Attachment 1 - Performance Work Statement.pdf
PDF 211 KB Posted
- Attached to
- Cytiva Equipment Service Contract Federal contract opportunity
- Solicitation number
- 1232SA25Q0632
About this file
This Performance Work Statement (PWS) is for preventive maintenance services of Cytiva scientific equipment at the National Bio and Agro-Defense Facility (NBAF) in Manhattan, Kansas, for the United States Department of Agriculture's Agricultural Research Service. The Biologics Development Module (BDM) requires maintenance for three specific Cytiva equipment pieces: two chromatographic units (Äkta avant and Äkta pure) and one surface plasmon resonance unit (Biacore S200). The contract period is one year, with work to be performed during normal business hours (7:00 am - 5:00 pm, Monday-Friday), and the contractor must provide comprehensive maintenance including thorough equipment inspections, functional testing, part replacements, calibration verification, and detailed documentation. Key performance requirements include adhering to local/state/federal codes, working collaboratively with USDA personnel, following NBAF safety and quality standards, and meeting manufacturer specifications. The Quality Assurance Surveillance Plan outlines multiple inspection methods, including 100% inspection, periodic inspection, random inspection, performance evaluation meetings, and personnel feedback to ensure contract compliance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend 1 - Clauses and Provisions - 1232SA25Q0632.pdf | ||
| Amend 1 - SF-30.pdf | ||
| Clauses and Provisions - 1232SA25Q0632.pdf | ||
| Attachment 2 - Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
Performance Work Statement
Project: Cytiva Equipment National Bio and Agro-Defense Facility USDA-ARS, Manhattan, KS
Contents
1. PURPOSE
2. MISSION AND BACKGROUND
3. PERIOD AND LOCATION OF PERFORMANCE
4. CONTRACTOR PERSONNEL
5. GOVERNMENT PERSONNEL
6. PERFORMANCE REQUIREMENTS
7. OPERATING CONTRAINTS AND ANY ADDITIONAL REQUIREMENTS
8. QUALITY ASSURANCE SURVEILLANCE PLAN
1. PURPOSE
This Performance Work Statement for Cytiva equipment will describe the work in terms of the required results and enable assessment of work performance against measurable performance standards. The equipment was purchased and operated by government employees and is located at the National Bio and Agro-Defense Facility (NBAF) in Manhattan, Kansas.
Acronyms Summary:
ARS: Agricultural Research Services BDM: Biological Development Module CO: Contracting Officer COR: Contracting Officer’s Representative CUI:
Controlled Unclassified Information FAR: Federal Acquisition Regulation ISO: International Organization for Standardization NBAF: National Bio and Agro-Defense Facility NDA:
Non-Disclosure Agreement POP: Period of Performance PRS: Performance Requirements Summary PWS:
Performance Work Statement QA: Quality Assurance QASP: Quality Assurance Surveillance Plan USDA:
United States Department of Agriculture
2. MISSION AND BACKGROUND
The NBAF provides and strengthens the nation with critical capabilities to diagnose animal diseases, to conduct research and develop vaccines and other countermeasures, and to train veterinarians and other scientists in preparedness and response to disease outbreaks. NBAF’s mission is to protect the United States against transboundary, emerging, and zoonotic animal diseases that threaten our food supply, agricultural economy, and public health. NBAF’s vision is to create a safer and more resilient America through a world-class science facility for large animal agricultural research, training, and diagnostics.
The mission of the Biologics Development Module (BDM) within the NBAF is to directly support and accelerate technology transfer of vaccines, diagnostics, biotherapeutics, and other veterinary medical countermeasures for development to commercial veterinary biologic manufacturers and other partners.
BDM efforts include, but are not limited to, the production of attenuated viral and bacterial master seeds, master cells for viral vaccine production, monoclonal antibodies, small scale viral and bacterial (attenuated or inactivated) vaccines, recombinant proteins, and diagnostic reagents. The BDM also provides dedicated space for formulation manufacture of experimental products for clinical studies, support the early development of veterinary medical countermeasures, implementation of quality assurance and quality control measures, and support the technology transfer to potential future commercial manufacturers. It is through these efforts and provisions, that the BDM envisions putting impactful biologics solutions into the hands of farmers, producers, and veterinarians through a focus on quality and collaboration with cutting-edge science institutions and biologics manufacturers.
3. SCOPE
The BDM needs maintained scientific equipment to meet its scientific, quality, and research goals and objectives. These preventive maintenance services need to be well-documented and properly coordinated to ensure well-maintained and effectively functioning scientific equipment.
The quantity of equipment needed to be maintained each year is expected to vary slightly based on the growth of the lab. Currently, three (3) cytiva equipment, two (2) chromatographic units and one (1) surface plasmon resonance unit, need preventative maintenance. In the future, Uniflux TFF and XDUOR mixer may also be added to the list of preventative maintenance. Contract modifications may be needed to update scientific equipment inventory numbers during the period of performance of this purchase order.
4. PERIOD AND LOCATION OF PERFORMANCE
The period of performance (POP) must be for one (1) Year of 12 months.
The work must be scheduled during normal business hours of the NBAF between 7:00 am and 5:00 pm local time; Monday – Friday. Work completed after hours or on weekends and/or holidays will be proposed at least a week in advance of the requested work time and may be coordinated and reviewed in conjunction with the Contracting Officer/Contracting Officer’s Representative.
Federally Observed Holidays:
New Year’s Day Martin Luther King’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans’ Day Thanksgiving Day Christmas Day
5. CONTRACTOR PERSONNEL
Identification:
All contract personnel attending meetings, answering government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are USDA/government officials.
They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.
For NBAF Facility security purposes, the contractor must provide the CO a list of all employees who will perform work under this contract. The list must include name and work assignment of each employee.
The contractor must maintain revisions and updates to this list and submit them to the COR monthly as needed. The contractor must furnish each employee a contract identification badge that must be conspicuously displayed when working. The ID badge must include the full name of the employee, company name, a badge serial number.
Conduct:
The CO may require the contractor to remove any employee(s) from the contract and worksite for nonperformance, misconduct, or failure to abide by all laws and regulations. The contractor must immediately comply with these requests. The following is not an all-inclusive list of conduct expectations:
1. There must be no fraternization or interference with the work of employees at the NBAF.
2. There must be no violation of the GSA Publication; Rules and Regulations Governing Conduct on
Federal Property (Federal Management Regulation Title 41, Code of Federal Regulations, Part 102- 74, Sub-Part C, November 2005).
3. Contractor personnel’s conduct must not reflect discredit upon USDA-ARS.
4. The contractor must ensure that personnel present a professional appearance.
5. The contractor’s employees must observe and comply with all NBAF and local policies and procedures concerning fire, safety, environmental protection, sanitation, security, and possession of firearms or other lethal or illegal weapons or substance. The contractor is responsible for ensuring that any contractor employees or subcontractor providing services under this contract conduct themselves and perform services in a professional, safe, and responsible manner.
6. The contractor must remove from the job site any employee or subcontractor for reasons of misconduct or security.
7. Neglect of Duties - includes sleeping on duty, failure to be attentive to assigned duties, failure to carry out assigned tasks, conducting personal business during duty hours.
8. Disorderly Conduct - e.g., the use of abusive or offensive language, quarreling, intimidation by words, actions, fighting, or participation in disruptive activities which interfere with normal and efficient operations of the NBAF or any organization or function on the NBAF Campus.
9. Criminal Actions - e.g., falsification or unlawful concealment, removal, mutilation, or destruction of any official documents, reports, or records, unauthorized use of government property, theft, vandalism, immoral conduct, organizing or participating in gambling of any form, unethical, improper, or fraudulent use of official authority or identification, the unauthorized, improper, or fraudulent use of communications equipment.
10. Release of Information - all contractor employees must be prohibited from releasing any information pertaining to duty assignments, manpower, personnel, or other information to any outside organization or person(s), without the explicit, written consent of the CO or COR.
11. Violations of Security Procedures or Regulations - includes violations of established security procedures, policies, regulations, or guidelines, as well as failure to report to appropriate security officials any unauthorized security activity, observed or otherwise known to have occurred, or which is about to occur, on or which could affect USDA, APHIS, ARS, any specific organization or mission within USDA, or the security posture of the NBAF.
12. Particular attention should be paid to acceptance of gifts/ gratuities, and on non-disclosure of sensitive or classified information.
13. The contractor must ensure employee or subcontractor conduct complies with 41 USC 423 relative to release of acquisition related information, or actions or discussions which may prejudice future competitions.
14. The contractor must ensure no contractor employees conduct political related activities or events on the Installation.
Furnished Items and Responsibilities:
The contractor must furnish all personnel, equipment, materials, supplies, services, and shipping costs required to achieve the performance requirements of the work in this contract, unless otherwise specified herein. The certifying engineer/technician performing work under this contract must safeguard all USDA- ARS equipment, information and property provided for contractor use. At the close of each work period, USDA-ARS facilities, equipment, and materials must be secured.
The contractor must provide a plan for the completion of the work outlined in this PWS and submit to the COR at a minimum of seven days (7) prior the start of work.
Conference / Performance Evaluation Meetings:
The contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The CO and COR must have performance evaluation meetings with the contractor to review the contractor's performance as needed. At these meetings the CO will apprise the contractor of how the government views the contractor's performance and the contractor will apprise USDA-ARS of problems, if any, being experienced.
Appropriate action must be taken to resolve outstanding issues. Meetings may be held at any time thereafter.
6. GOVERNMENT PERSONNEL
Provisions:
1. The government must provide access to spaces with equipment maintenance needs.
2. The government will provide documentation to confirm that the laboratory spaces have not been exposed to biological hazards or have been properly decontaminated and do not pose human exposure risk.
3. The government will provide escorts for necessary contractor personnel when onsite.
4. The government will provide training onsite for emergency procedures such as weather, fire, and any necessary biosafety practices that must be adhered to, as needed.
5. The government will communicate any additional equipment information/changes as required by the vendor during the contract.
Contracting Officer’s Representative (COR):
The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: Assure that the contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including government drawings, designs, and specifications;
monitor contractor's performance and notifies both the CO and contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of contractor personnel. The COR is not authorized to change any of the terms and conditions of the resulting order.
7. PERFORMANCE REQUIREMENTS
1. All services must meet all Local, State and Federal codes.
2. The Contractor will work with USDA personnel to ensure project is accomplished in a timely manner.
3. The contractor must perform work in accordance with NBAF’s safety and quality standards.
4. The contractor must perform work in accordance with the manufacturer's specifications.
5. The contractor must work with the BDM quality specialist to determine an equipment maintenance service schedule.
a. This schedule once defined will be adhered to with no exceptions by the contractor and/or government unless adequate justification is provided and communicated to all parties.
6. The contractor will provide adequate records to ensure documented evidence of maintenance status for internal and external audit purposes.
7. The contractor will be able to provide onsite maintenance services for the following identified equipment on a yearly basis
8. The contractor will perform thorough inspection of instruments, extensive set of functional tests, replace wear and tear parts, and provide a detailed visit record; verify calibration of uv probe and check the integrity of the tubing and the cleanness of the fittings
Identified Equipment Brand/Make Model Quantity
Äkta avant Cytiva 25 1
Äkta pure Cytiva 25 1
Biacore Cytiva S200 1
9. The contractor will provide the best practice recommendations for preventative maintenance, and routine cleaning of the equipment.
10. The contractor agrees to discuss any issues or actions that need improvement with the government and provide feedback or improvements as needed.
8. OPERATING CONTRAINTS AND ANY ADDITIONAL REQUIREMENTS
Security Requirements:
Personnel employed by the contractor or any representative of, or agent of the contractor, entering this facility must conform to the facility security regulations. The contractor must provide all information required for background checks to meet facility access requirements as performed by the facility security office. Contractor personnel must comply with all personal identity verification requirements as directed by USDA-ARS Security office. Each person accessing the site will be required to provide personal details, (full name, DOB, SSN, DL#) and will undergo a routine background check, such as a National Agency Check with additional inquiries, which may include a criminal and credit check. Details required for the check should be submitted to the security office no later than 5 days prior to the visit. Results of this check may be returned earlier; however, it should not be planned to have results earlier than 5 days. If, while on site the contractor/vendor will have access to sensitive information, they must complete a Non- Disclosure Agreement, along with the required training. This training will most likely be completed by reviewing a series of slides covering the topics of the definition of controlled unclassified information (CUI), access, handling, distribution, storage, and destruction of CUI. Each person will acknowledge receiving and understanding the training on the NDA. The process should not exceed two hours.
Acknowledgement and completion of the NDA will be turned in with the form required for the background check. Results will be returned through the Contracting Officer or Contracting Officer Representative.
The contractor and/or any representative of, or agent of the contractor, entering this facility must conform to the visitor and escorting policies. All visitors must display an appropriate badge and/or other identifying credentials. All visitor(s) have their government issued photo I.D. or equivalent, in addition to, NBAF issued visitor badge available for upon request by security personnel while on the NBAF. Visitors must sign applicable visitor log upon entrance and exit and stay with the escort at all times. The contractor and/or any representative of, or agent of the contractor must not take photography of the interior or exterior of the
NBAF from within the NBAF property. The contractor and/or any representative of, or agent of the contractor, entering this facility must comply with all USDA and NBAF procedures and/or policies (e.g., Rules and Regulations Governing Conduct on Federal Property Title 41 CFR Part 102) and submit to searches by security personnel of their person, personal effects, and vehicles as per 41 CFR 102-74.370.
9. QUALITY ASSURANCE SURVEILLANCE PLAN
This Quality Assurance Surveillance Plan (QASP) is a government developed and applied document used to provide a standard of surveillance for monitoring the maintenance of equipment contract.
This QASP establishes the approach the government will use to conduct surveillance of the contractor’s quality control. The intent is to ensure that the contractor performs in accordance with performance requirements set forth in the contract documents, that the government receives the quality of services called for in the contract, and that the government only pays for the acceptable level of services received.
The contractor is responsible for management and quality control actions to meet the terms of the contract.
The role of the government’s quality assurance (QA) representative (BDM Quality Specialist) is to ensure the contractor performs quality control to adequately meet contract standards. USDA-ARS performance assessments will be assigned to and authorized by the COR. The COR will evaluate the contractor's performance under the Quality Assurance Surveillance Plan (QASP).
From the start of the contract, all contractor operational procedures and quality assurance measures will be tested and implemented. As the performance period progresses, the levels of surveillance may be altered for service areas in cases where performance is either consistently excellent or consistently unsatisfactory.
If observations reveal consistently good performance, then the amount of surveillance may be reduced. If observations reveal consistent deficiencies, increased surveillance may be implemented.
Although USDA-ARS may develop a Quality Assurance Surveillance Plan, USDA-ARS surveillance of contractor performance is not limited to the QASP or the performance objectives, incentives/remedies, etc.
USDA-ARS has the right to inspect and test all services called for by the contract and commitments made by the contractor during the solicitation process, to the extent practicable at all places and times during the term of the contract. USDA-ARS will perform inspections and tests in a manner that will not unduly delay the work. If any of the services performed do not conform to contract requirements, USDA-ARS may require the contractor to perform the services again in conformity with contract requirements, at no increase in contract amount. When the defects in services cannot be corrected by re-performance, USDA-ARS may:
(1) require the contractor to take necessary action to ensure that future performance conform to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed. If the contractor fails to promptly perform the services again or take the action necessary to ensure future performance in conformity with contract requirements, USDA-ARS may: (1) by contract or otherwise, perform the services and charge to the contractor any cost incurred by USDA- ARS that is directly related to the performance of such service, or (2) terminate the contract for default. "Services", as used in this clause, includes services performed, workmanship, and material furnished or used in performing services.
The contractor’s routine performance is evaluated objectively against the performance-based standards provided in the PWS. The basis of performance-based contracting allows for some flexibility in enforcement to encourage innovation by the contractor in achieving the desired results. The government has the right to inspect and test all services called for in the contract. When services are deficient and cannot be re-performed satisfactorily by the contractor, the government will refer to the Inspection of Services clause for remediation.
Methods of Inspection:
The below listed methods of surveillance may be used in the administration of this QASP. They can occur quarterly, monthly, or as needed:
1. 100% Inspection
a. The COR may conduct 100% inspections of the work defined in the PWS. The COR will also review information submitted in the required reports defined in the PWS (if applicable).
2. Periodic Inspection
a. The government may conduct periodic inspections monthly, quarterly, or on an as-needed basis. The periodic inspection shall be conducted by the COR.
3. Random Inspection
a. The government may conduct random monitoring by reviewing information/reports required and submitted in accordance with the contract. The random monitoring shall be performed by the COR.
4. Performance Evaluation Meetings
a. The contractor and the COR will meet as often as necessary to review the contractor’s performance and address any discrepancies that have been noted during the period of performance. A mutual effort will be made to resolve identified issues.
5. Personnel Feedback
a. The COR may provide and collect BDM personnel surveys or complaints regarding performance. A mutual effort will be made to resolve any problems/issues identified.
Level of surveillance may be conducted on a monthly, quarterly, or as-needed basis and an analysis of the results will determine if the contractor met the standards or did not met the standards identified in the PWS/contract.
Performance Requirements Summary (PRS):
Performance Objective Acceptable Quality Level Method of Inspection
All services must meet all Local, State and Federal codes.
0 Local, State and Federal codes broken during the period of performance.
100% Inspection
The Contractor will work with USDA personnel to ensure project is accomplished in a timely manner.
All equipment that requires preventive maintenance will be scheduled out in a manner that no equipment loses its maintenance status, unless otherwise justified, documented, and communicated by all parties.
Periodic Inspection
The contractor must perform work in accordance with NBAF’s safety and quality standards.
The contractor will attend provided training listed in Section 8 and read and understand the BDM Visitor and Quality Policy as required. This training will not exceed 4 hours in total.
Personnel Feedback, and Periodic Inspection
The contractor must perform work in accordance with the manufacturer's specifications.
Manufacturers specifications referenced, and work done will be defined and shared with the BDM Quality Specialist.
100% Inspection
The contractor must work with the BDM quality specialist to determine a equipment maintenance schedule.
A maintenance schedule is created in collaboration with the BDM quality specialist within 30 days of being awarded the contract, and the schedule is adhered to, with any deviations noted, discussed, and justified.
Periodic Inspection
The contractor will provide adequate records to ensure documented evidence of maintenance status for internal and external audit purposes.
Formal paperwork and certification status documentation will be issued by the vendor to the government and then maintained by the government.
Any maintenance requirements, suggestions, or issues discussed will be documented at the time of inspection and service by the vendor.
100% Inspection, and Random Inspection
The contractor will be able to provide maintenance services for the following identified equipment on a yearly basis to the manufacturer’s standard.
The identified equipment are maintained on a yearly basis with minor additions or subtractions being documented and justified.
100% Inspection
The contractor will be able to provide onsite calibration services for the following identified equipment on a yearly basis.
The identified equipment pieces are calibrated on a yearly basis with minor additions or subtractions being documented and justified.
100% Inspection
The contractor will provide best practice recommendation for preventative maintenance, and routine cleaning of the equipment.
Technical expertise is provided by the maintenance specialist (or equivalent role) in either electronic or paper format of recommendations for preventative maintenance, and routine cleaning of the scientific equipment.
Personnel Feedback, and Periodic Inspection
The contractor agrees to discuss any issues or actions that need improvement with the government and provide feedback or improvements as needed.
Communications are kept open and honest between the COR, CO, and contractor.
Regular meetings are held depending on the nature and requirements of the contract.
Meeting requirements and frequency will be defined by the COR in coordination with the contractor within 30 days of awarding the contract.
Early on in scheduling/awarding it is expected that communication will happen on a daily or weekly frequency, but between maintenance dates, several months might lapse with no needed communication/meetings.
Performance Evaluation Meetings
Effective contract surveillance relies on the COR identifying and documenting discrepancies during performance of routine daily services, or through the period of performance of the contract. The COR will report discrepancies to the contractor for timely resolution. Surveillance may consist of periodic reports, and customer feedback and timeliness of contract deliverables/reports. The COR will maintain a complete QA file which will be retained by the COR for the life of the contract. Information in the QA file will be considered when completing the annual CPARS report.
| 1. PURPOSE |
| 2. MISSION AND BACKGROUND |
| 3. SCOPE |
| 4. PERIOD AND LOCATION OF PERFORMANCE |
| Federally Observed Holidays: |
| 5. CONTRACTOR PERSONNEL |
| Identification: |
| Conduct: |
| Furnished Items and Responsibilities: |
| Conference / Performance Evaluation Meetings: |
| 6. GOVERNMENT PERSONNEL |
| Provisions: |
| Contracting Officer’s Representative (COR): |
| 7. PERFORMANCE REQUIREMENTS |
| 8. OPERATING CONTRAINTS AND ANY ADDITIONAL REQUIREMENTS |
| Security Requirements: |
| 9. QUALITY ASSURANCE SURVEILLANCE PLAN |
| Methods of Inspection: |