Attach-1-SOW.pdf

PDF 86 KB Posted

Attached to
WHITE RIVER NWR, GRAVEL Federal contract opportunity
Solicitation number
140F0220Q0047
Issued by
Department of the Interior Fish and Wildlife Service Region 2

View the file

Other files for this federal contract opportunity

Other files attached to WHITE RIVER NWR, GRAVEL, newest first.
File Type Posted
Attach-2-Aera Map.pdf PDF
Attach-3-Delivery Map.pdf PDF
Attach-4-Clauses.pdf PDF
Sol_140F0220Q0047.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL INFORMATION AND REQUIREMENTS

PART 1: GENERAL

1.1 PROJECT DESCRIPTION

A. Furnish all equipment, supplies, labor, and materials to provide and tailgate spread to a depth of 9 inches approximately 4,067 tons of SB2 Class 7 Crushed Stone, to the Maddox Bay area of Dale Bumpers White River National Wildlife Refuge (NWR), near Saint Charles, Arkansas.

Base Bid:

Furnish and 9 inch tailgate spread approximately 4,067 tons of SB2 Class 7 Crushed Stone to the Maddox Bay area of Dale Bumpers White River NWR (see map). Provide a price per ton inclusive of all costs, overhead, and profit.

B. Delivery POC: Site Visit. Contact Bo Sloan (870) 282-8205 email charles_sloan@fws.gov

C. Means and Methods. Means and methods are the contractors. Contractor may only use trucks/trailers capable of evenly spreading SB2 Class 7 Crushed Stone.

1.2 COST

A. Contractor must provide a price per ton.

B. Costs of all required work including labor, equipment, materials, weighing, testing, transportation, overhead, profit, and contractor owed taxes, are to be included in the prices biding the schedule for which the work is required.

C. Measurement for Payment: Material shall be weighed on platform scales furnished at the Contractor’s expense or on public scales, provided that weight tickets are prepared by certified weighmasters. Weight tickets shall include, at a minimum, the date, truck number, gross weight, tare weight, net weight, time of weighing, and signature of certified weigh-master. Payment will be made at the unit price bid per ton in the schedule. Payment will be made for only quantities listed in the schedule.

1.3 CODE COMPLIANCE

Comply with the following listed codes and standards.

OSHA Safety and Health Standards for the Construction Industry (29 CFR Part 1926).

1.4 PERMITS

Contractor is responsible for any other permits needed.

1.5 UTILITIES

Power and water is not available at the site. The Contractor shall make all arrangements to provide power and water if needed for its operations.

1.6 USE OF PREMISES

A. Contractor activities are limited to Refuge hours of work: 7:00 a.m. to 4:00 p.m., Monday through Friday. Work outside these hours or on weekends or Federal holidays is not permitted unless approved in writing by Charles Sloan.

B. Remove surplus trash, and debris, and legally dispose of them off Refuge's property.

C. Daily housekeeping is required to ensure trash and debris do not leave site or affect nearby areas. ( example: lunch bags, soda or water bottles or trash of any kind ) D. Contractors must stay on designated roads.

E. Contractor must obey all posted speed limits while on the Refuge property.

1.7 SUBMITTALS

A. Product data for base material.

B. Weight tickets for all material.

PART 2 - PRODUCTS

2.1 BASE MATERIAL

A. Provide SB2 Class 7 Crushed Stone.

B. Crushed concrete is not acceptable.

C. Provide weight tickets to Charles Sloan or other designated refuge official with each load of SB2 delivered for the work. Weight tickets shall include, at a minimum, the date, truck number, gross weight, tare weight, net weight, time of weighing, and signature of certified weighmaster.

PART 3 - EXECUTION

3.1 COMPLIANCE

A. Comply with specified codes and standards to ensure safe and satisfactory project completion.

3.2 BASE MATERIAL PLACEMENT

A. REQUIREMENTS FOR ROADWAY DELIVERY: Spread with tailgate base material in the area marked on the attached map. To be delivered upon the request of refuge staff once the notice to proceed is agreed on by both parties.

B. After tailgate spreading the SB2 to a depth of 9 inches, trucks will turn around and exit the way they entered.

3.3 Contractor must plan for weather. Rain or flooding could affect contractor’s delivery schedules, or any other unexpected Refuge or Homeland Security Operations in the area.

3.4 End.

File details come from the government source that posted it. Updated .