Attachment 1 Statement of Work.pdf
PDF 4 MB Posted
- Attached to
- Greenhouse Controls Replacement for USDA ARS in Ames, IA Federal contract opportunity
- Solicitation number
- 1232SA25Q0648
About this file
This document is a Statement of Work (SOW) for the replacement of hot water heating lines, heating units, and controls at Greenhouse 2 (GH2) for the USDA Agricultural Research Service in Ames, Iowa. The project involves replacing the existing pneumatic control system with Conviron Argus Titan control panels, upgrading heating systems, and performing comprehensive modifications to the greenhouse's environmental control infrastructure.
The scope includes base bid and three optional bids: Base Bid involves replacing the pneumatic control system with DDC controls, Option Bid One covers replacement of three Modine unit heaters in the Headhouse and office, Option Bid Two involves replacing Modine unit heaters in all four greenhouse bays, and Option Bid Three includes replacing baseboard heaters in the greenhouse bays. The facility is approximately 9,400 square feet, constructed in 1976, with four 850-square-foot sections. The project requires precise coordination to minimize disruption to ongoing research, with a performance period of 75 days from Notice to Proceed, and potential additional 60 days for Option 01. The contractor must coordinate closely with USDA staff, protect sensitive research equipment, and ensure minimal impact on facility operations.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 4 ARS Form 372 Request for Payment.pdf | ||
| Attachment 2 Wage Determination IA20250074 08082025.pdf | ||
| Attachment 3 ARS Form 371 Construction Progress and Payment Schedule.pdf | ||
| SF1442_RFQ_1232SA25Q0648.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
Green House 2 (GH2): Hot Water Heating Lines/Heating Units/Controls Replacement Corn Insects and Corn Genetics Research Unit (CICGRU) USDA-ARS, Ames, IA
DATE: May 09, 2025
GH2: Hot Water Heating Lines/Heating Units/Controls Replacement CICGRU USDA-ARS, Ames, IA
TABLE OF CONTENTS
SOW Description
Project Specifications:
Division 01 General Requirements
01 32 00 Project Progress Documentation 01 33 00 Submittal Procedures 01 33 16 Design After Award 01 35 26 Accident Prevention Plans 01 42 00 References 01 50 00 Temporary Facilities and Controls 01 73 00 Execution 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data
Division 23 Mechanical Requirements
23 05 00 Common Work Results for HVAC 23 05 19 Meters and Gages for HVAC 23 05 23 General Duty Valves for HVAC Piping 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing, Adjusting, and Balancing (TAB) for HVAC – General 23 21 13 Hydronic Piping
Division 26 Electrical Requirements
26 05 00 Common Work Results for Electrical 26 05 19 Low Voltage Power Conductors 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 53 Identification for Electrical Systems 26 28 16 Enclosed Switches 26 29 13 Enclosed Controllers
Photographs//Drawings
General Notes and Requirements
Attachments Material Approval Submittal form Schedule of Material Submittals Recently Replaced Component Form AD-107 form
END OF TABLE OF CONTENTS
Scope of Work Description GH2: Hot Water Heating Lines/Heating Units/Controls
Scope of Work Description:
1. Project Location: Greenhouse 2 (GH2) USDA-ARS-Corn Insects and Corn Genetics Research Unit (CICGRU) 806 Wallace Road Ames, IA 50011
2. Point of Contact at Location: Primary:
Michelle Graham (515)-294-3626 (office) michelle.graham@usda.gov
3. MWA COR: Patrick Quance (515)-203-1447 patrick.quance@usda.gov
The scope of the project consists of the Base Bid to replace the existing pneumatic control system in the Greenhouse and Headhouse with Conviron Argus Titan control panels. There are up to three Argus Titan control panels that will be re-used as the basis of this upgrade. Additional Argus system components will need to be added (Access Point, software, weather station, additional I/O devices as needed). The newly installed Argus Titan system shall control the side vents, roof vents (north and south), radiant heat, hanging unit heaters, exhaust fans and lighting for each bay individually. Each bay shall have separate temperature control. Each bay will modulate the temperature and venting based on the weather station inputs. Ridge vents are operated independently in a north or south configuration. Side vent is independent and operates by weather station inputs. Exhaust fans shall operate in a staged/lead lag/both operation depending on inputs. Lighting in the bays shall be 3 circuits. The Argus system shall also control the radiant and unit heaters in the headhouse, office and the headhouse exhaust fan using local thermostats. Where possible all I/O devices shall have manual on/off/auto, as the existing Argus panels demonstrate. In addition, all control valves and actuators that are pneumatically controlled will be replaced with DDC controlled valves and actuators. Pneumatic thermostats shall be replaced with DDC thermostats. Each bay of the greenhouse has (1) side vent, (1) south facing roof vent, (1) north facing roof vent which will need DDC controllers. The existing pneumatic control system shall be demolished in its entirety. Current heating controls are provided by Johnson Controls, lighting controls by Lutron and venting by Micro-grow. Some of the existing conduits may be used.
The new Argus control system shall be fully programmed and include all wiring and conduit, actuators, valves, thermostats, lighting interface to provide a complete and useable system. The re-used I/O devices shall be relabeled to indicate their new function. The contractor shall perform a Test & Balance evaluation to ensure the hot water heating system meets performance standards, the lighting and ventilation systems operate as intended.
Option Bid One (01) will the replacement of the three Modine unit heaters in the Headhouse as well as the office and east and west cabinet heaters.
mailto:michelle.graham@usda.gov mailto:patrick.quance@usda.gov
Option Bid Two (02) will be the replacement of the Modine unit heaters in all four greenhouse bays.
Option Bid Three (03) will be the replacement of the baseboard heaters in the greenhouse bays.
The contractor is highly encouraged to visit the site and validate all existing systems and components.
There are four bays. Two bays have six (6) each 96-inch radiant heaters and two bays have six (6) each 72-inch radiant heaters. The radiant heaters were manufactured by Sterling Radiator Company Inc. They are still in business and their radiant heaters provide the basis of design for the replacement radiant heaters.
Each of the four bays have two (2) IS 280 Modine Heating Units. Modine is still in business and their unit provides the basis of design for replacement of the existing heating units.
Existing valves, actuators, heating units, radiant heaters, pipes and insulation provide the basis of design for this work.
• The facility is approximately 9,400sf and is located on the campus of Iowa
State University. The Greenhouse section is 3,400sf which has been sub-divided into four sections of 850sf each and is identified as GH 16, 17, 18 and 19. The headhouse and connecting link between the structures comprises the remaining 6,000sf. The building was constructed in 1976, and was designed by Brooks Borg and Skiles of Des Moines, Iowa. The headhouse is a pre-engineered metal building with metal siding and low height brick wainscot on the west façade, an alley between the headhouse and greenhouse is of similar construction. The greenhouse is an aluminum prefabricated unit sitting on reinforced CMU knee walls.
• The specified project activities and components shall be performed in a neat, workmanlike manner and shall be sequenced to minimize the downtime of the greenhouse. All new materials for project completion shall be on-site and ready for installation before proceeding with any demolition of the existing greenhouse steam heating system. Once “on-site” work commences, the work shall be completed without interruption to avoid jeopardizing ongoing research and impacting ongoing plant growth.
• The Contractor shall coordinate thoroughly with the Owner such that plants, research equipment, etc. are relocated in a timely manner. Relocation of plants, research equipment, etc. will be by Owner.
• Dimensions shown on the Drawings shall be considered approximate and for bidding purposes only. The Contractor shall confirm all existing conditions and dimensions prior to proceeding with any project activities.
4. Interested parties are strongly encouraged to visit the site of the proposed work and review the existing conditions there relating to construction and labor, and to be fully informed as to the facilities involved, and the difficulties and restrictions that may affect the performance of the Contract. Failure to visit the site will not disqualify those submitting a proposal. However, change order requests for items that could have been reasonably ascertainable from a site visit (and included in a proposal) will be reviewed by the CO and evaluated accordingly.
5. After project award, the Contractor shall confirm all existing conditions and dimensions prior to proceeding with any project activities and identify all existing conditions that may impact the work and alert the CO and COR immediately if conditions are discovered that differ from the SOW. Contractor shall point out discrepancies between work identified in this SOW and actual field-verified conditions, if they exist, prior to performing work.
6. Period of performance shall be as indicated in the Contract Documents and begins after Notice to Proceed is issued by CO. The period of performance is 75 days from Notice to Proceed (NTP) for the Base Bid and 60 additional days if Option 01 is awarded.
7. Basis-of-design products are indicated in this SOW to convey a specified standard of quality and salient characteristics desired but are not to be considered a single-source specification. Contractor-proposed equals will be considered.
• The Contractor must compare and validate that quality and salient characteristics are equal and approve the proposed equal products prior to submission for Government review and approval. Additional work required to incorporate Contractor-proposed equals shall be at the Contractor’s expense.
• Owner will review all Contractor-proposed equal equipment, materials, manufacturers, or installation. It shall be the Contractor’s burden to furnish all documentation and / or samples to show equality with specified items.
Owner’s decision on equality is final. Manufacturers / products that are submitted as “Approved Equal” are reviewed during the shop drawing process, not during bidding.
8. Submittals including product data and shop drawings shall be submitted as indicated in the Project Specifications. Items, that submittals shall be provided on, are indicated in the Project Specifications and Drawings, also see “Schedule of Material Submittals”. Submittals shall be reviewed by the Government for general conformance with the Contract Documents. Markings for comments and approval of the submittals by USDA shall not be construed as releasing the Contractor from compliance with the specified requirements.
• Use ARS submittal/transmittal form included with this SOW for each submittal.
• Submittals shall be marked, by the Contractor, to clearly note the model, type, size, performance characteristics of the material / product being proposed for the Government requirement.
• All submittals shall be distributed to and reviewed by the Government prior to commencing work at the site. Purchase of materials prior to submittal approvals are at the Contractor’s risk.
• See Project Specifications for requirements on documenting Contractor’s effort in diverting waste to recycle.
9. See Project Specifications for requirements on project progress documentation including, but not limited to: daily reports, project schedule(s), etc.
• Daily reports documenting project activities shall include workers present, weather conditions, differing site conditions encountered, etc. Photographs of project activities and conditions shall be taken daily and shall be submitted with daily reports. Daily reports shall be submitted on daily basis to project personnel as indicated in Project Specifications.
10. The Contractor shall furnish all labor, materials, equipment, supplies, transportation, utilities, supervision, *safety equipment, and incidentals for all elements of the work to provide a complete and properly functioning installation in accordance with this Statement of Work. The installation shall be ready for use by Final Completion date.
* Note: Contractor is solely responsible for safety measures and conformance to applicable requirements in accordance with FAR clauses referenced in Solicitation package.
• Contractor shall provide all means and methods to protect the facility and its installations from all project activities, including protecting the facility from environmental elements as the improvements are completed.
11. Contractor shall coordinate all work activities with the Owner prior to beginning any work. All work shall be scheduled in a manner such that ongoing research is not jeopardized, and facility’s ongoing day-to day operations are not affected negatively, including air quality.
• Contractor shall coordinate access to all areas with the Location.
• Contractor shall verify all parking, security, and health requirements with the
USDA staff.
• Coordinate with location for laydown and staging areas.
12. Applicable Codes and Standards:
• Current State of Iowa Building Codes.
• All current Ames, IA local codes.
• Most recent International Building Codes.
• NFPA/NEC
• ANSI/ASME SEC 9 - Welding and Brazing Qualifications.
• ANSI/ASME SEC B31.9 - Building Services Piping.
• ANSI/AWS D10.12 – Guide for Welding Mild Steel Pipe.
• ASTM A234 – Pipe Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and
High Temperature Service.
• ASME A112.4.14 – Manually or Automatically Operated Valves for use in Plumbing
Systems
• ANSI CSA B125.3 – 2022 – Plumbing Fittings
• International Mechanical Code
• ASME B 31.1 "Power Piping”: for materials, products, and installation.
• UFC 3-410-02 Direct Digital Control for HVAC and Other Building Control Systems, with
Change 2
• ISO 16484-5 – Building Automation and Control Systems (BACs).
• ANSI/ASHRAE 135 – Building Automation Control Network (BACnet).
• ASTM B 32 Solder Metal.
• ASTM B 75 Seamless Copper Tube.
• ASTM B 88 Seamless Copper Water Tube.
• MSS-SP-58 Pipe Hangers and Supports - Materials, Design and Manufacture.
• MSS-SP-69 Pipe Hangers and Supports - Selection and Application.
• MSS-SP-89 Pipe Hangers and Supports - Fabrication and Installation Practices.
Project Specifications GH2: Controls Hot Water Heating Lines/Heating Units
01 32 00 - 1 Project Progress Documentation
DIVISION 01 – GENERAL REQUIREMENTS
01 32 00 – PROJECT PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract including other Division 01 Specification
Sections apply to this Section.
1.2
SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of project during performance of the Work, including the following:
1. Contractor's project schedule.
2. Daily project reports.
B. Related Requirements:
1. Division 01 Section "Submittal Procedures" for submitting schedules and reports.
1.3
INFORMATIONAL SUBMITTALS
A. Contractor's project Schedule: Submit size required to display entire schedule for entire project period. Submit via email.
1. Submit a working electronic copy of schedule in “pdf” format and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.
B. Project Schedule Updating Reports: Submit upon request by Owner.
C. Daily Project Reports: Submit at weekly intervals.
1.4
QUALITY ASSURANCE
A. Scheduling Qualifications: Contractor shall have the capability of updated project schedule within 24 hours.
B. Contractor’s Project Schedule: The Contractor shall secure time commitments for performing project activities from his subcontractors and suppliers. The Contractor shall prepare a combined project schedule for the entire project. The schedule shall be a comprehensive, integrated, and fully developed.
01 32 00 - 2 Project Progress Documentation
1.5 REPORTS
A. Daily Project Reports: Prepare a daily project report recording events at Project site. An electronic copy (pdf format) of the daily reports shall be submitted daily to the COR/EPM. A copy of the daily reports shall be sent weekly to the CO along with certified payrolls (coordinate submission requirements with CO). The daily project report must be dated and signed and should including the following:
1. List of subcontractors.
2. High and low temperatures and general weather conditions.
3. Accidents.
4. Stoppages, delays, shortages, and losses.
5. Meter readings and similar recordings.
6. Orders and requests of authorities having jurisdiction.
7. Services connected and disconnected.
8. Equipment or system tests and startups.
PART 2 - EXECUTION
2.1 CONTRACTOR'S PROJECT SCHEDULE
A. Contractor's Project Schedule Updating: Upon request by Owner, update schedule to reflect actual project progress and activities.
B. Distribution: Distribute copies of approved schedule to CO/COR/EPM.
END OF SECTION 01 32 00
01 33 00 - 1 Submittal Procedures
01 33 00 – SUBMITTAL PROCEDURES
1.1 RELATED DOCUMENTS
Sections, apply to this Section.
B. See “Attachments” section of the SOW for “Material Approved Submittal” form
C. See “Attachments” section of the SOW for “Schedule of Materials Submittals” form.
D. See “Attachments” section of the SOW for “Recently Replaced Component” form.
E. See “Attachments” section of the SOW for “AD-700” form.
1.2 SUMMARY
A. Section includes requirements for the administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.3 DEFINITIONS
A. Submittals: Written and graphic information.
B. Portable Document Format (pdf): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
1.4 SUBMITTALS
A. Submittal Format:
1. Arrange the following information in a tabular format:
a. Name of subcontractor if applicable.
b. Description of the Work covered.
1.5 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of project activities.
01 33 00 - 2 Submittal Procedures
B. Processing Time: Allow time for submittal review, including time for re-submittals. Time for review shall commence on Owner's receipt of submittal. No extension of the Contract Time will be authorized because of failure to permit the processing of submittals, including re- submittals.
1. Initial Review: Allow 15 calendar days for initial review of each submittal.
2. Re-submittal Review: Allow 15 calendar days for review of each re-submittal.
C. Electronic Submittals: All submittals shall be submitted electronically in “pdf” format, via email. Identify and incorporate information in each electronic submittal file as follows:
1. Transmittal Form for Electronic Submittals: Format acceptable to Government, containing the following information:
a. Project name.
b. Date.
c. Name of Contractor.
d. Name of firm or entity that prepared submittal.
e. Names of subcontractor, manufacturer, and supplier.
D. Identify features, accessories and finishes requiring selection by CO/ACO/COR/ EPM.
E. Use for Project: Retain complete approved copies of submittals on Project site. Use only final action submittals that are marked with approval notation from CO/COR/ EPM.
PART 2 - PRODUCTS
2.1 SUBMITTAL PROCEDURES
A. General Submittal Procedure Requirements: Prepare and transmit submittals for material and products proposed for the project.
1. Submit via email with electronic submittal files attached.
2. Manufacturers / products that are submitted as “Approved Equal” are reviewed during the submittal / shop drawing process and not prior to bidding. Contractor shall be responsible for submitting information to show equivalence. Determination by CO/COR/EPM on equivalence is final.
3. Each submittal shall include a completed “Material Approval Submittal” form. See “Attachments” section of the SOW for this form.
B. Include one hard copy of each approved shop drawing in the Operations and Maintenance Manual submitted to the Government during Closeout Procedures.
C. Product Data: Collect information into a single submittal for each element of project and type of product or equipment.
1. Mark each submittal to show which products (manufacturer, model, type, size, options, etc.) are proposed.
01 33 00 - 3 Submittal Procedures
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO/COR/ EPM.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.2 CO/COR ACTION
A. General: CO/COR/EPM will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Submittals: CO/COR/EPM will review each submittal, make marks to indicate corrections or modifications required, and return it. CO/COR/EPM will provide notation on each submittal to indicate the appropriate determination from their review:
1. Reviewed - Approved with No Exceptions Noted.
2. Reviewed - Approved with Notes - Make Corrections Noted
3. Reviewed - Revise and Resubmit.
4. Reviewed - Rejected.
3.3 REQUIRED SHOP DRAWINGS AND PRODUCT DATA
A. See individual specification sections and Drawings.
END OF SECTION 01 33 00
01 33 16 - 1 Submittal Procedures
DIVISION 01 – GENERAL REQUIREMENTS 01
33 16 – Design After Award
1.6 RELATED DOCUMENTS
Sections, apply to this Section.
B. See “Attachments” section of the SOW for “Material Approved Submittal” form
C. See “Attachments” section of the SOW for “Schedule of Materials Submittals” form.
1.7 SUMMARY
Shop Drawings, Product Data, Samples, and other submittals.
1.8 DEFINITIONS
B. Portable Document Format (pdf): An open standard file format licensed by Adobe Systems used
1.9 SUBMITTALS
1. Arrange the following information in a tabular format:
a. Name of subcontractor if applicable.
b. Description of the Work covered.
1.10 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
activities.
01 33 16 - 2 Submittal Procedures
B. Processing Time: Allow time for submittal review, including time for re-submittals. Time for review shall commence on Owner's receipt of submittal. No extension of the Contract Time will be authorized because of failure to permit the processing of submittals, including re- submittals.
1. Initial Review: Allow 15 calendar days for initial review of each submittal.
2. Re-submittal Review: Allow 15 calendar days for review of each re-submittal.
C. Electronic Submittals: All submittals shall be submitted electronically in “pdf” format, via email. Identify and incorporate information in each electronic submittal file as follows:
1. Transmittal Form for Electronic Submittals: Format acceptable to Government, containing the following information:
a. Project name.
b. Date.
c. Name of Contractor.
D. Identify features, accessories and finishes requiring selection by CO/ACO/COR/ EPM.
E. Use for Project: Retain complete approved copies of submittals on Project site. Use only final action submittals that are marked with approval notation from CO/COR/ EPM.
2.2 SUBMITTAL PROCEDURES
products proposed for the project.
1. Submit via email with electronic submittal files attached.
2. Manufacturers / products that are submitted as “Approved Equal” are reviewed during the submittal / shop drawing process and not prior to bidding. Contractor shall be responsible for submitting information to show equivalence. Determination by CO/COR/EPM on equivalence is final.
3. Each submittal shall include a completed “Material Approval Submittal” form. See “Attachments” section of the SOW for this form.
B. Include one hard copy of each approved shop drawing in the Operations and Maintenance Manual submitted to the Government during Closeout Procedures.
C. Product Data: Collect information into a single submittal for each element of project and type of product or equipment.
1. Mark each submittal to show which products (manufacturer, model, type, size, options, etc.) are proposed.
3.4 CONTRACTOR'S REVIEW
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO/COR/ EPM.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.5 CO/COR ACTION
A. General: CO/COR/EPM will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Submittals: CO/COR/EPM will review each submittal, make marks to indicate corrections or modifications required, and return it. CO/COR/EPM will provide notation on each submittal to indicate the appropriate determination from their review:
1. Reviewed - Approved with No Exceptions Noted.
2. Reviewed - Approved with Notes - Make Corrections Noted
3. Reviewed - Revise and Resubmit.
4. Reviewed - Rejected.
3.6 REQUIRED SHOP DRAWINGS AND PRODUCT DATA
END OF SECTION 01 33 16
01 35 26 – Accident Prevention Plan
1.11 RELATED DOCUMENTS
Sections, apply to this Section.
B. See “Attachments” section of the SOW for “Material Approved Submittal” form
C. See “Attachments” section of the SOW for “Schedule of Materials Submittals” form.
1.12 SUMMARY
the Accident Prevention Plan
1.13 DEFINITIONS
B. Portable Document Format (pdf): An open standard file format licensed by Adobe Systems used
1.14 SUBMITTALS
1. Assessment of the safety risks and mitigation strategies during performance of the project.
2. Procedures for emergency response and medical treatment for job-site accidents, and description of how and where these procedures will be communicated to employees and posted for reference.
3. Procedures for reporting injuries to the Owners representatives.
4. Identification of a competent and trained person at the project site to function as the Safety & Health Officer (SSHO) for the Contractor. The Contractor shall provide a copy of the SSHO training qualifications upon request.
5. Identification of the job-site safety references that will be maintained on the site.
6. A description of the job-site daily safety inspections that will be performed, how the inspections will be recorded, and how deficiencies will be addressed and corrective actions documented.
7. A plan for conducting regular job-site safety meetings with topics relative to this project.
8. The Contractor's Confined Space Entry, Hot Work, and Lockout/Tagout Plans, or confirmation all work will be done in accordance with the minimum requirements identified in this Specification Section.
9. A Severe Storm Action Plan
10. The Contractor and/or subcontractor employees who will be making connections with existing piping and electrical sources will apply a lock-out/tag-out (LOTO) process to control dangerous energy sources. Contractor/subcontractors shall have a LOTO program established and use Contractor LOTO locks, tags, and procedures. The Contractor/subcontractor shall review their LOTO program with the Location Coordinator (LC) to coordinate LOTO programs before implementing LOTO.
11. The Contractor/subcontractor shall have a written plan in place to manage the safety and fire hazards associated with hot work. The Plan shall include a fire watch and all other requirements in accordance with OSHA. The Contractor/subcontractor shall maintain written records of hot work until final acceptance of the project and shall provide copies to the Owner's Representatives at any time requested.
1.15 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
activities.
B. Processing Time: Allow time for submittal review, including time for re-submittals. Time for review shall commence on Owner's receipt of submittal. No extension of the Contract Time will be authorized because of failure to permit the processing of submittals, including re- submittals.
1. Initial Review: Allow 15 calendar days for initial review of each submittal.
2. Re-submittal Review: Allow 15 calendar days for review of each re-submittal.
C. Electronic Submittals: All submittals shall be submitted electronically in “pdf” format, via email. Identify and incorporate information in each electronic submittal file as follows:
1. Transmittal Form for Electronic Submittals: Format acceptable to Government, containing the following information:
a. Project name.
b. Date.
c. Name of Contractor.
D. Use for Project: Retain complete approved copies of submittals on Project site. Use only final action submittals that are marked with approval notation from CO/COR/ EPM.
2.3 SUBMITTAL PROCEDURES
products proposed for the project.
1. Submit via email with electronic submittal files attached.
2. Manufacturers / products that are submitted as “Approved Equal” are reviewed during the submittal / shop drawing process and not prior to bidding. Contractor shall be responsible for submitting information to show equivalence. Determination by CO/COR/EPM on equivalence is final.
3. Each submittal shall include a completed “Material Approval Submittal” form. See “Attachments” section of the SOW for this form.
B. Include one hard copy of each approved shop drawing in the Operations and Maintenance Manual submitted to the Government during Closeout Procedures.
PART 3 - EXECUTION
3.7 CONTRACTOR'S REVIEW
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO/COR/ EPM.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.8 CO/COR ACTION
A. General: CO/COR/EPM will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Submittals: CO/COR/EPM will review each submittal, make marks to indicate corrections or modifications required, and return it. CO/COR/EPM will provide notation on each submittal to indicate the appropriate determination from their review:
1. Reviewed - Approved with No Exceptions Noted.
2. Reviewed - Approved with Notes - Make Corrections Noted
3. Reviewed - Revise and Resubmit.
4. Reviewed - Rejected.
3.9 REQUIRED SHOP DRAWINGS AND PRODUCT DATA
END OF SECTION 01 35 26
01 42 00 – REFERENCES
1.1 DEFINITIONS
A. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated."
B. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the project’s industry that control performance of the Work.
1.2 INDUSTRY STANDARDS
A. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated.
B. Copies of Standards: Each entity engaged in activities on Project should be familiar with industry standards applicable to its activity. Copies of applicable standards are not bound with the Contract Documents.
1. Where copies of standards are needed to perform a required activity, obtain copies directly from publication source.
1.3 ABBREVIATIONS AND ACRONYMS
A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities indicated in Thomson Gale's "Encyclopedia of Associations" or in Columbia Books' "National Trade & Professional Associations of the U.S."
B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract
Documents, they shall mean the recognized name of the entities in the following list. Names are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.
IAPMO International Association of Plumbing and Mechanical Officials
ICC International Code Council www.iccsafe.org
ICC-ES ICC Evaluation Service, Inc.
http://www.iccsafe.org/
C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.
DOE Department of Energy
EPA Environmental Protection Agency
FCC Federal Communications Commission
FDA Food and Drug Administration
LBL Lawrence Berkeley National Laboratory
NIST National Institute of Standards and Technology
OSHA Occupational Safety & Health Administration
PHS Office of Public Health and Science
SD State Department
USDA Department of Agriculture
USPS Postal Service
D. Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations in the following list. Names are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.
ADAAG American with Disabilities Act Accessibility Guidelines Americans with Disabilities Act (ADA) Architectural Barriers Act (ABA) Accessibility Guidelines for Buildings and Facilities
CFR Code of Federal Regulations
FED-STD Federal Standard
FTMS Federal Test Method Standard
UFAS Uniform Federal Accessibility Standards Available from Access Board
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 42 00
01 50 00 - 1 Temporary Facilities and Controls
01 50 00 – Temporary Facilities and Controls
1.1 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
1.2 USE CHARGES
A. Water Service from Existing System: Water from Government's existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for project operations.
B. Electric Power Service from Existing System: Electric power from Government's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for project operations.
1.3 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Contractor to obtain required certifications and permits.
C. Accessible Temporary Egress: Comply with applicable provisions in ICC/ANSI A117.1 and OSHA regulations and standards.
1.4 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Contractor to assume responsibility for operation, maintenance, and protection of each permanent service during its use.
2.1 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
01 50 00 - 2 Temporary Facilities and Controls
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Connect to existing service.
1. Arrange with COR / COTR for time when service can be interrupted, if necessary, to make connections for temporary facilities.
B. Water Service: Connect to Government's existing water service facilities.
C. Sanitary Facilities: Contractor shall furnish toilets, wash facilities, and drinking water at the facility for use of project personnel.
D. Telephone Service: Provide superintendent with cellular telephone for use.
E. Electric Power Service: Connect to Government's existing electric power service.
F. While Contractor is using existing installations for temporary facility purposes; Contractor shall maintain existing installations in condition acceptable to the Government. At Substantial Completion, Contractor shall restore existing installations used for temporary facilities to their original, properly operating condition prior to its initial use.
3.3 SUPPORT FACILITIES INSTALLATION
A. Maintain access for fire-fighting equipment and access to fire hydrants.
B. Parking: Use designated areas of Government's existing parking areas for project personnel.
C. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from project operations. Comply with requirements of authorities having jurisdiction.
D. Waste Disposal: Contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of project waste diverted to recycle. The Contractor shall submit diversion documentation as part of project closeout. If no project waste is diverted to recycle, the Contractor shall submit a letter stating this and why diversion was not practical.
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other installations and improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.
01 50 00 - 3 Temporary Facilities and Controls
B. Environmental Protection: Provide protection, operate temporary facilities, and conduct project activities as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
C. Barricades, Warning Signs, and Lights: Provide and maintain all safeguards in accordance with OSHA regulations and standards and to provide adequate protection to pedestrians and building occupants. Comply with OSHA requirements for erecting structurally adequate barricades, including warning signs and lighting.
D. Temporary Egress: Maintain temporary egress from existing occupied facilities as required by
OSHA.
E. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses, comply with NFPA 241.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal.
C. Termination and Removal: Remove each temporary facility when need for its service has ended or no later than Substantial Completion. Restore permanent installations that may have been disturbed due to the temporary facility. Repair damaged Work, clean exposed surfaces, and replace installations that cannot be satisfactorily repaired.
END OF SECTION 01 50 00
01 73 00 - 1 Execution
01 73 00 – EXECUTION
A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:
1. Installation of the Work.
2. Cutting and patching.
3. Progress cleaning.
4. Protection of installations.
1.2 DEFINITIONS
A. Cutting: Removal of in-place installations necessary to permit installation or performance of other work.
B. Patching: Fitting and repair work required to restore installations to original conditions after installation of other work.
A. Cutting and Patching: Cut and patch elements in a manner that will not change:
1. Load-carrying capacity or increase deflection.
2. Reduce their capacity to perform as intended.
3. Increase maintenance.
4. Decrease operational life or safety.
5. Reduce building’s aesthetic qualities.
B. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of products and equipment.
C. All phases of the Work shall be executed while maintaining full compliance with applicable EPA regulations and OSHA standards including, but not limited to, 29 CFR 1926 Safety and Health Regulations for Construction and 29 CFR 1910 Occupational Safety and Health Standards.
2.1 MATERIALS
A. General: Comply with requirements specified in other Sections and Drawings.
01 73 00 - 2 Execution
B. In-Place Materials: Use materials for patching identical to in-place materials and that visually match in-place adjacent surfaces to the fullest extent possible.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions for all other conditions affecting installation and performance. If conditions detrimental to that installation and performance are identified, submit report to CO/COR/COTR/EPM. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly. Verify dimensions of existing conditions and related Work elements before fabrication.
B. Space Requirements: Verify space requirements and dimensions of items.
C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to CO/COR/EPM according to requirements in Contract.
3.3 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment, elevation, and as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
C. Conduct project operations so no part of the Work is subjected to damaging operations or loading.
D. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels (85 db or greater) to the public or Government staff without prior approval by COR / COTR.
E. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned.
1. Allow for building movement, including thermal expansion and contraction.
01 73 00 - 3 Execution
F. Joints: Make joints of uniform width. Arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.
G. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
3.4 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching.
B. Existing Warranties: Remove, replace, patch, and repair by methods and with materials so as not to void existing warranties.
C. Temporary Support: Provide temporary support of work to be cut.
D. Protection: Protect in-place installations during cutting and patching to prevent damage. Provide protection from adverse weather conditions.
E. Cutting: Cut in-place installations using methods least likely to damage elements retained or adjoining installations.
F. Patching: Patch installations by filling, repairing, refinishing, closing up, and similar operations.
Patch with durable seams that are as invisible as practicable.
G. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.
3.5 PROGRESS CLEANING
A. General: Maintain clean Project site and work areas, free of waste materials and debris. Dispose of materials lawfully.
B. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.
3.6 PROTECTION OF INSTALLATIONS
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
END OF SECTION 01 73 00
01 77 00 - 1 Closeout Procedures
01 77 00 – CLOSEOUT PROCEDURES
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Final completion procedures.
2. Submission of Documentation on Diverting Project Waste to Recycle
3. Warranties.
4. Final cleaning.
B. Related Requirements:
1. Division 01 Section "Execution" for progress cleaning of Project site.
2. Division 01 Section “Operating and Maintenance Data” for operating and maintenance manual.
1.2 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion:
1. Submit project record documents in accordance with Government’s solicitation package and paragraph 1.3.
2. Submit Documentation on Diverting Project Waste to recycle in accordance with
Government’s solicitation package and paragraph 1.4.
3. Submit Project Warranties in accordance with Government’s solicitation package and paragraph 1.5.
B. Final Site Inspection: Submit a written request for final inspection. On receipt of request, CO/COR/COTR/EPM will either proceed with site inspection or notify Contractor of unfulfilled requirements.
1.3 SUBMISSION OF PROJECT RECORD DOCUMENTS
A. Submit electronic copy (scan) of project record documents along with three (3) hard copies of project record documents to the CO/ACO/COR/EPM.
1.4 SUBMISSION OF DOCUMENTATION ON DIVERTING PROJECT WASTE TO RECYCLE
A. See Section 01 50 00 for additional information.
01 77 00 - 2 Closeout Procedures
B. The Contractor shall submit documentation on the amount of project waste diverted to recycle as part of project closeout. Contractor shall submit the type and amount of waste that was diverted to recycle, present information in a clear, typewritten format. If no project waste is diverted to recycle, the Contractor shall submit a letter stating this and why diversion was not practical. Submit this documentation in accordance with the procedures indicated in Section 01 33 00.
1.5 SUBMITTAL OF PROJECT WARRANTIES
A. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual. Submit electronic copy of the warranty manual along with three (3) hard copies of warranty manual to the CO/ACO/COR/EPM. Hard copy of the warranty manual shall be a bound and indexed three ring binder containing written warranties for equipment/products furnished under the contract with a complete listing of such equipment/products.
1. The equipment/products warranty list shall:
a. Identify the product / equipment.
b. Include the duration of the warranty
c. Indicate the start date of the warranty
d. Indicate the ending date of the warranty
e. List the point of contact and contact information (name, address and telephone number) for fulfillment of the warranty.
2. 1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
3.1 PROJECT RECORD DOCUMENTS
A. Maintain, at project site, one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Approved shop drawings, product data, and samples.
6. Manufacturer's instruction for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Government.
01 77 00 - 3 Closeout Procedures
C. Store record documents separate from documents used for project activities.
D. Record information concurrent with project progress.
E. Legibly mark to record actual project completion.
3.2 WARRANTIES
A. Verify that documents are in proper form, contain full information.
B. Retain warranties until time specified for submittal.
3.3 CLEANUP
A. Provide final cleaning in accordance with ASTM E 1971. Remove waste and surplus materials, rubbish, and project facilities from the site.
END OF SECTION 01 77 00
01 78 23 - 1 Operation and Maintenance Data
01 78 23 - Operation and Maintenance Data
A. Section includes administrative and procedural requirements for operation and maintenance manuals.
1.2 CLOSEOUT SUBMITTALS
A. Manual Content: Submit manual content formatted and organized as required by this Section.
B. Format: Submit electronic copy of the operation and maintenance manual (pdf format) along with three (3) hard copies of operation and maintenance manual to the CO/COR/COTR/EPM.
2.1 REQUIREMENTS FOR OPERATION AND MAINTENANCE MANUALS
A. Organization: Each manual shall contain the following materials. Organize each manual with a separate section for each of the following materials in the order listed.
1. Title page.
2. Table of contents.
3. Manual contents for hot water heating piping and associated components.
4. Manual contents for DCC control system and associated components.
5. Manual contents for Heating Units.
6. Manual Contents As-Built Drawings.
B. Title Page: Include the following information:
1. Name and address of Project.
2. Government contract number.
3. Date of submittal.
4. Name and contact information for Contractor.
C. Table of Contents: List each product and system included in manual, identified by product name.
D. Manuals, Paper Copy: Submit manuals in bound and labeled volumes.
1. Binders: Heavy-duty, three-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.
2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section of the manual.
Mark each tab to indicate contents.
01 78 23 - 2 Operation and Maintenance Data
2.2 OPERATIONAL AND MAINTENANCE INFORMATION
A. Content: Include the following information:
1. Maintenance, Operation, and cleaning procedures.
B. Descriptions: Include the following:
1. Product name and model number.
2. Manufacturer's name.
C. Maintenance Procedures: Include manufacturer's written recommendations and the following, as applicable:
1. Manufacturer’s standard maintenance instructions and bulletins.
2. Drawings,…
This is the start of the file's text. The full file is on GovTribe.