This document includes a purchase description and solicitation for two coordinated measuring machines. The purchase description provides technical requirements for the machines, including specifications for measurement accuracy and range, scanning speed, software capabilities, and training requirements. It also lists standards and publications that systems must comply with.

The solicitation is issued by the Department of the Army Materiel Command Contracting Command and seeks proposals for the coordinated measuring machines along with advanced training. Proposals are due by February 23, 2024 and must include completed pricing sheets and signed representations. The government intends to make award without discussions to the responsible offeror providing the most reasonable price. Delivery within 30-60 days of award is required to Crane Army Ammunition Activity in Indiana.

View the file

Other files for this federal contract opportunity

Other files attached to ZEISS COORDINATE MEASURING MACHINES, newest first.
File Type Posted
Amendment 002.pdf PDF
Amendment 001.docx DOCX document
Attachment 04 Redacted LSJ CMM.pdf PDF
Attachment 03- Pricing Sheet.xlsx XLSX spreadsheet
Attachment 01 SF1449 W519TC.24.Q.2147 CMM Per PWS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Description of Requirement Crane Army Ammunition Activity (CAAA) Coordinate Measuring Machine (CMM) Modernization Project

1. GENERAL SYSTEM DESCRIPTION

Crane Army Ammunition Activity (CAAA), Crane, IN, is looking to modernize its inspection equipment by replacing its old Coordinate Measuring Machines (CMMs). Due to increasingly complex parts, quality requirements, and increased production throughput, as well the loss of tribal knowledge of outdated programs and equipment CAAA has recognized a need to replace old equipment that is critical to meet current quality goals. These new CMMs would also allow CAAA to measure with higher accuracy providing customers with higher confidence in CAAA measuring capabilities.

CAAA is in an immediate need of two (2) bridge style, CMMs with updated tactile measuring capabilities. The CMMs shall be run on air bearings and shall have ability to contact scan (passively or actively) the form of features and parts as well as perform single and multi-point measurements with a scanning error of less than .00012”, single point error of less than .000079” and repeatability of at least .000079”. Probe shall also be able to articulate with a front-to-back and lateral tilt range of ±180° with a minimum rotation increment of 2.5° with automatic angular correction for all probing points. CMMs shall come with an automatic probe changer for running fully automated programs that require different probe length/sizes. CMMs shall be able to travel up to 15 inches per second and scan at 5 inches per second to help accommodate timely part throughput. CMMs shall have a measuring range of at least 35 inches in the X- axis, 47 inches in the Y-axis, and 23 inches in the Z-axis. CMM shall come ready to install and include any filters and dryers needed for air lines and have the power requirements of 100-240V (50-60Hz). Must have a rotary table.

CMM control software shall be graphically based and not require coding skills or manually entered drive points to create and run a measurement programs. Control software must run on an included computer system including computer, monitor, mouse, keyboard, printer, and can connect with a hardwired network system for storage backup and program recall. Software shall be able to program, calculate, and output all geometric dimensioning and tolerancing (GD&T) functions and relationships required to determine is a part is acceptable based on blueprints and technical data packages. Software must be able to be programed with or without a CAD model availability. If CAD model is available, software must be able to create and run a program with minimal operator input. Created programs shall be able to be run automatically and be able to create customized physical (printed) and digital reports on intended and found measurements, as well as report pass/fail conditions. Software shall be able to identify quickest possible travel path and probing sequence to optimize program for time and efficiency. Multiple programs shall be able to be loaded at once, so multiple parts can be checked at same time. Training for software shall be included in total price of the machine for up to six operators. CMM Program and Hardware shall come with a minimum of 1 year remote service support.

CMMs shall have modular capacities for use with future additions to the machine to allow for future modernization. CMM shall have ability to easily switch out measuring devices or probes to support active scanning functions, profilometer functions, and 3D non touch optical scanning with either white light functionality and/or triangulation laser technology.

A single CMM cannot exceed the following footprint: length 87.5 inches, width 62.5 inches, and height of 105 inches. CMMs must be able to fit through an entrance that is 6 feet wide by 7 feet tall.

All the above components shall be of brand name or equivalent from the same manufacturer to guarantee interoperability without modification.

The Contractor shall provide operation and maintenance manuals.

The Contractor shall install, calibrate, and provide a calibration certificate traceable back to a national standards.

The Contractor shall provide training for equipment and software for up to six people.

2. BRAND NAME

The following is known equipment that meet the requirements in section 1:

2.1 (2X) Zeiss Contura 9/12/6:

Control Interface
Refrigerated Air Dryer
RDS-D Articulating Sensor Holder
Vast XXT TL3 Sensor
RDS-Vast XXT Adapter Plate
30mm Reference Sphere/Holder
Multi-Sensor Rack
3 Position Rack for Vast XXT TL3 plates
Probe Change Socket
Stylus Adapter Plate for Vast XXT TL3 (X3)
Starting Stylus Kit for Vast XXT Sensor

Profilometer Attachment Rotary Table One Printer per CMM (Black, White, Color capability)

Workstation/Computer Bundle
Calypso Software Package
Zeiss Service (1 year)
Calypso Basic Training (X6)
Calypso Advanced Training (X6)

Installation/Verification

3. STANDARDS AND PUBLICATIONS

3.1 NATIONAL STANDARDS AND SPECIFICATIONS: The following specifications in effect on the Date of Invitation for Bid/Request for Proposal form a part of this description of requirement. In the case of conflicting requirements, the more stringent shall apply.

3.1.1 American National Standards Institute (ANSI).

3.1.2 Occupational Safety and Health Act of 1970 (OSHA).

3.1.3 American Society of Testing and Materials (ASTM).

3.1.4 American Society of Mechanical Engineers (ASME).

3.1.5 National Electrical Manufacturers Association Standards (NEMA).

3.1.6 Institute of Electrical and Electronics Engineers (IEEE).

3.1.7 American Code for Information Exchange (ASCII).

3.1.8 National Fire Protection Association (NFPA).

3.1.8.1 NFPA-70 National Electrical Code

3.1.8.2 NFPA-79 Electrical Standard for Industrial Machinery.

3.1.9 International Standard (ISO) 10360 Geometrical Product Specifications

4. DESIGN REQUIREMENTS

4.1 OWNERSHIP: This equipment is a standard product of the manufacturer and shall require either no change, or minor design changes, to meet requirements of these specifications. Therefore, ownership of the design will remain with the manufacturer.

4.2 GENERAL DESIGN STANDARDS

4.2.1 DEVIATION FROM PRODUCT: Modifications to the manufacturer’s standard design to achieve requirements as specified in this document are only permissible as dictated by good design practice. For example, mounting a 20-hp motor in a power train designed and normally using a 10-hp motor would not be acceptable.

4.2.2 UNITS OF MEASURE: Dimensions and capacities in this purchase description are given in the English-US (in-Lb.) system. All dials, gauges, and drawings shall be in the English-US system or both the English-US and the metric systems, unless otherwise specified in this document.

4.2.3 DATA PLATES: All instruction, data, and identification plates and labels attached to this equipment and its controls shall be manufactured of corrosion and oil resistant metal or plastic material. All wording shall be in the English language using plain, bold face lettering. Lettering shall be permanent and have a contrasting background.

4.2.4 UTILITY CONNECTION: Equipment supplied to Crane Army Ammunition Activity will have single point shut-off for each utility supplied to a system. This means that equipment constituting a single system shall be wired to a single main electrical disconnect point, plumbed to a single pneumatic shut-off valve, etc. This will be referred to as the “point of first connection”. Each type of power source may have only one point of first connection. E.g. (1) pneumatic shut-off valve, (1) water supply shut-off valve, (1) electrical disconnect, etc. Each point of first connection shall be clearly labeled on the system and shown in the safety lockout portion of the documentation package. These points must be located on a stationary component and positioned such that they will not create a hazard to personnel during normal operation of the system. The first connection points shall be accessible from the shop floor without the use of ladders, steps, or stools. Access cannot be hampered by operation of the system.

4.2.5 DEFLECTION: The system shall recover from distortion and deflection at no load. The machine and its components shall be sufficiently rigid that work piece finish and tolerances are not impaired by machine vibration.

4.2.6 NEW EQUIPMENT: The equipment furnished under this purchase description shall be new, unused, and not refurbished.

4.2.7 CASTINGS AND FORGINGS: All castings and forgings shall be free of defects, scale, and mismatching. No process such as welding, peening, plugging, or filling shall be used for reclaiming any defective part for use in this equipment without the prior written consent of the contracting officer.

4.2.8 SURFACE BUILDING AND COATINGS: Welding, brazing, soldering, coating or plating shall be employed only where specified in the original design. These operations may not be employed as a means of reclaiming a defective part.

4.2.9 FASTENING DEVICES: All screws, pins, bolts, and similar parts shall be installed in such a manner as to prevent change in tightness. Those devices subject to removal or adjustment shall not be swaged, peened, staked, or otherwise permanently deformed. They shall not be installed using permanent bonding adhesives.

4.2.10 CLEANING AND DEBURRING: All surfaces of castings, forgings, molded parts, stampings, and welded components shall be cleaned and free from sand, dirt, fins, flash, scale, flux, and other harmful or extraneous materials. All edges shall be either rounded or beveled unless sharpness is required to perform a necessary function. Except as specified herein, the condition and finish of all surfaces shall be commensurate with the manufacturer’s commercial practice.

4.2.11 PAINTING: All unfinished surfaces of the equipment shall be painted with a lead free and chromium free commercial grade of metal primer and a minimum of one finish coat. The color shall be in accordance with the manufacturer’s standard commercial practice, or as necessary to maintain compliance with OSHA regulations, as applicable.

4.2.12 LUBRICATION: Components specified as requiring lubrication by the original manufacturer shall have an appropriate means of providing said lubrication included in the design of the machine. The lubrication points will be labeled on the lubrication drawing provided as part of the manual/maintenance documentation and will also be labeled on the machine at the lubrication point and on any access panel covering the lubrication point. These labels will include as a minimum standard, the specific type of lubricant, the quantity to be used, the frequency for change, and the maintenance manual reference for detailed instructions. The lettering shall be English and the units shall be English standard (i.e. pints, quarts, and gallons).

5. SAFETY AND ENVIRONMENTAL

5.1 INDUSTRY AND REGULATIONS: The equipment shall comply with the most current of all local, state, and federal laws and regulations listed in Standards and Publications.

5.2 MATERIAL EXCLUSIONS: The equipment shall not contain polychlorinated biphenyl (PCB), ozone depleting substances (Class I or Class II), or asbestos materials.

5.3 SAFETY REGULATION COMPLIANCE: The installation and use of electrical equipment at CAAA shall comply with the National Electrical Code (NFPA 70) or OSHA regulations (29 CFR 1910, Subpart S), whichever is more stringent. Electrical equipment installed at CAAA shall be approved by the Underwriters’ Laboratories (UL) or other recognized testing agency.

5.4 SAFETY LOCKOUTS: Each point of first connection shall be designed and constructed to allow the utility to be completely isolated from the equipment. This isolation shall be insured by application of a standard key locking padlock. The device(s) shall only be lockable in the de-energized (OFF) condition.

5.5 TRAPPED ENERGY: Means shall be provided for the controlled release of stored energy. This energy may be in the form of, but not limited to, air and hydraulic pressure accumulators, capacitors, springs, counter balances and flywheels. This is to allow for the safe release of energy in the event of electrical power loss. When appropriate, a label shall be affixed to the stored energy source to identify the hazard.

6. APPROVAL/SHIPPING

6.1 SHIPPING: The contractor is responsible for delivery of the equipment to Crane Army Ammunition Activity (a tenant on Naval Support Activity). Adequate preserving of equipment surfaces, packing, marking, and skidding of materials for shipment shall be the responsibility of the contractor. If special lifting devices, such as hooks or eyes, are required for ease of handling, they shall be supplied with the equipment. Any special devices shall be returned to the contractor upon request only if they will not be required for future movement of the equipment, and at the contractor’s expense.

6.2 INSTALLATION: Contractor is responsible for installation and initial calibration of equipment.