This statement of work describes a requirement for a contractor to replace an existing heat exchanger at a naval facility in Cutler, Maine. The contractor will remove the 1994 vintage Graham UFX-12 heat exchanger and dispose of all materials, leaving the work area clean. The contractor must then acquire and install a replacement plate type heat exchanger, modifying connection locations as needed. The replacement must be nearly identical to the UFX-12 and meet or exceed its specifications. The work is to be completed within eight hours of taking the system offline to minimize downtime. The contractor will provide all new installation materials, manuals, drawings, and warranties. The Navy will inspect the completed installation for leaks or defects before acceptance. This requirement appears to align with solicitation N7027223Q0033 to provide a replacement heat exchanger at the Cutler facility.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 23Q0033 RFQ.docx | DOCX document | |
| ANNEX C PRICE BREAKDOWN.xlsx | XLSX spreadsheet | |
| Attachment 1.pdf | ||
| ANNEX B TECH EVAL FACTORS.docx | DOCX document | |
| Attachment 2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ANNEX A
STATEMENT OF WORK
NCTS HR DET Cutler Power Plant Donor system heat exchanger replacement
1.0 INTRODUCTION: NCTS HR Det Cutler Power Plant is charged with all power switching and emergency power generation for the VLF transmitter at Cutler.
2.0 BACKGROUND: The emergency power generation equipment consists of four Cooper –Bessemer LSV-16V engines, and all four are maintained at 140F by a heated donor water system. Integral to this system is a water to water heat exchanger between the building boiler system and the donor water.
3.0 SCOPE OF WORK:
3.1 The contractor will acquire and install a replacement plate type heat exchanger for the existing 1994 vintage Graham UFX-12. The contractor will remove and dispose of the UFX-12 along with any unused materials from the modifications made to the plumbing. The area shall be left broom clean with all trash and debris removed and properly disposed of.
3.2 Location of Performance: Basement area of building 103 (Power Plant) at NCTS HR Det Cutler, 175 Ridge Road, Cutler, ME 04626
3.3 Proposed Period of Performance: TBD ARO
3.4 Work hours – 0730 – 1600 M-F. Overtime will not be authorized by the KO without mitigating circumstances identified.
3.5 The purpose of this contract request is for the vendor to remove the existing UFX-12, modify connection flange locations, and install a new equivalent replacement plate type heat exchanger. The removal and installation shall be preplanned and executed to minimize the out of service time for the donor system to less than 8 hours. There is limited space available, so the new replacement heat exchanger must be a nearly direct replacement for the no longer available UFX-12. All operational specifications of the proposed replacement must meet or exceed those of the original UFX-12. The contractor will present a written schedule to the technical point of contact for approval prior to starting the project. The written schedule will include information that verifies the training and/or experience that qualifies the contractor to successfully complete the SOW.
3.6 Government Furnished Material – There will be no government furnished material.
3.7 Contractor Furnished Material – The contractor will provide the replacement heat exchanger, OEM operation and maintenance manuals, as-built drawings for the installation, warrantee statements, all new installation hardware, any required fittings to adapt the new heat exchanger to the existing plumbing, and any other required parts and materials for successful completion of the scope of work.
3.8 CDRL’s – N/A
4.0 APPLICABLE DOCUMENTS
4.1 Graham OEM drawing and specifications are attached.
5.0 QUALITY CONTROL SURVEILLANCE PLAN (QASP)
5.1 Contractor Quality Control methods - Contractor shall exercise quality control procedures to ensure that the heat exchanger will function as designed for a reasonable period of time upon completion of the SOW.
5.2 Government Quality Assurance – Det Cutler will inspect the heat exchanger and all associated installation work, verifying no leaks, damage or obvious defects.
5.3 Corrective Action – The contractor will correct any issues that do not meet the SOW.
5.4 Conditions Found:
5.4.1 If while performing services there are conditions found that require repair/replacement and tie to this scope of work, the contractor shall submit a Condition Found Report to the COR and the Contracting Officer. Condition Found Report shall identify the conditions with a statement identifying the discrepancy along with a full price quote of required additional service. No additional service shall take place prior to Contracting Officer approval.
5.4.2 If COR or Contracting Officer determines the Condition Found does not warrant additional services, contractor shall continue with original scope of work.
5.5 Safety section.
5.6 Contract deliverable
5.7 Sanitation and space cleanliness directions – Contractor shall maintain an orderly and neat work area and leave it “broom clean” at the end of each day.
6.0 BASE ACCESS/SECURITY
6.1 Contractor shall contact technical point of contact for base access instructions as soon as possible after award. All personnel must complete the base access request and must possess a valid form of “Real ID” or a valid US passport. A security clearance is not required at this time.