This statement of work outlines a project to replace carpet and vinyl base in Room 400 of Building 11 at Eglin Air Force Base. The contractor will be required to remove existing carpet, sheet vinyl, cove base and transition strips; dispose of all waste; and install new 24"x24" carpet tiles, cove base, and transition strips where needed. The project must follow all applicable NFPA, NEC, UFC and Eglin AFB electrical standards. The contractor will be responsible for maintaining safety requirements, permitting, and demonstrating standard construction methods. The point of contact for the project is Susan Landess of AFLCMC/EBDA Logistics. The related federal contract opportunity is solicitation number FA282323Q4029 from the Department of the Air Force Materiel Command Test Center to replace the carpet in Room 400 of Building 11.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA282323Q4029_Combo RFQ.pdf | ||
| Att 3 Tier 1 Contract Inquires POC.pdf | ||
| Att 4 Carpet Ordering Form.xlsx | XLSX spreadsheet | |
| Att 1 Provisions and Clauses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract # TBD
CE 332: TBD
Project Title: Replace Carpet, Room 400, Bldg 11 Date: 9 August 2023
SUMMARY OF WORK
1. PURPOSE OF SECTION: The purpose of this section is to provide the Contractor with a Statement of Work for the above mentioned project. The Contractor shall follow the guidelines and Service Summary provided in the PWS of said contract. The Contractor shall seek clarification from the Contracting Officer (CO) if there is any question on the applicability of a provision. These provisions are for the purpose of general information only and are not intended to completely describe the regulations and restrictions that apply on Eglin AFB.
2. PROJECT SCOPE: The project is located on Eglin AFB, Florida. The Contractor shall be required to furnish all materials, equipment, plant, labor and personnel necessary to design, manage, and accomplish this work in accordance with the contract requirements. The Contractor is expected to maintain safety requirements and demonstrate standard construction methods, at all times.
A. Provide everything necessary to remove sheet carpet & vinyl base, then replace with carpet squares/tiles along with new rubber base as indicated on the Task Order. Scope is limited to room 400 within building 11 on Eglin AFB.
B. Contractors shall be responsible for the disposal of the old carpet, vinyl cove base, transition strips and any waste generated by the installation of flooring products.
3. PRINCIPAL FEATURES: Principal features of work are as follows:
A. Civil:
a. None.
B. Architectural:
a. Remove existing cove base, scrape and prep to receive new. (~ 520 LF)
b. Remove existing transition strips, as required.
c. Remove existing roll/sheet carpet. Do not disturb substrate to ensure a smooth and secure bonding surface. (~ 432 SY)
d. Install new carpet squares, 24”x24” or approved otherwise. Tier 1 Approved
Carpet Vendor (~ 432 SY)
e. Install cove base (color will coordinate with carpet tiles) ~ 520 LF
f. Install matching transition strips where required.
g. All work shall be in accordance with the latest NFPA and NEC requirements to ensure maximum protection against loss of life and property by fire.
h. Design and installation must meet all UFC 3-600-01 and applicable NFPA
Standards.
i. All interior finishes, contents and furnishings must meet NFPA 101 Chapter 10.
C. Mechanical (HVAC):
a. None
D. Electrical
a. All electrical work must be completed IAW NFPA 70 and by a certified electrician.
b. Any fire detection or fire alarm devices that are moved or disconnected for any reason will require reacceptance testing IAW NFPA 72.
c. All work must be in compliance with UFC 3-520-01 Interior Electrical Systems, latest edition.
d. Ensure compliance with the Eglin AFB specific electrical requirements.
E. COMMUNICATIONS: (Customer and 96 CS will verify)
a. All work shall be IAW 96 CS Eglin AFB Cable Installation Specifications, 2 March 2012 (96 CS), or latest release. Provides the technical criteria and information for the installation of base cable infrastructure.
F. SPECIAL INSTRUCTIONS:
a. This project must be completed in a timely matter with minimal impact. Notify CO immediately of any impact regarding long lead items, delays or anything that could affect the negotiated schedule and completion date.
b. Customer will provide escorts if needed.
c. The adjacent areas within this facility will be occupied during construction.
d. Ensure adequate ventilation and coordination prior to work generating fumes, dust, debris and vibration, prior to the activity.
e. Provide warranty, certificates of compliance plus maintenance/cleaning instructions, as applicable the COR prior to the invoice being paid.
Point of contact) will be: Susan Landess/AFLCMC/EBDA Logistics Lead 850-882-7956