Attachment 1 - PWS Airfield Lighting 24 Feb 21.pdf
PDF 256 KB Posted
- Attached to
- Aircraft Lighting Computer System Maintenance and Repair Federal contract opportunity
- Solicitation number
- FA480021Q0011
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation - FA480021Q0011.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
FOR
AIRFIELD LIGHTING COMPUTER SYSTEM
(ALCS)
FA4800-21-Q-0011
633 CES
Langley Air Force Base
Joint Base Langley-Eustis, VA
TABLE OF CONTENTS
FA480021Q0011 – ALCS – 24 Feb 2021
1.0. SCOPE OF WORK
2.0. DESCRIPTION OF SERVICES
3.0. GENERAL INFORMATION
4.0. SERVICES SUMMARY
5.0. GOVERNMENT AND CONTRACTOR FURNISHED PROPERTY, SUPPLIES AND
SERVICES
APPENDIX A – CONTRACTOR MANPOWER REPORTING
APPENDIX B – APPLICABLE PUBLICATIONS AND FORMS
1.0. SCOPE OF WORK. The contractor shall provide all management, transportation, tools, supplies, equipment, and labor necessary to perform airfield lighting control system maintenance on Joint Base Langley-Eustis (JBLE), Langley Air Force Base (LAFB), Virginia (VA) in a manner that shall ensure continuous and reliable service. The contractor shall provide all labor, equipment, transportation, materials, and perform all operations necessary to perform a comprehensive package of diagnostics and testing of the Airfield Lighting Computer System (ALCS) by certified technicians with a follow up detailed report of work and actions that took place. The contractor shall inspect the ALCS semi-annually. Contractor shall also be available for emergency repairs to the ALCS as required.
2.0. DESCRIPTION OF SERVICES.
2.1. Semi Annual Inspections:
2.1.1. Perform an ALCS check-up that inspects each computer node in the ALCS network, including the following tasks but not limited to: Communication system tests, Computer hard drive diagnostics, Database Clean-Up, Touch screen calibrations, Enclosure inspections (fans / heating / cooling), Printer testing, Keyboard / Monitor cleaning, Network hubs, and Switch inspections.
2.1.2. Perform a system calibration on associated airfield lighting circuits including but not limited to the following tasks: Constant current regulator calibrations, Calibration of lamps out, Distribute control equipment (ACE) testing and diagnostics, Software versions updates, Insulation resistance (IRMS) diagnostics, Circuit selector functionality, Record CCR output current Voltage, VA and IRMS readings, and Firmware version updates.
2.1.3. On site technician shall provide a separate cost estimate if during the calibration or check up stage, problems are identified that may require parts and/or additional site visits. All additional site visits will be coordinated during the core hours of 0730-1630 unless specified otherwise.
2.1.4. Reports: The contractor shall provide the Contracting Officer Representative (COR) a report within 5 business days of the quarterly service. The report shall have as a minimum: Date of Service, Location, Service performed, Name of technician(s) and any issues pertaining to the service, i.e. electrical service, etc. The contractor shall provide a complete analysis of the ALCS system, recommendations of required maintenance or upgrades that would aid system performance, and any additional maintenance tools that are available, as well as a recommended spare parts list.
2.1.5. Contractor shall allow government personnel to accompany technician and train government personnel during the ALCS checkup and system calibration. Contractor must coordinate with the 633 CES Exterior Electric shop foreman (Mr. David Spangler, 757-846- 6242) prior to scheduled work or visits on base.
2.1.6. The contractor shall provide a contract manager and an alternate who shall be responsible for the performance of the work. These individuals shall have full authority to act for the contractor on all contract matters relating to the daily operation of this contract and shall be designated in writing to the Contracting Officer. The alternate contract manager shall act for the contract manager when the manager is absent. The contract manager and alternate contract manager shall have experience in management, supervision, computer operations, and education services background to include distance learning, testing and computer technology.
2.2. Part/Materials
2.2.1. Contractor shall be responsible for procuring any part/materials for repairing the ALCS.
Please reference para 2.3 Repairs for additional instructions.
2.3 Repairs. The contractor shall identify, in writing, all necessary repairs considered to be out of the scope of preventative maintenance as defined within this PWS. The contractor shall accomplish all work order tasks during normal duty hours; however, occasions may arise that require work to be accomplished outside of these hours. The contractor shall coordinate all routine work outside of normal duty hours with the COR and the CO.
2.3.1. The COR will approve each repair that has a total cost under $2,500.00 and the Contracting Officer (CO) will approve each service call/repair that has a total cost of $2,500.00 and greater. The contractor is not authorized to perform unscheduled work without the below approvals.
2.3.1.1. All work with the total cost of each repair under the micro-purchase threshold limit (currently $2,500.00) shall be approved by the COR first before the contractor is authorized to perform. The contractor shall repair the affected system or area within the mutually agreed upon time after notification.
2.3.1.2. All work with the total cost of each repair over the micro-purchase threshold limit (currently $2,500.00) is required to be approved by a CO to determine the price to be fair and reasonable. The process for CO approval is outlined below.
2.3.1.2.1. When the contractor identifies a repair that is estimated to cost $2,500.00 or more, the contractor shall contact the COR first and provide the COR with the scope of work for repairs.
The contractor shall not provide any pricing or estimates, for any repair that is estimated to cost $2,500.00 or more. The contractor shall only provide the scope of work to the COR.
2.3.1.2.2. The COR will submit a repair request to the 633 CONS contract specialist, who will then send a Request for Quote (RFQ) to the contractor.
2.3.1.2.3. The contractor shall provide their quote to the 633 CONS contract specialist, who will then coordinate with the COR to ensure technical acceptability. Once the COR provides their technical review to the 633 CONS contract specialist, a Letter of Direction (LOD) will be issued by 633 CONS for the contractor to begin the repairs. The contractor shall complete the repairs within the mutually agreed upon time stated in the LOD after the LOD notification. A minimum of three (3) quotes shall be submitted by the contractor for items that are not proprietary to the Original Equipment Manufacturer (OEM).
2.3.1.3. The contractor shall invoice for all repairs after the work is completed and submit all tickets for the work as one (1) attachment in iRAPT.
2.4. Personnel Qualifications (if applicable): Contractor personnel shall have the technical skills necessary to provide the required service to all contracted equipment and contractor furnished equipment.
2.5. Deliverables. The contractor shall submit all deliverables in electronic form and shall produce reports using the Microsoft Office suite of applications. All deliverables must meet professional standards and the requirements set forth in contractual documentation. The contractor shall be responsible for delivering all end items specified.
Document/Item Due Contract Manager Designation Prior to the beginning of performance Contractor's Quality Control Plan NLT 10 working days after contract award Blank Inspection Report Prior to the beginning of performance Annual Inspection Report W/in five business days of inspection Repair & Maintenance Quotes As needed
Repair & Maintenance Report
W/in five business days of repair &maintenance
3.0. GENERAL INFORMATION.
3.1. Hours of Operation. The hours of operation are 0730 to 1630 Eastern Standard Time (EST), Monday – Friday, excluding federal holidays. If the contractor wishes to perform any services outside of the normal hours of operation, the contractor shall coordinate with the Contracting Officer Representative (COR) and the Contracting Officer (CO) no later than one week prior to the scheduled event. In the event of emergency circumstances, accommodations may be made on a case by case basis.
3.1.1. Base Closure Days. If the Base Commander determines the base is closed due to snow, hurricane, or Acts of God, the contractor shall reschedule work planned for this time.
3.1.2. Federal Holidays. The Contractor shall not be required to work any of the following federal holidays:
New Year’s Day - 1 January Martin Luther King Day - 3rd Monday in January Washington’s Birthday - 3rd Monday in February Memorial Day - last Monday in May Independence Day - 4 July Labor Day - 1st Monday in September Columbus Day - 2nd Monday in October Veteran’s Day - 11 November Thanksgiving Day - 4th Thursday in November Christmas Day - 25 December
3.1.2.1. If a holiday falls on Saturday, the preceding Friday shall be observed. If a holiday falls on Sunday, the following Monday shall be observed. If a holiday falls on a scheduled service day, the contractor shall be responsible for rescheduling services for the first day post the holiday observance.
3.2. Non Mission-Essential Functions. It has been determined by the Functional Commander of this service that the requirements under this PWS are non-essential and therefore shall not be performed during a crisis, exercise or inclement weather.
3.3. English Language Requirement. All contractor personnel shall read, understand, speak and write English fluently.
3.4. Contract Manager. The Contractor shall provide a contract manager and an alternate who shall be responsible for the performance of the work; these duties can be an additional duty.
These individuals shall have full authority to act for the contractor on all contract matters relating to the daily operation of this contract and shall be designated, in writing, to the Contracting Officer (CO). The alternate contract manager shall act for the contract manager when the manager is absent.
3.4.1. The contract manager or alternate shall be available within 2 hours to meet on the installation or by telecom with the CO and/or with other government personnel designated by the CO during normal duty hours to discuss issues or concerns.
3.5. Communication. Contractor personnel shall maintain open and professional communication with government personnel at all times. Complaints validated by the COR shall be reported in writing to the CO and the contractor for action. Failure of the contractor to take corrective action on validated complaints raised by the COR and the CO will be considered a failure to perform.
3.6. Appearance. Contractor personnel shall present a professional, conservative, and neat appearance. Contractor personnel shall report for duty in a professional manner, in appropriate attire and having complied with socially acceptable standards of personal hygiene.
3.7. Contractor Identification. All contractor personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious are required to identify themselves as such to avoid being mistaken for Government officials. Contractors performing work at Government workplaces will provide their employees with an easily readable identification (ID) badge indicating the employee's name, the contractor's name, the functional area of assignment, and a recent color photograph of the employee.
Contractors shall require their employees to wear the ID badges visibly when performing work at Government workplaces. Contractor personnel must also ensure that all e-mails, documents, or reports they produce are suitably marked as Contractor products or that Contractor participation is appropriately disclosed. All signature blocks on e-mails shall indicate the Contractor's name.
All e-mail address lines shall include CTR in the address line.
3.8. Conflict of Interest. The contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest.
The contractor shall not employ any person who is an employee of the Department of the Air Force, either military or civilian, unless such a person seeks and receives approval in accordance with the Department of Defense (DoD) Directive 5500.7 and Air Force policy. If prior military, personnel must have been discharged under honorable conditions with no administrative actions taken against them.
3.9. Security Requirements for Unclassified Contracts. The contractor shall ensure the necessary pass and identification items required for contract performance are obtained for all personnel.
3.9.1. Listing of Personnel. The contractor shall maintain a current listing of personnel. The list shall include the employee’s name, social security number and level of security clearance. The list shall be validated and signed by the company’s Facility Security Officer (FSO) and provided to the sponsoring agency’s security manager, the COR, and the CO. An updated listing shall be provided when an employee’s status or information changes.
3.9.2.Temporary Base Access Passes. The contractor shall ensure that each employee obtains the following pass and identification items: all necessary cards, passes, buttons, decals, or other items required for access to the areas and the installation. Upon contract award and the replacement of any employees, the contractor will be required to complete a base access request form which will be submitted to the COR. The COR will submit the pass request to the 633d Security Forces Squadron (633 SFS) to obtain the necessary identification items. Upon approval of the pass request by 633 SFS, the contractor employee will be required to obtain any individual and vehicle identifications media at the 633 SFS Pass and Identification Section, 20 Nealy Ave (Bldg 5) on Langley AFB, VA.
3.9.3. Pass and Identification (Not Required): All prospective contractors shall undergo a verification process to determine the trustworthiness and suitability prior to being granted access to federal property. Limited access with escort may be granted (at the installation's discretion) for an interim period while investigations are being conducted. The 633d Security Forces Squadron or 733rd Security Force Squadron, as appropriate, will conduct background checks on all contractor personnel requiring access to the installation. IAW 18 USC 1382, the authority of the Installation Commander to control and deny a Contractor employee entry to all or part of the installation is absolute.
3.9.4. Employee clearance requirements. As a minimum, contractor personnel must be able to obtain and maintain a TIER 1, favorable suitability/fitness determination under 5 CFR 731 or equivalent. The Government will submit background investigations for positions that require a Common Access Card (CAC) and/or IT access only. Prior to CAC issuance, an FBI fingerprint check must be completed without adverse comment, and the T1 Investigation or equivalent must be initiated. CACs will not be issued before the fingerprint check results have been completed and the investigation has been opened/scheduled at Office of Personnel Management (OPM).
Contractor personnel receiving unfavorable T1 Investigations shall not be employed. The sponsoring Government agency will submit requests for investigation on AF Form 2583, Request for Personnel Security Action, at no additional cost to the contractor. The contractor shall comply with the requirements of DoDM 5200.02, AFM 16-1405 Personnel Security Program and AFI 33-119, Electronic Mail (E-Mail) Management and Use.
3.9.5 Physical Security (Security of Government Property). The contractor shall safeguard all government property, including controlled forms provided for contractor use. At the close of each work period, government equipment, facilities, and squadron assets and materials shall be secured.
3.9.6. Entry Procedures to Controlled/Restricted Areas. The contractor shall implement local base procedures for entry to Air Force (AF) controlled/restricted areas where contractor personnel will work.
3.9.7. Reporting Requirements. The contractor shall comply with the requirements of Volume 1, AFI 71-101, Criminal Investigations, and paragraph 1.1 of Volume 2, Protective Service Matters. Contractor personnel shall report to an appropriate authority any information or circumstances of which they are aware that may pose a threat to the security of DoD personnel, contractor personnel, resources, and classified or unclassified defense information. The contractor personnel’s immediate supervisor shall brief him/her upon initial on-base assignment and as required thereafter.
3.9.8. Retrieving Identification Media. The contractor shall return all identification media to the sponsoring agency’s security office, the COR or the CO upon completion/termination of the contract or upon departure of any personnel during the course of the contract. Failure to do so may delay payment to the contractor. Final payment may be withheld until identification media is returned.
3.10. Traffic Laws. The contractor and/or contractor personnel shall comply with the installation traffic code as specified in Virginia State Law and Air Force Instruction (AFI) 31-218, Motor Vehicle Traffic Supervision (current edition). The Contractor and/or contractor personnel shall comply with current instruction on cell phone use while on any military installation.
3.11. Weapons, Firearms, and Ammunition. Contractor personnel are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor-owned vehicle or privately-owned vehicle while on any military installation. This prohibition includes any individual who may otherwise possess any legally issued concealed weapons permit.
3.12. Smoking in Air Combat Command (ACC) Facilities. Contractors are advised that the ACC Commander has placed restrictions on the smoking of tobacco products in ACC facilities.
AFI 40-102, Tobacco Use in the Air Force (current edition), outlines the procedures used by the commander to control smoking in our facilities. Contract personnel and visitors are subject to the same restrictions as Government personnel. Smoking is permitted only in designated smoking areas.
3.13. ENVIRONMENTAL MANAGEMENT: Joint Base Langley-Eustis (JBLE) is dedicated to the conservation, protection, and enhancement of the environment. The contractor shall comply with all: federal laws and regulations; state and local laws, ordinances, and regulations;
and Installation policies and procedures. JBLE Installation specific policies and procedures:
3.13.1. Joint Base Langley-Eustis – Langley Air Force Base. The contractor must comply with all provisions of the JBLE-Langley Environmental Special Conditions. You can review or download the document at http://www.jble.af.mil/Units/Air-Force/Langley-Environmental/ under the "Contracting- Compliance" heading. This is a living document that is updated periodically so ensure you have the latest version. If you have any questions, please contact your project manager or the 633d Contracting Officer first and have them contact the 633d CES Environmental Element on your behalf.
3.13.2. Joint Base Langley-Eustis - Fort Eustis. The contractor must comply with JBLE-I 32-101, Environmental Management with related Environmental Management Procedures (EMPs). EMPs are reviewed and/or updated at least annually. JBLE-I 32-101 and EMPs can be reviewed and downloaded at:
http://www.jble.af.mil/Units/Army/Eustis-Enviromental.
3.14 Operations Security (OPSEC)
This contract has been determined to not have critical or sensitive information requiring an OPSEC Plan.
http://www.jble.af.mil/Units/Air-Force/Langley-Environmental/ http://www.jble.af.mil/Units/Army/Eustis-Enviromental
4.0. SERVICES SUMMARY (SS). The contract service requirements are summarized in performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimally acceptable levels of service required for each requirement. The SS and the contractor’s Quality Control Plan provide information on contract requirements, the expected level of contractor performance and the expected method of government surveillance and confirmation of services provided. These thresholds are critical to mission success.
Procedures as set forth in the Federal Acquisition Regulation (FAR) 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance, will be used to remedy all deficiencies. The absence of any contract requirements from the SS shall not detract from its enforceability nor limit the rights or remedies of the Government under any other provision of the contract. The Government has the right to inspect all services required in the contract.
Performance Objective PWS Para Performance Threshold
Remedy Method of Assessment
SS-1
Perform an ALCS check-up on each computer node
1.1. thru 1.1.1.9.
inclusive and Tech Exhibit A
0 defects Re-performance Within 8 hours of notification
100 % Surveillance
SS-2
Perform system calibration
1.1.2. - 1.1.2.8.
inclusive.
& Exhibit A
0 defects Re-performance Within 8 hours of notification
100 % Surveillance
SS-3
Reports
1.1.4. 0 defects Re-performance Within 8 hours of notification
100 % Surveillance
4.1. Performance Evaluation. The purpose of the Services Summary is to define performance evaluation and payment procedures. The Performance Objective (column 1) describes what the government will survey. Performance of a service will be evaluated to determine whether or not it meets the Performance Threshold (PT) of the contract. When the PT is exceeded, the COR will document the performance issue in a Corrective Action Report (CAR) or a Performance Assessment Report (PAR) and provide it to the Contracting Officer to finalize it and issue the report to the contractor.
4.1.1. The Government will periodically evaluate the contractor’s performance by appointing a representative(s) to monitor performance to ensure services are received. The government representative will evaluate the contractor’s performance through inspections of reports and contractor services documentation. The Government may inspect each task as completed or increase the number of quality assurance inspections if deemed appropriate because of repeated failures or because of repeated customer complaints. Likewise, the Government may decrease the number of quality assurance inspections if performance dictates.
4.1.2. If any of the services do not conform to contract requirements, the Government may require the contractor to perform the services again in conformity with contract requirements at no increase in contract amount. When the defects in services cannot be corrected by re-performance, the Government may:
- Require the contractor to take necessary action to ensure that future performance conforms to contract requirements; and
- Reduce the contract price to reflect the reduced value of the services performed.
4.1.3. Failing to meet the performance threshold as outlined in the SS for any of these performance objectives in any one month period may result in an immediate Progress Meeting with the Multi-Functional Team (MFT). All remedies shall be in accordance with the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance.
4.2. Quality Control. The contractor shall develop and maintain a quality control program to ensure services are performed in accordance with this contract and PWS. The contractor shall develop and implement procedures to identify and prevent non-performance and continual repeat of defective service. A written Quality Control Plan (QCP) shall be submitted to the CO and COR for review and feedback. The plan shall be submitted no later than 10 working days after award. The plan shall specifically address the contractor’s strategy to provide quality workmanship, continual process improvement and for correcting deficiencies as required.
4.3. Quality Assurance. The Government shall inspect and evaluate the contractor’s performance to ensure services are received in accordance with requirements set forth in this contract. The COR shall inspect by watching actual task performance, physically checking an attribute of the completed task, checking management information reports, investigating customer complaints, conferring with facility managers, or otherwise inspecting the task or its results to determine whether or not performance meets the standards contained in this PWS. The COR will record surveillance results. Results of the surveillance then become the official Air Force record of the contractor’s performance. When a performance threshold has not been met or contractor performance has not been accomplished, the COR will initiate a Corrective Action Report (CAR) or Performance Assessment Report (PAR), and provide the Contracting Officer a Contract Discrepancy Report (CDR) for issuance to the contractor. The contractor shall respond to the CDR in accordance with instructions provided and return it to the Contracting Officer no later than the suspense given by the CO.
4.4. Surveillance Methods.
4.4.1. 100% Surveillance. This method requires the COR to inspect the service each time it occurs. Results shall be annotated on the inspection checklist. Any deficiency shall be documented and the contractor shall re-perform service as directed by the COR. Any unsatisfactory inspection identified but re-performed acceptably, shall still be counted as an unsatisfactory inspection for trending purposes.
5.0. GOVERNMENT AND CONTRACTOR FURNISHED PROPERTY, SUPPLIES
AND/OR SERVICES.
There is no Government-furnished property for this Contractor that meets the intent of FAR Part 45. There is Government equipment that will remain in the control and accountability of the Government.
Equipment Inventory. An inventory of Government equipment to be used by the contractor to perform this requirement shall be done within five (5) calendar days after the start of the contract period, and not later than ten (10) calendar days before the completion of the contract period (including any option periods). The Contractor and CORs shall conduct a joint inventory of all Government equipment and the Contractor shall sign a hand receipt for all equipment provided by the Government. During joint inventory, any items of equipment missing or not in working order shall be recorded and the Contracting Officer notified in writing. The Contractor and the Government representative shall jointly determine the working order and condition of all equipment and document their findings on the inventory.
| PERFORMANCE WORK STATEMENT |
| FA4800-21-Q-0011 |
| 633 CES |
| Langley Air Force Base |
| Joint Base Langley-Eustis, VA |
| TABLE OF CONTENTS |
File details come from the government source that posted it. Updated .