portuguese airline

TAP, SATA and Ryanair.

1.3 LEGAL HOLIDAYS

For information purpose, the base acknowledges the following United States and Portuguese holidays:

*New Year's Day 01 January

Document 00 73 03 Page 3

Mardi Gras Variable

Good Friday Variable

Day of Liberty 25 April

Day of the Worker 01 May

Holy Spirit Monday Variable

Corpus Christi Variable

Day of Portugal 10 June

Praia da Vitoria Day 11 August

Assumption Day 15 August

Founding of the Republic 05 October

All Saint's Day 01 November

Restoration of Independence 01 December

Immaculate Conception 08 December

*Christmas Day 25 December

*Martin Luther King's Birthday Third Monday in January

*President's Day Third Monday in February

*Memorial Day Last Monday in May

*Independence Day 04 July

*Labor Day First Monday in September

*Columbus Day Second Monday in October

*Veteran's Day 11 November

*Thanksgiving Day Fourth Thursday in November

(*) NOTE: Any of the above holidays falling on a Saturday will be observed on the proceeding Friday. Holidays falling on a

Sunday will be observed on the following Monday.

1.4 SPECIAL CONSIDERATIONS

a. Contractor(s) must use and regard the most current and valid "Lajes

Document 00 73 03 Page 4

Field Facilities Excellence Standards (LFFES)" for construction projects on Lajes Field, Azores. A copy of this standard will be provided to the contractor(s) by the CO upon request by each contractor. All project staging areas, construction sites, and storage areas shall be securely fenced around the entire perimeter of the job site. Fencing shall be completely secured at top and bottom to prevent pedestrian access. Fences shall be screened with opaque screening material to prevent visibility of the fenced area (min 2 m in height) in areas where material storage, contractor work trailers, trash container and any debris that maybe collected as result of construction. Fences and screens shall be adequately staked and/or anchored to prevent blowing over during high wind conditions. Submit photos or samples of the screening material for approval prior to installation.

b. The contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The contractor shall only remove trees when specifically authorized by 65 CES

Environmental Management function to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound. The contractor shall return all areas disturbed during construction to its original condition.

c. The contractor shall request approval for laydown area and placing an office trailer at any project location. Any office trailer shall be no more than 10' x 32' in size, provided with a skirt on all sides, in like new condition, and painted Cream Beige or an equivalent color of similar tone approved by CO, if it is not obscured and hidden by the opaque fencing material. Office trailers in need of painting and / or repairs or, that are in an unsightly condition will not be allowed at the project site. A nameplate shall be displayed on the exterior of all trailers which lists the name of the contractor's company, contractor's point(s) of contact (POC) and telephone number where he/she can be reached, contract number, and title, and the date trailer was placed at the job site.

d. All contractor employees shall obey all traffic laws on installation.

The contractor shall park all vehicles only in legally designated locations, or within the fence line of the construction site.

e. The contractor shall perform normal housekeeping functions inside and outside contractor job sites. Such functions include grounds maintenance, sweeping, mopping, dusting, disposal of accumulated waste materials and rubbish and other operations necessary to present a neat appearance at all times. All rubbish and waste materials shall be removed daily and shall be placed in contractor furnished containers.

During construction, the contractor shall maintain all areas in a neat and orderly manner. The contractor shall clean the construction site and/or structure of all construction trash, trash generated by employees, debris, demolished building materials, combustible waste material, and/or dust daily or more frequently as necessary for safe operations. During the laying of asphalt roads, streets and/or parking

Document 00 73 03 Page 5 surfaces, areas soiled by residual asphalt shall be cleaned daily. The contractor shall treat with lime entrances and exits to asphalt work site at their own expense. The contractor shall ensure all light or moderate weight debris at the construction site is properly secured in waste receptacles so that it does not blow to another area or onto the airfield. At the end of each project all equipment, rubble and rubbish shall be completely removed from the base by the contractor, leaving the area in a safe, clean and orderly manner to the satisfaction of the

CO.

f. Trucks loaded with loose material that can create a dust, debris or falling hazard shall be secured and covered. Fasten a suitable cover, such as tarpaulin, over the load before his/her vehicles and such spillage shall be cleaned up immediately. For the duration of entering surrounding streets. The contractor is solely responsible for spillage from this contract and on a daily basis, the contractor shall remove from all base roads and/or streets asphalt, mud, soil, rocks, trash, and debris that result from their construction business on the particular day affected. In the case of asphalt, roads will be cleaned operation on base. All roads and/or streets affected shall be cleaned before close of and/or treated with lime immediately.

g. Grassy areas disturbed by any type of construction work including storage, equipment staging, and material delivery areas shall be sodded or seeded as required on each delivery order. Contractor shall be responsible for the successful growth and maintenance of all new grass areas under this contract for a period of thirty (30) calendar days, or three mowings, after final acceptance of the work. All grass, shrubbery, and ornamental plants fenced by the construction site shall be maintained to base standards by the contractor.

h. All contractor owned items such as, but not limited to, stakes, traffic/safety cones, barriers, warning tape, erosion control fences that are erected during construction, shall be removed entirely after completion of project and prior to Government acceptance of the project site. The contractor, at his own expense, shall return to the site to remove any items left at or near the project site after this time period.

i. The contractor shall coordinate the exact location of each item of work with the inspector, such as drainage systems, drop inlets, repairs, and so forth. Once a week, the contractor shall layout and stake the proposed work in the field, and then review the layout with the inspector, who shall make recommendations as to adjustments needed.

Prior to doing any work, the contractor shall receive approval from the inspector, who will coordinate with the CO, engineer, and environmental flight as required.

1.5 CONDUCT OF CONTRACTOR PERSONNEL

The Contractor shall report to the Contracting Officer, immediately upon receipt or discovery of any information, whether or not verified, relating to physical security incidents, misconduct, crimes, and misdemeanors, including but not limited to murder, arson, larceny of any weapon, ammunition, or explosives, larceny of other property, robbery, burglary, narcotics and dangerous drugs, destruction of Government property, fraud, malfeasance, sabotage, subversions, disaffections, treasons, or espionage.

The Contractor shall recognize and comply with the rules and regulations

Document 00 73 03 Page 6 promulgated by the foreign country where the work is performed to the extent required by pertinent international agreements.

1.6 TURN-IN OF U.S. GOVERNMENT-OWNED MATERIAL AND EQUIPMENT

Property, material, or equipment removed during the course of repairs, alterations, or renovation of any building or other structure remains the property of the U.S. Government and shall be disposed of as follows:

a. Material other than scrap shall be turned over to the Government.

b. The Contracting Officer will designate the time and place and prepare the necessary forms for receiving the materials.

c. The items designated as scrap by the Contracting Officer shall be disposed of as directed.

1.7 INVESTIGATION OF DAMAGE OR INJURY

The U.S. Government will have the right to conduct an investigation, or participate in the Contractor's investigation, of any damage or injury to

U.S. Government property, equipment, or personnel.

1.8 PROCESSING OF CONTRACTOR'S PERSONNEL AND PROPERTY

The Contractor shall process Contractor personnel and property through the

Contracting Officer prior to commencement and at the completion of work under this contract. This processing shall include such things as registering and deregistering vehicles, arranging for the issuance and turn-in of identification and passes, and clearing liabilities incurred such as clubs, billeting, and loans.

1.9 VISAS--DIPLOMATIC CLEARANCES

The Contractor shall ensure that his employees obtain the required diplomatic clearances (visas) of sufficient duration to cover the performance period of the contract. (Sixty-day visitor visas are available at Portuguese Immigration at Lajes Field.)

1.10 SPECIAL REQUIREMENTS FOR OUTDOOR SIGNS

In accordance with USFORAZINST 5710.2D outdoor signs displayed on local military facilities are mandatory to be in both Portuguese and English languages. Identical size lettering shall be used for both languages, with

Portuguese on top. The same requirement applies to project signs and safety and warning signs as used by the Contractor.

1.11 WRITTEN CORRESPONDENCE

Written correspondence from the Contractor to the Contracting Officer shall be in English language, including but not limited to Contractor's invoice, Contractor's Monthly Estimate for Voucher, Contractor's schedules, samples and submittals, reports, and as-built drawing markups.

1.12 PORTUGUESE EQUIVALENT

Document 00 73 03 Page 7

Where equipment, materials, or installations are to be in accordance with

American standards, the equivalent Portuguese standard may be used subject to the approval of the Contracting Officer. The Contractor shall be responsible for proving the equivalency of the Portuguese standard.

1.13 SECURITY REQUIREMENTS

a. The contractor shall comply with security regulations imposed by the

Installation Commander and/or the agency occupying the space where the work is to be performed, including adhering to, or, obtaining any security clearances.

b. Closure of Openings: The contractor shall close every fence opening resulting from work in order to prevent outside intrusion at the end of each workday. The Closure(s) shall remain in place when contractor is not actively engaged in working on the site(s), including each and every day, night, weekends, and holidays, to reduce wind and weather intrusion. The closure(s) shall be constructed of mesh wire anchored in place to stud framing, if necessary, or similar construction as approved by a government representative through the CO.

c. Contractor Access to Air Force Installations: The contractor shall obtain temporary installation passes for all contractor/subcontractor personnel who visit or perform work on the Air Force Installations cited in the contract. The contractor shall obtain passes through the

65th Contracting Flight. Contractor personnel are required to wear or prominently display contractor furnished badges while visiting or performing work on the installation.

d. Work Performed in Secured Areas: Projects in secured areas may require a local agency check of contractor personnel and all sub-contractors prior to commencement of work. If a check is required, the contractor should allocate time in the work schedule to accomplish this check. The contractor shall price work performed in secured areas according to standard work hour rates unless prior approval to use non-standard work hour rates is obtained from the CO.

e. Escort in Restricted Areas: Contractor personnel must be escorted at all times in a controlled/restricted area by a government escort.

Escorts for secured areas will be scheduled by the contractor at least ten (10) calendar days prior to starting work. The government will provide an escort as quickly as possible, but the contractor should expect delays due to the sensitive nature of secured areas.

f. Unauthorized Reconnaissance: The contractor shall inform all personnel working under his/her jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside the immediate work area (excluding cafeterias and rest rooms near the work site, direct haul and access routes, contracting and points of supply and storage) is strictly prohibited. Circulation of the above personnel shall be limited to official business only. Persons engaged in unauthorized reconnaissance of other contractor or government activity will be referred to the CO for disposition. Infractions involving possible compromise of national security will be turned over to the

Office of Special Investigation (OSI) for disposition.

Document 00 73 03 Page 8

1.14 CONSTRUCTION SITE MAINTENANCE

a. The contractor shall maintain each site in a neat and orderly manner.

All supplies and equipment on the project site shall be stored to preclude mechanical and climatic damage. All grass, weeds, etc. shall be cut as necessary to prevent any fire/safety hazards and shall be no higher than 5 cm at any one time or as directed by the CO. All trash, debris, paper etc. shall be picked up immediately and placed in proper containers.

b. Contractor Parking: The contractor shall inform his employees, suppliers, and subcontractors that their vehicles shall not be parked on grass, in Fire Lanes or other restricted areas, parking spaces marked as "Handicapped" or "Government", at any time. In addition, vehicles may not be driven over grass surfaces, unless indicated during a site visit or pre-performance conference. Any damage done to lawns, shrubs, sidewalks etc. shall be repaired or replaced by the contractor at no additional cost to the government.

c. Trucking: Loose debris on trucks leaving the site shall be loaded in a manner that will prevent dropping of materials on streets and conform to local ordinances and laws. Fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets. The contractor shall be responsible for immediately cleaning up any materials that fall from trucks.

d. Fencing of Construction Site: Fences will be used to isolate construction sites as per instructions by the CO and per recommendations of the Lajes Facility Excellence Standards.

e. Barricades

(1) The contractor shall barricade access to all construction sites.

Barricading shall be used to isolate areas from access. The barricades shall be maintained in good condition, and be installed such that people approaching from the predominant direction can clearly read the warning. Barricades on streets shall have battery powered flashers for night use. Construction fencing shall be used to isolate exterior areas from pedestrian access, and shall be maintained in good condition. Cones shall only be used to temporarily block pedestrian traffic. Extended pedestrian blockages or road traffic shall use rigid barrels/barricades. All barricades, barrels, cones, etc., are included in the contractor's supplied equipment/supplies and therefore shall not be a direct cost to any contract unless the CO deems the individual contract requirements so extensive as to warrant payment.

(2) All projects involving excavation shall be secured with flashing lights on all sides and have construction fencing completely surrounding the site at a minimum of five (5) feet from the hole.

1.15 DRAWING REQUIREMENTS

a. Existing Condition Drawings and As-built Drawings (including utilities):

(1) Existing condition drawings showing existing underground utilities are available upon request. The contractor shall avail himself of

Document 00 73 03 Page 9 the drawings. Any utility line shown on the record drawings (or made known to the contractor) and damaged during construction work shall be repaired immediately by the contractor at no additional cost to the government.

(2) The government does not guarantee the accuracy or adequacy of existing record drawings. It is the contractor's responsibility to verify all existing conditions prior to starting work.

(3) During the progress of the job, the contractor shall keep a careful record at the job site of all work accomplished from the layouts shown on the drawings. The contractor shall provide documents (drawings or sketches) to describe all of the work accomplished, and enter changes and corrections on contract or record drawings promptly and submit to the CO.

b. As-built Work Element in Progress Schedule:

(1) As-builts shall be in the form of one (1) CD-ROM with all documents and drawings (.pdf/.dwg)_and shall be turned over to the CO within twenty-one (21) calendar days of final inspection.

(2) The as-builts shall be professionally drafted in AutoCAD and the contractor shall use conventional drafting techniques, nomenclature, symbols, lettering, noting, and dimensioning.

Resolution of reproducible as-builts shall be legible.

(3) Computer-Aided Design and Drafting (CADD) drawings shall comply with the most current version of Department of Defense (DOD)

Technical Report arcGIS.

(4) The as-built drawings shall indicate, in addition to all changes and corrections, the actual as-built condition. In order that the location of sub-surface utility lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, utility record drawings shall show by offset dimensions to two permanently fixed surfaced features, the end of each run including each change in direction. Valve, splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.

1.16 PERMITS

a. Welding Permit: No welding shall be started without first obtaining a permit issued by the 65 CES/CEF, Fire Prevention and Emergency Service

Office. Contractor shall request the welding permit not less than five

(5) working days before the welding work starts.

b. Work Clearance Requests:

(1) In order to avoid damaging any underground utilities, such as sewer, water, gas, electrical, telephone, cable TV, and possibly others, the contractor must obtain digging permits. The contractor shall process, obtain and maintain a Work Clearance Request (AF

Form 103) required, prior to beginning construction.

Document 00 73 03 Page 10

(2) The contractor is responsible for obtaining a Work Clearance

Request for each contract right after Notice to Proceed (NTP) is issued. The contractor must fill out the request form (AF Form

103) with pertinent information and attach a plan showing the location of the respective work (contract drawings with areas highlighted is acceptable).

(3) Contractor shall submit to CO one (1) signed copy of the form

(AF Form 103).

(4) Also, as a part of the work request process, the contractor shall be required to mark all locations of excavation work on site with white spray paint or stakes with flagging. Existing utilities will be marked in the field by the respective agency in proposed construction areas. The contractor is required to maintain these markings (or reference points) so that the pertinent agency does not have to duplicate their work.

1.17 PROGRESS REPORTS

The reports mentioned in FAR clause 52.236-15, "Schedules for Construction

Contracts" shall be accomplished on AF Form 3064, Contracts Progress

Schedule, and AF Form 3065, Contract Progress Report.

1.18 MATERIAL SUBMITTAL AND APPROVAL FORM

In accordance with FAR clause 52.236-5 "Materials and Workmanship," all material requiring approval shall be submitted by the contractor to the CO for approval on an AF Form 3000 within ten (10) calendar days after NTP (or as other-wise established by the CO).

1.19 COORDINATION WITH GOVERNMENT ACTIVITIES

a. If it becomes necessary to interrupt work activities due to construction, permission to do so must be requested in writing to the

CO twenty-one (21) calendar days in advance.

b. The contractor shall request street closings, both partial and/or total, twenty-one (21) calendar days prior to the closing.

c. Work in conjunction with this contract which requires utility outages which will affect (as determined by the CO) normal activities in the building, construction area, or other work areas, shall be performed by the contractor at a time other than regular work periods of the organization occupying the facility or area.

d. Temporary construction for facilities used by the contractor for preventing interruption of normal work activity or loss of utilities shall be subject to approval of 65 CES/CEN through the CO.

e. Utility Outages:

(1) The contractor shall coordinate all utility outages with the using agency through the CO or his representative prior to the outage.

Services shall not be interrupted until receipt of approval of proposed hours and dates from the 65 CES/CEN through the CO. All work shall be arranged to ensure that the outage will be of

Document 00 73 03 Page 11 minimum duration. The contractor will provide notice to the CO, in writing, not less than twenty-one (21) working calendar days prior to the required outage or as determined by the CO. No response to the outage/interruption request shall be considered as disapproval for the outage/interruption. In the event a scheduled utility outage is canceled by the Government, notification shall be given to the contractor at least 24 hours in advance of the time for the outage to start and the contractor waives his right to any claim for equitable adjustment or increased cost of performance under this contract as a result of this cancellation. Once a utility outage is arranged and work begun, work must go on continuously until the affected utilities are restored to the affected facility.

(2) The contractor's Interruption and Outage Requests shall include specific location of interruption/outage, hours and dates of interruption/outage, services affected by the interruption/outage.

(3) Water Mains. Operation of valves on water mains will be by government personnel only. Where shut-off of water lines interrupts service to fire hydrants or fire sprinkler systems, the contractor shall contact the CO and arrange his operations to have sufficient personnel available to restore service without delay in the event of an emergency as determined by the 65 CES/CEF Fire

Prevention Office.

(4) Fire Protection System. Where interruption of electrical power affects a fire protection system service, the contractor shall notify the CO twenty-one (21) working calendar days before making such interruptions and shall restore service prior to leaving the job site each day.

1.20 REMOVAL AND REPLACEMENT RESPONSIBILITY

The contractor shall be responsible for the replacement or repair of all existing finished surfaces, utilities, equipment, landscapes, grounds, and structures or parts thereof that he/she has damaged, removed, or cut into in order to perform work specified. Removed items to be reinstalled shall be stored by the contractor, free from damage, until reinstalled at no additional cost to the Government.

1.21 WARRANTY SERVICE REQUIREMENTS

a. The contractor shall furnish, as a minimum, one (1) primary name and telephone number of an individual on his/her management staff, available twenty four (24) hours per day, seven (7) days per week, for the life of this contract to respond to warranty situations. In the event the primary individual is unavailable, the contractor shall furnish an alternate individual and shall notify the CO of the alternate individual's telephone number.

b. Following notification by the CO or, the COR, the contractor shall respond to a warranty service requirement identified by the CO, or the

COR, in accordance with the "Warranty Service Priority List" of this program. This list prioritizes warranty work into the following categories:

Emergency: Perform on site inspection to evaluate situation, Document 00 73 03 Page 12 determine course of action, initiate work within 2 hours and work continuously to completion.

Urgent: Perform on site inspection to evaluate situation, determine course of action, initiate work within 24 hours and work continuously to completion.

Routine: All other work to be initiated within 48 hours and work continuously to completion.

c. The "Warranty Service Priority List" is as follows:

Emergency: Emergency deemed as any damage on the active runway.

Urgent: All repairs on the airfield taxiways and/or parking aprons.

Routine: All other areas.

d. Should parts be required to complete the work and the parts are not immediately available the contractor shall have a maximum of 12 hours after arrival at the job site to provide the CO with firm, written proposals for emergency alternatives and temporary repairs for government participation with the contractor to provide emergency relief until the required parts are available on site for the contractor to perform permanent warranty repair. The contractor's proposals shall include a firm date and time that the required parts shall be available on site to complete the permanent warranty repair.

The CO will evaluate the proposed alternatives and select the alternative considered to be in the best interest of the government to reduce the impact of the emergency condition. Alternatives considered by the CO will include the alternative for the contractor to "do nothing" while waiting until the required parts are available to perform permanent warranty repair. Negotiating a proposal, which will require government participation and the expenditure of government funds, shall constitute a separate procurement action by the government.

1.22 CONTRACTOR PERSONNEL

Contract Manager: The contractor shall provide a contract manager and at least one alternate. The contract manager and alternate shall have full authority to act for the contractor in all contractual matters. The contract manager or alternate shall be available during standard work hours. The contract manager and alternate shall be able to read, speak and write English fluently.

1.23 GOVERNMENT PERSONNEL

Personnel from 65 CES/CEN are designated as the representative (COR) of the

CO for the purpose of technical surveillance of workmanship and inspection of materials for work being performed under this contract. This designation in no way authorizes anyone other than the CO to commit the Government to changes in the terms of the contract. No oral statement of any person and no written statement of anyone other than the CO shall modify or other-wise affect the terms or meaning of this contract. All requests by the contractor for interpretations, modifications, or changes shall be made in writing to the CO. The Government shall not be liable for any costs incurred by the government or any action taken by the contractor, which are

Document 00 73 03 Page 13 not in conformance with this statement.

1.24 E-MAIL CAPABILITY

The contractor shall have e-mail capability, via Internet or other means.

This will allow the CO and 65 CES/CEN to communicate with contractor via e-mail.

1.25 GOVERNMENT LIABILITY

The Government shall not be liable for any loss or damage to the contractor's property, including stock, or for expenses incidental to such loss or damage. The contractor shall file a report with the Base Security

Forces immediately as is practicable to report loss.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Document --

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

Preconstruction Submittals 2 List of Contractor and Subcontractors Personnel; G 3 Safety Plan; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes The preliminary and full cleaning of all existing medium (and above) severity cracks and joints (6 mm or higher) on Apron Fox, i.e.

the area defined in the Government Drawings. The cracks and joints cleaning shall be performed by a hotlance blaster with the capacity of burning weeds and and drying the cracks deep down, at a pressure of 8 bar through a maximum dimention pipe of 6 milimenters (complementary high pressure equipment is also authorized according to Section 32 01 17.61). The work shall also include a high pressurized water cleaning of all the asphalt area of Fox Apron (i.e. the Area defined in the Government Drawings), the removal of all airfield paint markings of this area, to be previously surveyed by the Contractor for re-establishment when resurfacing is done (see Section 32 01 18.71). After Cleaning works are finished, the Contractor shal seal all aforementioned cracks and joints, and apply a three component sealant, based on a regenerating emulsion, modified bitumen and water, mixed in a specific equipment/truck (in accordance with section 32 01 13.62) (prime/tack coat trucks are not allowed!) to the entire asphalt surface of Apron Fox (i.e. where designated in the Government Drawings) and re-establish all paint markings as they where (section 32 17

24) and incidental related work.

Aditional details on the work to be performed are included in the appropriate specifications of this Government Statement of Work.

in order to ensure that the friction on the pavement is not reduced, surface friction tests shall be carried out…