ANFVRD_RedSpringsRestroom_SOW_2023.pdf
PDF 214 KB Posted
- Attached to
- Precast Cement Vault Toilet Federal contract opportunity
- Solicitation number
- 1240LS23B0004
- Issued by
- Department of Agriculture Forest Service
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ANFVRD_RedSpringsC.G._ScheduleofItems_2023 Solicitation.pdf | ||
| Sol_1240LS23B0004.pdf | ||
| ANFVRD_RedSpringsRestroom_Map_2022.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
0401 RAC Red Springs C.G. Restroom Replacement
1. Scope of Work
• Ashley National Forest, Vernal Ranger District, is planning to replace the restroom at Red Springs Campground with a double vault pre-cast concrete toilet.
2. Background
• Ashley National Forest, Vernal RD applied and was awarded funds from the Northern Utah Resource Advisory Committee, project # 21-0401-012.
3. Contractor Requirements
• Contractor will fabricate, deliver, off-load and set/assemble the new pre-cast concrete restroom buildings with vaults.
• Provide restrooms that meet the specifications according to the attached Schedule of Items, Region 4 Concrete Vault Toilet Order Forms.
• Toilet buildings must be fully accessible and must meet the design standard for naturally ventilated, odor free buildings.
• Pre-cast concrete buildings shall be delivered in a completed state with minimal fieldwork required to place and complete installation on the site. No painting except for touch-up may be complete at the site. No concrete work shall be allowed at the site as part of the building construction.
• Provide crane and crew to off-load and set the concrete vaults and concrete restrooms.
• Provide Contracting Officer Representative with specifications on site prep work to be done by the Forest Service.
4. Government Furnished
• Provide gravel bed and fill material per contractor specifications.
• Government will prepare the site for the contractor to offload and set structures.
• Provide site preparations to contractor specifications prior to delivery of cement vault restroom buildings.
• Finalize site landscaping after installation is completed.
5. Deliverables/Schedule
• Coordinate with Contracting Officer Representative (COR) to schedule deliveries.
• Deliveries acceptable as early as June 2023 and shall be finalized by October 2024.
• Deliveries accepted Monday – Friday (excluding Federal Holidays).
• Deliveries shall be delivered to locations shown on Schedule of Items.
File details come from the government source that posted it. Updated .