About this file

This statement of work outlines fence repair services required by the Bureau of Land Management's Safford Field Office in Arizona. The contractor will repair 4.5 miles of boundary fence between the Tanque and Badger Den grazing allotments to specifications provided. Work must be completed between September 1st and December 31st, 2023. The contractor will furnish all necessary labor, equipment, materials, and transportation to complete repairs and dispose of waste properly according to regulations. The government will provide maps and specifications to guide work. Inspections will occur periodically and upon completion to verify all requirements are met. Payment will be made in increments according to an agreed schedule upon acceptance of completed work.

View the file

Other files for this federal contract opportunity

Other files attached to TANQUE/BADGER DEN FENCE REPAIR, newest first.
File Type Posted
Amendment_1_0001.pdf PDF
Sol_140L6423Q0033_Amd_0001.pdf PDF
B08_Combined_Synopsis_Solicitation.docx DOCX document
B03_Attachment_3_Wage_Determination_2015-5481_RV_21.pdf PDF
Sol_140L6423Q0033.pdf PDF
Attachment_4_Additional_Instructions_52_212-1.pdf PDF
Attachment_2__Contract_Clauses___Provisions.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF LAND MANAGEMENT

TANQUE/BADGER DEN FENCE REPAIR

GILA DISTRICT – SAFFORD FIELD OFFICE

STATEMENT OF WORK

PURPOSE FOR WORK

The boundary fence between two BLM grazing allotments needs repair. The two grazing allotments include the Tanque and Badger Den Allotments. The boundary fence has been frequently repaired by the Tanque Allotment permittee, and there has not been a permittee on the Badger Den Allotment to assist with the maintenance because the allotment has been unpermitted for livestock grazing for many years. Much of the boundary fence is still in good condition, however, a 4.5 mile section needs extensive repair or replacement. The fence that needs to be repaired consists of a combination of steel and wooden material; damaged or nonfunctional materials would be replaced. Repair of fences are necessary for livestock grazing management to prevent unauthorized grazing/trespass from occurring. If the fence repair is not completed, trespassing cattle could affect the amount of forage available on each allotment and could negatively impact the health of the rangeland.

The work identified in this contract aligns with the DOI Departmental Priority, “Working to conserve at least 30% each of our lands and waters by the year 2030”, by controlling livestock movement and thus providing protection of rangelands from unauthorized livestock grazing. This work also supports the presidential administration’s “America the Beautiful” Initiative priority, “Creating jobs by investing in restoration and resilience project and initiatives, including the Civilian Climate Corps,” through the creation of work regarding the restoration of critical infrastructure for livestock grazing management.

DEFINITIONS

CO – Contracting Officer COR – Contracting Officer Representative Global Positioning Systems (GPS) – A system of satellites, computers, and receivers that is able to determine the latitude and longitude of a receiver on Earth by calculating the time difference for signals from different satellites to reach the receiver.

PI – Principle Investigator Universal Transverse Mercator (UTM) – A mapping coordinate grid system based upon one of many different mapping projects. The BLM in Arizona uses a projection in UTM Zone 10 North, North American Datum 1983, Continental US (NAD83 CONUS). The data is displayed in meters easting and northing.

WORK TO BE PERFORMED

3.1GENERAL INFORMATION
3.1.1Description of work

· Transport all necessary materials.

· Provide any material needed to complete the fence repair.

· Furnish necessary labor and transportation (see Section 3.1.3 Access for further details) to successfully complete the fence repairs, and properly remove and dispose of all scrap materials.

· Complete the repair of 4.5 miles of fence, per the BLM Fence guidelines described in Attachment A BLM Fence Specifications. Deviations from the BLM Fence Specifications is allowed where necessary to accommodate the terrain or topography but should be documented and reported to the COR/PI as it occurs.

· Remove damaged fence and dispose of properly.

· It is the responsibility of the Contractor to know the applicable disposal requirements and regulations based on Federal, State, and/or County guidance.

3.1.2 Project Location

· Work under this Contract is located in Graham County, State of Arizona, 30 miles south of Safford, Arizona.

· The fencelines are grazing allotment boundary fences between the Tanque Allotment and the Badger Den Allotment.

· The work locations are shown on the See Attachment B Work Location and Access Map.

3.1.3 Access

· Access to the work site including transport of personnel, equipment, supplies, and materials will be the responsibility of the Contractor.

· Contractor will coordinate with the COR/PI upon award to coordinate access.

· All portions of the fencelines are located in remote, rough, and rugged terrain. A rough, two-track road private land to BLM-administered lands is available for access to the vicinity of the work area. This is shown as a green line on the map (See Attachment C) and identified as ATV/UTV/4WD Access Only. Alternate transportation of personnel and materials will be necessary during construction and to access the work site. Pack animals may be permitted. See Attachment C Work Location and Access Map.

· Vegetation removal or trimming is only authorized within the fence line path to facilitate maintenance of the fence and not to create access routes.

· Access shall be accomplished with regard for environmental considerations, as described above and displayed in Attachment C Project Location and Access Map.

· Work Camp - The Contractor shall obtain written authorization from the COR prior to camping on BLM administered lands. Comply with all fire regulations and obtain any permits as needed.

CONTRACTOR-FURNISHED PROPERTY AND SERVICES

4.1The Contractor shall provide all labor, equipment, crew supervision, transportation, supplies (except those designated as Government-furnished), and incidentals necessary in accordance with the enclosed specifications, terms and conditions.
4.2Specifically, but not necessarily all inclusive, the Contractor shall furnish:

· Contractor will be responsible for purchasing ALL required materials to construct the fence line to the specifications as outlined in Attachment A: BLM Fence Specifications.

· GPS handheld navigator or other tool to determine UTM and elevation.

· All necessary camping gear if camping is deemed necessary to complete work.

· All safety materials and proper personal protective equipment (e.g., boots, gloves, eye protection, ear protection, sunscreen, hard hat, water).

GOVERNMENT – FURNISHED PROPERTY AND SERVICES

5.1 The Government will furnish to the Contractor the following materials, supplies, property, or services:

· Item 1: Paper maps and/or aerial photos that identify the project area including road maps and topographic maps.

· Item 2: Loadable georeferenced maps for navigation, if requested.

· Item 3:

· Attachment A – BLM Fence Specifications

· Attachment B – Work Location and Access Map

SPECIFIC TASKS

6.1FIELD WORK
6.1.1Pre-work Conference

· Will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

· The Contractor, subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.

· Be prepared to summarize and explain procedures planned for the project.

6.1.2Notify COR prior to starting work.
6.1.3Document and notify the COR/PI daily when deviations from the BLM Fence Specifications occurs due to topography and/or terrain conditions.
6.1.3Post-Construction

· Once fence construction is complete, properly remove and dispose of all leftover materials and trash, per the applicable Federal, State or county regulations. Consult the COR for guidance if needed.

6.2DOCUMENTATION
6.2.1Provide photos of before, during and after the fence construction has occurred to document completion and cleanup of materials.
6.2.2Provide documentation and written notification of BLM Fence Specification deviations daily when they occur.

SURVEILLANCE PLAN AND INSPECTION

7.1The COR/PI may walk with the Contractor through the first day of construction to ensure understanding and compliance with BLM Fence Guidelines.
7.2The COR/PI may inspect progress after the completion of each quarter-mile for quality assurance.
7.3The COR/PI may walk with the Contractor at the end, after the construction and trash disposal is completed, to document final product quality, clean-up, and compliance.
7.4Primary COR: Tommy Schnell, Rangeland Management Specialist, (520) 507-1451 or tjschnell@blm.gov
7.5Principle Investigator: Christina Porter, Rangeland Technician, (928) 348-4415 or cporter@blm.gov

ACCEPTANCE

8.1Field Work – All work, as described under 3. WORK TO BE PERFORMED and 5. SPECIFIC TASKS is complete and determined by the COR/PI to meet the BLM Fence Specifications, as described in Attachment A, and all applicable disposal regulations. Deviations reported to the COR/PI will not count against the Contractor’s performance.
8.2All reworks must be initiated within two (2) days unless otherwise agreed upon by COR.
8.3Documentation – All required documentation shall be sufficient to satisfy all requirements as specified in 5. SPECIFIC TASKS and 6. SPECIFIC TASKS. Any submittals not meeting these requirements will be returned to the Contractor and shall be re-done.

MEASUREMENT AND PAYMENT

9.1Payment will be based on the government inspection results. The Contractor’s inspection results are to be used as a guide for the Contractor’s use in complying with contract specifications and not as a basis for payment.
9.2Payment will be made for completed field work, disposal, and documentation, inspected, and accepted by the Government.
9.3A mutually agreed upon scheduled for periodic payments will be arranged at the pre-work conference.
9.4Final payment will not be made until all deliverables are returned as directed by the COR.

CONTRACT TIME

The Contactor shall begin work within five (5) calendar days from the effective date of the Notice to Proceed. The Contractor shall continue performance of the work under the contract without delay or interruption except by cause for action under the “Default” clause. The Contractor shall complete all work required within six (6) months of the Notice to Proceed (September 1 – December 31, 2023).

PROGRESS PLAN

At the prework conference, the Contractor shall provide to the COR a written “work progress plan” that details the proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule should reflect a work progress rate equal to the available amount of contract performance time. The unit sequence work schedule will be determined by the COR at the prework conference and may be subject to change because of normal variations in weather conditions at no change in contract time or price

ATTACHMENT A: BLM FENCE SPECIFICATIONS

ATTACHMENT B: PROJECT LOCATION AND ACCESS MAPS

image1.emf image2.jpeg