Attachment_01_SOW.pdf
PDF 98 KB Posted
- Attached to
- Pavement Marking from Slaters Ln to Roaches Run (N Federal contract opportunity
- Solicitation number
- 140D0423B0001
About this file
This document outlines the scope of work for a federal contract to provide pavement marking services on the George Washington Memorial Parkway in Virginia. The contract requires removing existing pavement markings and reapplying new markings along 2.25 miles of the parkway between Slaters Lane and Roaches Run according to the provided plans. Work must be performed in accordance with MUTCD standards and includes maintaining traffic during construction, removing old markings, installing temporary markings, applying permanent markings, and installing signs and wooden posts. The related solicitation was issued by the Department of the Interior's Interior Business Center for bids due on or before the unspecified date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_SOL_GWMP_Paving_IFB_solicitation_pgs_4-41.pdf | ||
| Attachment_04_Wage_Determination.txt | TXT text file | |
| Attachment_03_Schedule_of_Values.pdf | ||
| Attachment_02_DS_Plans.pdf | ||
| Sol_140D0423B0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project: Pavement Marking from Slaters Ln to Roaches Run (North and South Bounds)
Park: GWMP
PMIS: 317362
Scope of Work (SOW):
The work requires to provide the labor, equipment, and material needed to remove existing pavement markings and reapply new pavement markings according to the contract plans. The pavement marking material is specified on the schedule of values and it is described in the project specifications (FP‐14). The work includes lane lines, marker, symbols, sign, and wooden post installation. This project is for the north bound (NS) and south bound (SB) on George Washington Memorial Parkway (GWMP). This section of the parkway begins at Slaters Ln and ends at the exit onto the Ronald Reagan Washington National Airport traveling north (about
2.25 miles). The exact limits are shown on the contract plans. All pavement marking work will be in accordance with current Manual Uniform Traffic Control Devices (MUTCD) standards. The major work items include: (1) Maintenance of Traffic during construction, (2) Remove existing pavement markings, (3) Install temporary pavement markings, (4) Apply permanent pavement markings, (5) Install sign and wooden posts.