This document is a Performance Work Statement (PWS) for an Integrated Solid Waste Management (ISWM) contract for the 911th Airlift Wing at Pittsburgh Air Reserve Station. The contractor shall provide all personnel, equipment, and services necessary to collect and dispose of municipal solid waste, construction/demolition debris, and cardboard recycling. Key requirements include weekly municipal solid waste collection, monthly construction/demolition and cardboard recycling collection, on-base container maintenance, and disposal at permitted off-base facilities. The contract includes a 12-month base period and four 12-month option years with a 6-month extension. The related federal contract opportunity is a Request for Quotation (RFQ) under Solicitation Number FA671224Q0020 for the same ISWM services. Quotes are due by April 5th and the contract is expected to start on May 1, 2024. Award will be made to the lowest technically acceptable offeror with an acceptable past performance rating.

View the file

Other files for this federal contract opportunity

Other files attached to Integrated Solid Waste Management Service, newest first.
File Type Posted
Attachment 4 TABLE A2 Tasks and Frequencies.docx DOCX document
Attachment 2 - QUOTE TEMPLATE-911th AW FY24 Rev1.xlsx XLSX spreadsheet
Attachment 3 - Wage Determination 2015-4235 Rev 25 Dated 12-26-23.pdf PDF
Attachment 5 Provisions and Clauses.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT FOR

INTEGRATED SOLID WASTE MANAGEMENT (ISWM)

911th AIRLIFT WING

PITTSBURGH AIR RESERVE STATION

26 July 2023

1. DESCRIPTION OF SERVICES. The Contractor shall provide all personnel, equipment, tools, materials, front loader garbage trucks, supervision, and other items and services necessary to perform integrated solid waste management encompassing municipal solid waste (MSW) collection, construction and debris (C&D) collection, and cardboard recycling collection at 911th Airlift Wing, Pittsburgh Air Reserve Station, PA. The Contractor shall perform to the standards in the contract as well as all local, state, and federal regulations, international agreements, Status of Forces Agreements (SOFA) and appropriate Final Governing Standards (FGS) or, in their absence, the Overseas Environmental Baseline Guidance Document (OEBGD). Estimated workload factors in Appendix A and collection areas in Appendix B.

1.1. COLLECTION REQUIREMENTS.

1.1.1. Main Base

1.1.1.1. Municipal Solid Waste/C&D. The Contractor shall empty refuse containers once per week using a front loading garbage truck and empty one 30 cubic yard (C&D), container once per month; collection schedules, and container sizes are in Appendix B. The Contractor may propose adjustments to the schedule at any time but as a minimum the Contracting Officer’s designated Representative (COR), and contractor shall monitor fill capacities during the first 30 days of performance and during one other period to be agreed upon during the same performance period, in order to determine if adjustments to container size, routes, or frequencies should be made to provide the minimum number of pickups necessary to maintain a healthy, vector free environment and prevent waste container overflow. No changes are allowed to the schedule or haul route without the Contracting Officer (CO), or COR coordination. When the Contractor completes service at a location there shall be no litter, waste, or recyclable material on the ground within a 10-foot radius of the container. The contractor must provide weekly weight slips for the municipal solid waste and monthly weight slips for C&D. Scale location is identified on the map in Appendix B.

1.1.1.2. Cardboard Recycling. The Contractor shall empty cardboard recycling containers once per month. The vehicle routes, collection schedules, and container sizes are in Appendix B. The Contractor may propose adjustments to the schedule at any time but as a minimum, the COR and contractor shall monitor fill capacities during the first 90 days of performance and during one other period to be agreed upon during the same performance period, to determine if adjustments to container size, routes, or frequencies should be made. No changes are allowed to the schedule or haul route without CO or COR coordination. When the Contractor completes service at a location there shall be no litter, waste, or recyclable material on the ground within a 10-foot radius of the container. The contractor must provide monthly weight slips for the cardboard. Scale location is identified on the map in Appendix B.

1.1.2. Over and Above Requirements. The following services shall be priced separately in accordance with the cost contained in the bid schedule. The contractor shall be compensated IAW the price specified in the bid schedule for that service.

1.1.2.1. Unscheduled Pickup and Special Events. In addition to the scheduled solid waste, C&D, and cardboard collections, the CO or COR may request the contractor make unscheduled collections and disposals. For unscheduled events, the contractor shall respond within one business day of notification from the CO or COR. For special events, the contractor shall also provide (or re-position as directed) solid waste containers. These containers shall be placed in locations for a length of time designated by the CO or COR. The CO shall notify the contractor in writing at least 7 days in advance of the special event date. See Appendix A for workload data.

1.1.2.2. Construction and Demolition Debris (C&D). When requested by the CO or COR, the contractor shall provide roll-off containers for collection of C&D. The contractor shall place containers at the designated site within one business day of notification by the CO or COR. The contractor shall recycle or dispose of all C&D at a recycling facility or permitted landfill. The contractor must provide weight tickets of all roll-off containers to the COR.

1.1.2.3. Additional Pickups: In the event unusual conditions cause a container to require pickup before the scheduled time, the CO or COR may request in writing (email/Fax sufficient) pickup within 24 hours and the contractor will be compensated at a unit rate based on the container size.

1.1.2.4. Container Relocations: The Government may request relocation of containers. The request will be made in writing and the container will be relocated within 72 hours.

1.1.4. Inclement Weather Schedule. The contractor shall collect MSW and recyclable material during periods of inclement weather. In cases of severe weather, the CO or COR may authorize exceptions. When exceptions are granted, all missed collections shall be performed within 24 hours after the severe weather has terminated, unless the CO authorizes additional time.

1.1.5. Route Parameter and Collection Days/Times. The contractor shall propose base collection routes to the CO and COR for acceptance. Collection shall be made on Thursday for solid waste and Wednesday for recyclables between the hours of 0400 and 1600. Collection outside these hours shall require prior approval of the CO or COR.

1.1.6. Points of Collection. Collection stations for MSW, C&D, and recyclable cardboard are shown in Appendix B. The contractor shall position bulk containers for customer ease in depositing MSW. The contractor shall also position containers to minimize interference with adjacent parking areas, sidewalks, roadways, overhead utilities, trees, storm drains, and other potential obstructions.

1.1.7. Cubic Yard Capacity. Proposed capacity of containers is indicated in Appendix A, Table A2. The contractor is encouraged to identify changes to the capacity of containers and/or pickup frequency to improve the overall efficiency of MSW and cardboard removal, and to submit these changes to the CO or COR. No changes shall be made until the proposed change is coordinated with the CO or COR.

1.1.8. Government-Approved Containers. Collection of MSW, C&D, and recyclable materials in all areas shall be from contractor-provided, CO or COR accepted containers, and recycling bins.

1.1.9. Maintaining Containers and Collection Area. The Contractor shall return all MSW, C&D, and recycling containers to their original location after servicing, in an upright position with the lids securely in place (closed). The Contractor is responsible for cleaning up any spills, debris, etc., on the ground within 10 feet of the container when servicing a location. The Contractor shall notify the COR of locations where debris is frequently placed outside of containers so the COR may notify facility managers and, if necessary, the Contractor can adjust the container size or pickup frequency with CO or COR approval. The contractor shall also notify the COR if it is discovered that a particular receptacle is being utilized for the wrong material.

1.1.10. Vehicle Weighing. All vehicles used to collect MSW, C&D, and recyclable cardboard shall be weighed on state-certified vehicle scales located at building 320 upon entering and before departing the base. Incoming and outgoing vehicle weights shall be recorded on weigh tickets provided by the self-service weigh station. The Contractor shall leave weight slip at the scale house upon completion of final weighing.

1.3. DISPOSAL.

1.3.1. Off-Base Disposal. The contractor shall transport and dispose of all municipal solid waste at a permitted off-base disposal site. A copy of the landfill(s) operating permit that material is transported to shall be provided to the CO. The contractor shall transport recyclable commodities to an off-base material recovery facility. The contractor is responsible for disposal being in accordance with existing local, state, and federal regulations.

1.3.2. Disposal of Non-marketable Materials. Any commodity rejected by a predetermined commodity buyer must be reclaimed by the contractor for commodity rework or disposal. Commodity rejection explanation must be provided to the CO or COR within 24 hours of buyer rejection along with remedy of the reject and plans to prevent same future rejections.

1.4. EQUIPMENT MAINTENANCE. The Contractor shall furnish containers that match the architectural/appearance standards of the base. Additional re-painting must match the approved color scheme. The Contractor shall maintain containers so that they have a professional appearance and ensure they are free of unpleasant odors, dirt, debris, and pests. All containers must remain in good, workable condition, with no leaks. They must remain easily accessible to customers. The Contractor shall perform all cleaning, painting, repair, and other maintenance tasks off-base. Trucks and trailers used for hauling and collecting shall be free of odor, dirt, debris, and pests.

1.5. LEAKING EQUIPMENT. Contractor vehicles and equipment shall not have any waste or equipment leaks such as oil or hydraulic fluid. Should any contractor vehicles or equipment have any leaks, the contractor is responsible for cleanup.

2. SERVICE SUMMARY. The contract service requirements are summarized in performance objectives (table below), that relate directly to mission essential items. The performance threshold briefly describes the minimally acceptable levels of service required for each requirement. The Services Summary (SS) and the Contractor’s Quality Control Plan provide information on contract requirements, the expected level of Contractor performance, and the expected method of government validation and confirmation of services provided. These thresholds are critical to mission success. Procedures as set forth in the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance, will be used to remedy all deficiencies. During the first initial 30 days of the contract, two additional errors on each Performance Objective shall be allowed to identify normal phase-in problems.

Performance Objective
PWS para.
Performance Threshold
Collect Municipal Solid Waste and Cardboard in accordance with the established schedules.
1.1
No more than 2 Customer Complaints monthly.
Dispose of Municipal Solid Waste in accordance with the established governing directives.
1.3
0 Deficiencies permitted.
Maintain equipment in good workable condition. Trucks and solid waste containers washed and free of odors.
1.4
No more than 2 Customer Complaints monthly.
Perform unscheduled collections required by the contracting officer in accordance with paragraph 1.1.
1.1.3.1
0 Deficiencies permitted.
Submit copy of the landfill operating permit at contract start.
1.3.1
0 Deficiencies permitted.

2.1. QUALITY CONTROL

The contractor shall develop and maintain a quality program to ensure integrated solid waste management is performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non- recurrence of defective services. As a minimum the contractor shall develop quality control procedures addressing the areas identified in paragraph 2, Service Summary.

2.2. QUALITY ASSURANCE

The Government shall inspect and evaluate the Contractor’s performance to ensure services are received in accordance with requirements set forth in this PWS. The contractor shall provide work schedules to the COR in accordance with paragraph 4.3 of this PWS. The COR shall inspect by validating actual work performance, physically checking an attribute of the completed task, investigating customer complaints, conferring with facility managers, or otherwise inspecting the task or its results to determine whether performance meets the standards contained in this PWS. The COR will use the Contractor’s work schedule or modified version thereof, to record validation results. Results of the validation then become the official Air Force record of the Contractor’s performance. When a performance threshold has not been met or Contractor performance has not been accomplished, the COR will initiate a Status Report to document deficiencies.

2.3 PERFORMANCE ASSESSMENT

2.3.1. Periodic Validations. This method requires the COR to employ a “spot check” style of evaluation based on the Contractor’s schedule. Periodic validations will be conducted on a scheduled basis (daily, weekly, monthly, quarterly, semi-annual, or annually) and may be adjusted, based on quality trends.

2.3.2. Unsatisfactory Performance. Any unsatisfactory inspection (defect) result shall be recorded, and the Contractor shall re-perform the service after notification by the COR. Failing to meet the performance threshold as outlined in the SS for any of these performance objectives in any one month period shall result in a warning or letter of concern from the CO. Failing to meet the performance threshold as outlined in the SS of these performance objectives in any combination for any two, or more consecutive or non-consecutive months during a contract period shall constitute an immediate Progress Meeting with the Multi-functional Team. All remedies shall be in accordance with the FAR 52.212-4 (a), Contract Terms and Conditions - Commercial Items, Inspection/Acceptance.

2.4. PERIODIC PROGRESS MEETINGS

2.4.1. Meetings. The CO, Functional Commander, COR, QRP Manager and/or Solid Waste Manager, other government personnel as appropriate, and the Contractor shall periodically meet to discuss the Contractor’s performance. The following issues shall be discussed: opportunities to improve the contract, required contract modification(s), unsatisfactory inspections and trends against each performance objective observed, positive performance and steps taken by the Contractor to prevent unsatisfactory occurrences in the future. The Contractor shall provide a summation of unsatisfactory inspections and customer complaints and provide insight into any identified trends.

2.4.2. Meeting Minutes. The minutes of these meetings will be reduced to writing, signed by the CO, and any other signatures as deemed appropriate, distributed to the functional area and the Contractor. Should the Contractor not concur with the minutes, the Contractor shall provide a written notification to the CO identifying areas of non-concurrence for resolution.

3. GOVERNMENT FURNISHED PROPERTY AND SERVICES. SELF-SERVICE WEIGH STATION (Identified on the map in appendix B)

4. GENERAL INFORMATION.

4.1. MISSION

The overall Civil Engineer mission at Pittsburgh ARS is to plan, maintain, operate, and protect the infrastructure, facilities, and environment for assigned Airmen, families, and civilian employees.

4.2. HOURS OF OPERATION.

Perform integrated solid waste management services between the hours of 0400 and 1600 Monday through Friday and be available (by phone, pager, cell phone, text message or fax) during the Government Program Office’s hours (7:00 a.m. to 3:30 p.m., Monday through Friday) and for after-hours response to refuse/recycling problems or emergencies. This excludes federal holidays, unless otherwise required in the contract or approved by the CO. There may be situations that require the Contractor to work at times other than normal duty hours. When the Contractor’s work schedule conflicts with an Air Force mission requirement, advise the CO and reschedule the work to minimize disruption.

4.3. HOLIDAYS & CLOSURES

4.3.1. Recognized Federal Holidays. There may be federal holidays when the Contractor is not required to perform service, except in emergency situations or to support specific mission needs. The holidays are:

New Year’s Day - 1 January Martin Luther King Day - 3rd Monday in January Washington’s Birthday - 3rd Monday in February Memorial Day - last Monday in May Juneteenth National Independence Day – 19 Jun Independence Day - 4 July Labor Day - 1st Monday in September Columbus Day - 2nd Monday in October Veteran’s Day - 11 November Thanksgiving Day - 4th Thursday in November Christmas Day - 25 December

If a holiday falls on a Saturday, the preceding Friday will be observed. If a holiday falls on Sunday, the following Monday will be observed. If a holiday falls on a scheduled service day, the Contractor will be responsible for rescheduling services for the first day after the holiday observance.

4.3.2. Other Base Closures. Work scheduled but not accomplished because of base closure due to exercises or real-world events will be accomplished as soon as possible after base reopening.

4.5. PERFORMANCE OF SERVICE DURING CRISIS OR HEIGHTENED SECURITY

The services under this contract are not essential for performance during crisis. The CO will determine circumstances which constitute a crisis based on direction from Security Forces and base leadership.

4.6. CONTRACTOR WORK SCHEDULE

4.6.1. Schedule Submission and Approval. The Contractor shall submit a schedule for all services described in this PWS and Appendices to the CO for approval at the post-award conference. The schedule shall include routes, pickup points, times, and days that pickups will occur. The Contractor shall not deviate from the approved schedule without prior approval from the CO or COR. Permanent changes to the schedule must be submitted 10 days before implementation and receive CO approval before the Government will allow the proposed changes. The schedule must be submitted electronically using a file format compatible with Government software.

4.6.2. Schedule Changes. Occurrence based (non-permanent) schedule changes due to customer requests or base exercises shall be submitted to the COR and require CO approval.

4.7. CONTRACT PERSONNEL

4.7.1. Contract Manager. The contractor shall establish and maintain an office through which the contract manager or alternate(s) can be contacted during work hours. The contract manager or alternate shall be available during normal duty hours to meet on the installation within 1 hour with the government personnel designated by the CO to discuss problem areas. The contractor shall provide the CO telephone number(s) where validation results and complaints can be reported. The contractor shall also provide to the CO the names and phone numbers of contractor POCs for after business hours including nights, weekends, and holidays. This information will be kept updated by the contractor whenever personnel changes occur. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to the daily operation of this contract.

4.7.2. Personnel. Contractor personnel shall present a neat appearance. Contractor personnel shall be easily recognizable while on the installation in conjunction with this contract. This shall be accomplished through the wear of distinctive clothing, overcoats, or hats, bearing the company name or logo. The coloring or design of the items selected should be such that identifies personnel easily and quickly for reasons of safety and personal protection.

4.7.3. Employee Restrictions. The government is authorized to restrict employment under the contract of any contractor employee or prospective contractor employee who is identified as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.

4.8. SECURITY REQUIREMENTS.

Contractor employees shall comply with Pittsburgh ARS security requirements (imposed by the Installation Commander), while on Pittsburgh ARS premises. The Contractor shall obtain all necessary passes, decals, badges, or other items required for access to perform contract services at Pittsburgh ARS. The Contractor is responsible for accountability of all such media, which shall be surrendered to the Security Forces Squadron Pass and Registration Section upon completion or termination of the contract or upon termination of an individual’s employment for the Contractor. The Contractor shall comply with all Pittsburgh ARS policies regarding entry to the installation, rules of the road, contingency operations compliance, and photography prohibitions. Contractor employees are authorized entry to the installation for the purpose of work under this contract only and are not authorized in other facilities or areas without prior government authorization. Due to safety/security requirements, Contractor personnel shall be required to fluently speak, comprehend, read, and write English.

4.8.1. Base Access. The Contractor must be aware that entry requirements are subject to change due to installation and world situations. All employees may be subject to a background check through the FBI for base access.

4.8.2. Main Base Access. Current security access restrictions at main base entry gate require all contractor vehicles to enter through the vehicle inspection station, building (106) before entering the main gate access. Contractor vehicles may be subject to search prior to gaining base entry. The Contractor should plan and allow for delays as a result of increased and ever- changing security procedures.

4.8.2.1. Security Authority. The Contractor shall brief all employees that they shall immediately leave any area upon notification by the CO, COR, constituted authority, Security Forces, or when directed as occasional operational requirements, real world activities, or emergencies dictate.

4.9.4. Restricted/Controlled Areas. Contractor performance within restricted/controlled areas shall require Contractor compliance with various levels of security and established personnel security entry control procedures. The Contractor shall ensure all contractor employees performing services in secured areas are processed for a controlled area, limited access, or visitor badge by the Entry Controller of the restricted/controlled area.

4.9.4.1. Access Coordination. The facility manager/user/occupant/requester will be responsible for providing access, escorts, or temporary visitor access badges for contractor personnel while performing ISWM duties. The Contractor shall be responsible for scheduling access/escorts/badges by contacting the facility manager/requester at the Entry Control Point of the restricted/controlled area.

4.9.4.2. Escorts. At all times while in restricted/controlled areas, contractor employees shall be under direct surveillance of a person from that facility who is cleared to wear a controlled area badge and perform escort duties. Visitor badges shall be returned to the Entry Controller each time the employee completes the duties and leaves the area. This requirement is waived for contractor personnel who have unescorted access privileges and display a controlled area badge for the restricted/controlled areas.

4.9.5.1. Access Revocation. The Pittsburgh ARS Installation Commander reserves the right to deny restricted area entry to any contractor employee whose NAC is unfavorable, and the right to terminate the entry of any employee upon disclosure of information indicating the individual’s continued entry to a secure area is not in the best interest of national security.

4.9.5.2. Contract Personnel Requirements. The Contractor shall not employ persons for work on this contract who are identified to the Contractor by the CO as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.

4.9.6. Contractor Vehicles. Contractor vehicles must be maintained in a safe and operational condition at all times while on Pittsburgh ARS.

4.9.7. Reporting Requirements. Contractor personnel shall report to an appropriate authority any information or circumstances of which they are aware may pose a threat to the security or well-being of DoD personnel, contractor personnel, resources, and classified or unclassified defense information.

4.10. SAFETY REQUIREMENTS AND REPORTS. The contractor shall perform work in a safe manner as required by OSHA Safety and Health Requirements. Provide a verbal report to the CO as soon as possible of each occurrence of damage to Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of required Accident Investigation Reports to the CO within five calendar days of each occurrence.

4.11. SPECIAL QUALIFICATIONS. Drivers of refuse and cardboard collection trucks are required to have an active Commercial Driver’s License (CDL).

4.12. CONTRACTING OFFICER AND CONTRACTING OFFICER REPRESENTATIVE. (QUALITY ASSURANCE PERSONNEL) The Contracting Officer will appoint a primary and alternate representative for management of the day-to-day activities of the contract. The identity, title, and authority of this representative will be provided in writing to the contractor after contract award.

4.13. MULTI-FUNCTIONAL TEAM. The Senior Leadership may require a multi-functional team be established between the government and the contractor to ensure joint cooperation and a sound customer focus of all parties involved in the execution of this contract.

4.14. DAMAGES TO GOVERNMENT BUILDINGS, EQUIPMENT, OR VEGETATION Damages to government buildings, equipment, or vegetation are addressed in FAR 52.237-2, Protection of Government Buildings, Equipment, and Vegetation.

5. APPENDICES.

APPENDIX A

Table A1. Estimated Workload Data Table A2. Tasks and Estimated Frequencies

APPENDIX B

Maps and/or Site Plans

APPENDIX A

TABLE A1 - ESTIMATED WORKLOAD DATA

ITEM

NAME

ANNUAL ESTIMATED QUANTITY

1
Municipal Solid Waste
65
Tons
2
Cardboard Recyclables
25
Tons
3
Special Event Container Placements
1
Each
4
Construction and Demolition (C&D) Container Placement

Each

5
Construction and Demolition (C&D) Debris
60
Tons

ONE WAY

6
Distance To Disposal Site
32
Miles
7
Distance To Recyclable Processing Center
40
Miles

TABLE A2 - TASKS & FREQUENCIES

COLLECTION STATION

LOCATION

SIZE

TYPE

FREQUENCY

1
320
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
2
333
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
3
316
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
4
312
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
5
213
6 CY (2)
MUNICIPAL SOLID WASTE
1x/Week Thursday
6
300
6 CY (2)
MUNICIPAL SOLID WASTE
1x/Week Thursday
7
411
6 CY (2)
MUNICIPAL SOLID WASTE
1x/Week Thursday
8
405
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
9
420
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
10
416
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
11
130
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
12
125
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
13
120
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
14
110
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
15
208
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
16
221
6 CY
MUNICIPAL SOLID WASTE
1x/Week Thursday
C&D
342
30 CY
C & D
Monthly
1 Cardboard
416
6 CY
RECYCLING
Monthly
2 Cardboard
300
6 CY
RECYCLING
Monthly
3 Cardboard
213
6 CY
RECYCLING
Monthly
4 Cardboard
335
6 CY
RECYCLING
Monthly

APPENDIX B

Numerical Haul Route and Refuse / Cardboard Container Location / Size (See Map Legend). Map Located on Page 14

BASE STREET MAP

HAUL ROUTES (Identified on the Base Street Map in Numerical Sequence)
CARDBOARD RECYCLING STATIONS (Identified by Colors and Geometrical Symbols within the Map Legend)
MUNICIPAL SOLID WASTE COLLECTION STATIONS (MSW, Identified by Colors and Geometrical Symbols within the Map Legend)
WEIGH STATION (Identified on the map as “scale”)
PERTINENT GOVERNMENT OFFICES (Identified on the map as Contracting Officer CO and Contracting Officer Representative COR)