Text version
Statement of Work for
Law Enforcement Safety and Compliance Directorate
Pre-Deployment Training Branch
Harpers Ferry, West Virginia
SCOPE: The Customs and Border Protection (CBP) Law Enforcement Safety and Compliance
Directorate (LESC), Harpers Ferry, West Virginia requires a new 40’ insulated climate-controlled storage container to provide storage of portable equipment/instruments. This will facilitate offsite operations at the Summit Point Training Center, in which the Pre-Deployment
Training Branch facilitates training for CBP personnel. It is the intention of the Pre-Deployment
Training Branch to use the storage container for approximately 6-7 years.
DELIVERABLES AND DELIVERY SCHEDULE:
1) The system shall be load certified able to transport on USA highways.
2) The contractor shall deliver a fully operable new container.
3) Dimensions
a. Exterior: 8’ W x 40' L x 9'6" H
b. Interior: 7'9' W x 39'6 L x 8'10" H
4) Amenities:
a. 2” ISO Poly foam R-12 with plywood over all foam on interior walls
b. 2” ISO Poly foam R-12 with plywood over all foam on the ceiling
c. All interior walls and ceiling painted white
d. Operable cargo doors with handles 36” – 42” from the ground
e. Marine-grade plywood or bamboo floors
f. 125A panel ready to accept main electric line
g. Five standard 4-foot light fixtures, each with two 4-foot LED tubes
h. 1 – Light switch to operate internal and external lights
i. One 15K PTAC unit
j. Two external security lights on the front of the unit
5) Container will be delivered to Summit Point, West Virginia (25446).
6) Vendor will place storage unit in customer’s desired location and provide electrical connections between the storage container and the provided electrical box on sight.
PLACE OF DELIVERY/INSTALL:
Summit Point Raceway Associates, Inc, 201 Motor Sports Park Circle
Summit Point, WV, 25466
A 60’ tilt bed truck will have enough room to lower the container to the ground. The container will sit on concrete pads (2 in the rear and 2 in the front). The area is a gravel lot, approximately
45’L x 15’W. The container will sit on four concrete pads that are placed in the gravel lot, two
(2) at the front and two (2) at approximately the 40’ mark. The concrete pads are approximately
1” – 2” above the gravel line. The area leading up to the gravel lot is an asphalt parking lot/road and is approximately 250’ long and straight.
The awardee will not be responsible for any electrical work required to connect the container once delivered. The electrical connection will be hardwired, not a plug connection.
DRAWING/INSTALL DETAILS:
File details come from the government source that posted it. Updated .