RFP_William_Kent_2017_Solicitation.doc
DOC document 299 KB Posted
- Attached to
- William Kent Campground 2017 Federal contract opportunity
- Solicitation number
- AG-9JGP-S-17-0032
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_Amend_001_Wiliam_Kent.doc | DOC document | |
| 1_J_FirePlan.doc | DOC document | |
| 4_WK_Drawings.pdf | ||
| 5_WK_ECP.pdf | ||
| 2_WK_SuppSpecs.docx | DOCX document | |
| 3_J_DBWages.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOL. NO. AG-9JGP-S-17-0032
William Kent Campground 2017
Lake Tahoe Basin Management Unit www.acquisition.gov/far/
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
Ag-9JGP-S-17-0032
2. TYPE OF SOLICITATION
FORMCHECKBOX
SEALED BID (IFB)
FORMCHECKBOX
NEGOTIATED (RFP)
3. DATE ISSUED
March 2, 2017
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
841100
6. PROJECT NO.
7. ISSUED BY
CODE
| 9JGP |
| 8. ADDRESS OFFER TO |
USDA FOREST SERVICE
Central California Acquisition Service Area
631 Coyote Street
Nevada City, California 95959 See Block 7.
9. FOR INFORMATION
CALL:
A. NAME
Matthew Gagnon B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) matthewgagnon@fs.fed.us
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
William Kent Campground 2017 The Government's estimate is between $100,000 and $250,000.
Contractor MUST be registered in: System for Award Management www.sam.gov Please provide the following information:
DUNS#___________________
11. The Contractor shall begin performance within 10 calendar days and complete it within 50 calendar days after receiving
FORMCHECKBOX
award, FORMCHECKBOX notice to proceed. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
FORMCHECKBOX
YES
FORMCHECKBOX
NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A.
Sealed offers in original and 01 copies to perform the work required are due at the place specified in Item 8 by 2:00 PM Pacific (hour) local time April 4, 2017. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B.
An offer guarantee
FORMCHECKBOX
is, FORMCHECKBOX is not required.
C.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D.
Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
1442-101
STANDARD FORM 1442 (REV. 4-85)
Computer Generated
Prescribed by GSA
FAR (48 CFR) 53.236-1(e) OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
| 16. REMITTANCE ADDRESS (Include only if different than Item 14) |
CODE
FACILITY CODE
17.
The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
| AMENDMENT NO. |
| DATE |
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
FORMCHECKBOX
10 U.S.C. 2304(c)( )
FORMCHECKBOX
41 U.S.C. 253(c)( )
26. ADMINISTERED BY
CODE
| 27. PAYMENT WILL BE MADE BY |
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
FORMCHECKBOX
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
FORMCHECKBOX
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated
STANDARD FORM 1442 BACK (REV. 4-85)
PART 1, SCHEDULE OF ITEMS
SECTION B
SUPPLIES OR SERVICES, AND PRICES/COSTS
| PROJECT |
| William Kent Campground 2017 |
| UNIT |
| Lake Tahoe Basin Management Unit |
| SOL. # |
| AG-9JGP-S-17-0032 |
METHOD OF
| ITEM NO. |
| DESCRIPTION |
| MEASURE |
| UNIT |
| QUANTITY |
| UNIT PRICE |
| TOTAL PRICE |
| 15101 |
| Mobilization |
| LS |
| LS |
| 1. |
| $ - |
| $ - |
| 15701 |
| Erosion Control BMPs |
| LS |
| LS |
| 1. |
| $ - |
| $ - |
| 20102 |
| Clearing and Grubbing |
| AQ |
| SY |
| 400. |
| $ - |
| $ - |
| 20207 |
| Tree Removal (greater than 6" DBH) |
| AQ |
| EA |
| 20. |
| $ - |
| $ - |
| 20405 |
| Infiltration Basin Construction |
| AQ |
| EA |
| 12. |
| $ - |
| $ - |
| 61501 |
| Construct Concrete Pathway |
| AQ |
| LF |
| 510. |
| $ - |
| $ - |
| 61904 |
| Purchase and Install Boulders |
| AQ |
| EA |
| 12. |
| $ - |
| $ - |
| 25101 |
| Install Dripline Trenches |
| AQ |
| LF |
| 260. |
| $ - |
| $ - |
| 40301 |
| Paved Camping Spur Construction |
| AQ |
| EA |
| 8. |
| $ - |
| $ - |
Option Items (Quantities shown are the maximum possible)
Optional Items will be awarded within 60 days after contract award
| 20207-OP |
| Tree Removal (greater than 6" DBH) |
| AQ |
| EA |
| 20. |
| $ - |
| $ - |
| 61904-OP |
| Purchase and Install Boulders |
| AQ |
| EA |
| 30. |
| $ - |
| $ - |
| 40301-OP |
| Paved Camping Spur Construction |
| AQ |
| EA |
| 16. |
| $ - |
| $ - |
| TOTAL |
| $ - |
| NOTES: |
| 1) Respondent must price each item to be considered for award. |
2) Responses for quantities less than those listed may be rejected.
3) If award is made in excess of $30,000, bonds will be required.
4) If response is greater than $150,000, include bid bond =20% of the total price.
5) Following are abbreviation definitions from FP-03, Section 109 that may appear in the "Unit" column of the Schedule of Items; AC=Acre, CQ=Contract Quantity, CY= Cubic Yard, EA=Each, GAL=Gallon, HR=Hour, LF=Linear Foot, LS=Lump Sum, MI=Mile, LB=Pound, SF=Square Foot, SY=Square yard, ST=Station, TON=Ton. CQ and LS will be measured and paid as stated in FP-03, Section 109-02. All other Units will be paid according to FAR clause 52.211-18, Variation in Estimated Quantity.
PRICE SUBMITTED BY:
Signature
Phone
Vendor Name
FAX
Address
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract
The William Kent Campground Construction project of 2017 mainly consists of the installation of accessible concrete pathways to all 6 restrooms within the campground, as well as the reconstruction of several paved camping spurs (8 in the base bid, with an option to award up to 16 additional spurs). The work includes cutting trees, placing boulders, moving campsite amenities, constructing permanent drainage structures, and installing new concrete and asphalt pavement, including the grading of existing ground and placement of aggregate. The campground with be open during construction, requiring both vehicular and pedestrian traffic control to ensure the safety of the public.
Project Location
From the intersection of California State Routes 89 and 28 in Tahoe City, CA travel South on California State Route 89 approximately 2.2 miles. The campground is on the West side of the highway. Latitude 39 degrees, 8 minutes, 22.60 seconds north; Longitude 120 degrees, 9 minutes, 15.92 seconds west.
NOTE: Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. In no event shall failure to inspect the site constitute grounds for a claim after contract award. (See Section L, 52.236-27, SITE VISIT.)
Price Range The Government's estimate is:
[ ] < $25,000
[ ] $25,000 to $100,000.
[X] $100,000 and $250,000.
[ ] $250,000 and $500,000.
[ ] $500,000 and $1,000,000.
[ ] $1,000,000 and $5,000,000.
[ ] $5,000,000 and $10,000,000
[ ] > $10,000,000
Estimated Start Date May 1st, 2017
Contractor must begin work within 10 days of the effective date of the Notice to Proceed. See Section F for additional information.
Option Items
For option items 20207-OP (Tree removal), 61904-OP (Purchase and Install Boulders), and 40301-OP (Paved Camping Spur Construction), the Government reserves the right to award any quantity up to and including the maximum, listed in Section B.
Restrictions on Work
1. In accordance with the fire plan, included in Section J.
2. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
3. Daily work activities will not be allowed to begin until 8:00 am and must stop at 6:00 pm, Monday through Friday.
4. Construction activities will be restricted on Federal holidays as follows: No work will be allowed Memorial Day weekend from Friday May 26th at 1:00 pm until Tuesday May 30th at 8:00 am. No work will be allowed during the July 4th holiday from Friday June 30th at 6:00 pm until Thursday July 6th at 8:00 am. No work will be allowed Labor Day weekend from Friday September 1st at 1:00 pm until Tuesday September 5th at 8:00 am. It is expected that work will be completed prior to the July 4th holiday.
5. See the attached Erosion Control Plan for information on ground disturbance restrictions and the winterization plan.
Worker's Compensation Insurance
The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.
Camping and Housing (see also Section H, Camping Permit Compliance)
Camping is not permitted in US Forest Service campgrounds. Contractor [ ] will [X] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.
Maps
INCLUDED WITH DRAWINGS
Drawings and Specifications
Project Drawings: The following drawings are part of this solicitation:
Drawings for William Kent Campground Construction 2017 (10 sheets)
Specifications:
[ ] Construction Standard Institute (CSI) specifications
These specifications are physically incorporated in the solicitation.
[ X] Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects
FP-03 (US Customary Units)
This document is incorporated by reference and is available on the web in either MS Word
(http://www.wfl.fha.dot.gov/design/specs/English/FP03_USCust_final_111403.doc) or Acrobat
(http://www.wfl.fha.dot.gov/design/specs/English/FP03_USCust_final_111403.pdf)
It is also available as a wire-bound book that can be purchased from the US Government Printing
Office:
Superintendent of Documents U.S. Government Printing Office Internet: bookstore.gpo.gov Phone: (toll free) 866.512.1800 Fax: 202.512.2250 Mail: Stop SSOP, Washington, DC 20402-0001
Stock Number: 050-001-00341-4 (U.S. Customary)
Special Project Specifications are physically incorporated within this solicitation, beginning on the next page.
The following Standard and Special Project Specifications are applicable to this contract:
| # |
| Description |
| Date |
| 1 |
| Supplemental Specifications to the FP-03 |
| 1/24/2017 |
The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996) Inspections Government inspections are for the purpose of satisfying the Government that the supplies and/or services are acceptable and do not relieve the Contractor of the responsibility for maintaining quality control. The Contracting Officer's Representative or designated inspector will conduct all inspections. The Contractor (or designated representative) is encouraged to be present to observe inspections
SECTION F--DELIVERIES OR PERFORMANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 50 days after the effective date of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
Work Timing
Delays due to normal adverse weather, weekends, and holidays have been included in the calculation of contract time.
Winter Shutdown
When winter weather sets in and the continuation of work is impractical, the Contracting Officer may authorize a total suspension until such time as work can proceed. During the period of total suspension, the calendar days elapsed will not be charged against the contract time specified.
SECTION G—CONTRACT ADMINISTRATION DATA
GOVERNMENT-FURNISHED PROPERTY
The government will provide the following item(s) of Government property to the contractor for use in the performance of this contract. The property shall be used and maintained by the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract.
NONE
Invoices
Payment will be made from the contractor’s invoice. All invoices are to be submitted via the electronic Invoice Processing Platform (IPP). This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. There is no pre-award registration.
After award of a contract, please make sure that your company registers promptly at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. The one-time enrollment in IPP means a series of emails will be sent to the point of contact (POC) established in your System for Award Management (SAM) account at www.sam.gov. Please verify that the POC’s email address is up to date in your company’s SAM account prior to starting the IPP enrollment process. If you have questions on the IPP enrollment process, the help desk phone number is 1-866-973-3131.
Invoices shall be accompanied by the signed contractor certification, using the exact wording in the clauses, FAR 52.232-5, and be up-to-date on certified payrolls for the invoiced timeframe, FAR 52.222-8. (See next page for invoice certification language.) Invoices that do not meet these requirements will be rejected.
The contractor shall submit payrolls weekly for each week in which any contract work is performed. The copies shall be sent to the COR. Payrolls submitted shall set out accurately and completely all of the information listed on the form WH-347 (available for download at www.dol.gov., including the certification verbatim from the WH-347. Forms from other State or County governments are not compliant. Invoices that do not meet these requirements will be rejected.
A Contract Release is required with the final invoice, or the invoice may be rejected.
Payment for Materials Off-Site In accordance with Clause 52.232-5, progress payments may include payment for materials stored off site. Contractor shall provide a copy of the paid invoice; provide evidence that the material will be included in the finished project; and identify the location where the materials are stored, so that the government may make visual inspection if the Contracting Officer deems it necessary. The Contractor shall be liable for loss, damage, or destruction of the materials until such time as the materials are physically in the possession and control of the government. The Contractor will not be held liable to the extent that the Contracting Officer determines that the loss, damage, or destruction occurred through the fault or negligence of the government or its agents.
Incidental Items
The intent of the contract is to provide for the completion of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment of items shown.
Preconstruction Conference
This required conference will be scheduled by the COR. (See also Section I, Clause 52.236-26.)
PAYMENT CERTIFICATION
I hereby certify, to the best of my knowledge and belief, that—
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.
(Name)
(Title)
(Date)
SECTION H—SPECIAL CONTRACT REQUIREMENTS
Emergencies
Fire Plan: See Section J.
Area of Responsibility for Fire. Unless otherwise noted elsewhere in the contract, the following define the limits of a contractor's area of responsibility for fire under the terms of the Fire Plan (Section J):
Construction of Structures - 100 meters around the perimeter of the project area Utility Services
NONE
Superintendence by Contractor
In addition to Clause 52.236-6, the following applies: The name and the specific authorities of the foreman or superintendent must be designated in writing to the Contracting Officer. The Contractor may use his/her own prepared letterhead stationery or a "Designation of Contractor's Representative" form available from the Contracting Officer. If the Contractor or the designee is not present when work is being performed on the contract, a Suspend Work Order may be issued with contract time continuing to run. The Contractor shall have a person on-site that is fully conversant in the English language.
Loss, Damage or Destruction
Equipment Furnished with Operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.
Other. Even though this contract may provide for performing services at the direction of Government personnel, the contract is not for personal services, and neither the Contractor nor his or her personnel are Government employees. The Government assumes no liability for injury occurring to Contractor personnel or to third parties, or for loss, damage, or destruction involving third parties' property as a result of the Contractor's operation. Except that the Government is liable for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) acting within the scope of their employment.
Camping Permit Compliance
Contractor shall comply with all terms and conditions of any camping permit issued to allow use of premises. Any non-compliance will result in suspension of work until compliance is achieved.
Archaeological and Historic Sites
Location of known archaeological, historic, or pre-historic materials--such as Native American artifacts and/or historic mining, logging, or fur trapping remains protected by the American Antiquities Act (l6 USC 433)--will be identified for the contractor before work commences.
Spill Plan
If the total oil or oil products storage exceeds 1,320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare and implement a Spill Prevention and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112), including certification by a registered professional engineer. The Contractor under the direction of the Contracting Officer, or in the absence of said officer, acting independently, shall immediately take action to contain and clean up, without expense to the Government, all petroleum products spills on or in the vicinity of the project which are caused by the Contractor's employees directly or indirectly as a result of contract operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government for the containment and cleanup of petroleum products spills caused by Contractor's employees or resulting from contract operations. The Contractor shall immediately report all petroleum products spills to the Contracting Officer.
Equipment Cleaning
All off-road equipment used on this project shall be washed before moving into the project area so that the equipment is free of soil, seeds, vegetative material, or other debris that could contain or hold seeds of noxious weeds. “Off-road equipment” includes all logging and construction equipment and such brushing equipment as brush hogs, masticators, and chippers; it does not include log trucks, chip vans, service vehicles, water trucks, pickup trucks, and similar vehicles not intended for off-road use.
Equipment will be considered clean when visual inspection does not reveal soil, seeds, plant material, or other such debris. Disassembly of equipment components or specialized inspection equipment is not required. Contractor shall notify the Contracting Officer at least five days in advance of moving equipment in so that arrangements can be made for inspection.
If the project area is known to contain noxious weeds, the equipment shall be cleaned before moving to other Forest Service system lands which do not contain noxious weeds.
Work Limit Items
All construction activity shall be performed during the period between May 1st and Oct 15th.
Any ground disturbing work not completed by Oct 15th shall be winterized. Ground disturbing work may resume on May 1st of the following year. Winterization shall consist of placing wood chips on all disturbed areas at the direction of the COR, aggregate material (if asphalt work is not complete), covering of stockpiles, leaving the site in a safe condition and allowing for use of the site by the Forest Service or its assignees. Winterization shall be at the contractor’s expense if the work is not completed by October 15th.
Work may continue past Oct 15th if the foundation and any other ground disturbing work have been completed. Materials may only be staged from hardened surfaces such as pavement or concrete. Native soil or vegetated areas may not be used as staging areas. Stock piles shall be covered during any storm events and after October 15th.
The Contracting Officer and/or Contracting Officer’s Representative may direct the contractor to install additional Best Management Practices (BMPs) not identified in the plans or specifications. The contractor will have 24 hours to install these BMPs.
Work must be buttoned on July 1st and may resume after July 6th. The job site must be in a condition to allow for heavy public use during that time period
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.acquisition.gov/far/ www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (NOV 2013)
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant against Contingent Fees (MAY 2014)
52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)
52.203-7 Anti-Kickback Procedures (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights. (Apr 2014)
52.204-4 Printed or Copied Double- Sided on Recycled Paper (MAY 2011)
52.204-7 System For Award Management (JUL 2013)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Oct 2015)
52.204-19 Incorporation by Reference of Representations and Certifications.(DEC 2014)
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. (JUL 2013)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)
52.211-12 Liquidated Damages—Construction (Sept 2000)
52.211-18 Variation in Estimated Quantity (APR 1984)
52.215-2 Audit and Records -- Negotiation (OCT 2010)
52.215-8 Order of Precedence—Uniform Contract Format. (Oct 1997) 52.219-8 Utilization of Small Business Concerns (OCT 2014)
52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside. (NOV 2011)
52.222-3 Convict Labor (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (May 2014)
52.222-6 Construction Wage Rate Requirements (May 2014)
52.222-7 Withholding of Funds (MAY 2014)
52.222-8 Payrolls and Basic Records (MAY 2014)
52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (MAY 2014)
52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (MAY 2014)
52.222-21 Prohibition of Segregated Facilities (Apr 2015)
52.222-26 Equal Opportunity (APR 2015)
52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015)
52.222-35 Equal Opportunity for Veterans (OCT 2015)
52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014)
52.222-37 Employment Reports on Veterans (OCT 2015)
52.222-50 Combating Trafficking In Persons (MAR 2015)
52.223-1 Biobased Product Certification (MAY 2012)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)
52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997)
52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)
52.223-6 Drug-Free Workplace (MAY 2001)
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. (Oct 2015)
52.227-1 Authorization and Consent (DEC 2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)
52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)
52.228-2 Additional Bond Security (OCT 1997)
52.228-11 Pledges of Assets (JAN 2012)
52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014)
52.228-14 Irrevocable Letter of Credit (NOV 2014)
52.228-15 Performance and Payment Bonds – Construction (OCT 2010)
52.229-3 Federal, State, and Local Taxes (FEB 2013)
52.232-5 Payments Under Fixed-Price Construction Contracts (May 2014)
52.232-9 Limitation on Withholding of Payments (APR 1984)
52.232-16 Progress Payments (APR 2012)
52.232-17 Interest (MAY 2014)
52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts (MAY 2014)
52.232-33 Payment by Electronic Funds Transfer-System for Award Management. (Jul 2013)
52.233-1 Disputes (MAY 2014)--Alternate I (DEC 1991)
52.233-3 Protest After Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (Oct 2004)
52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by the Contractor (APR 1984)
52.236-7 Permits and Responsibilities (NOV 1991)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984)
52.236-10 Operations and Storage Areas (APR 1984)
52.236-11 Use and Possession Prior to Completion (APR 1984)
52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991) Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984)
Alternate I (APR 1984)
52.236-17 Layout of Work (APR 1984)
52.236-21 Specifications and Drawings for Construction (FEB 1997)
52.236-26 Preconstruction Conference (FEB 1995)
52.242-13 Bankruptcy (JUL 1995)
52.243-4 Changes (JUN 2007)
52.244-6 Subcontracts for Commercial Items (DEC 2015)
52.246-21 Warranty of Construction (MAR 1994) Alternate I (APR 1984)
52.248-3 Value Engineering – Construction (OCT 2015)
52.249-2 Termination for Convenience of the Government (APR 2012)--Alternate I (SEP 1996)
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)
452.236-72 Use of Premises (NOV 1996)
452.236-73 Archeological or Historic Sites (FEB 1988)
452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996)
52.211-18 Variation in Estimated Quantity (Apr 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.
52.217-5 Evaluation of Options. (July 1990) As prescribed in 17.208(c), insert a provision substantially the same as the following:
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
52.217-6 Option for Increased Quantity. (Mar 1989) As prescribed in 17.208(d), insert a clause substantially the same as the following:
The Government may increase the quantity of supplies called for in the Schedule at the unit price specified. The Contracting Officer may exercise the option by written notice to the Contractor within 60 days. Delivery of the added items shall continue at the same rate as the like items called for under the contract, unless the parties otherwise agree.
52.217-7 Option for Increased Quantity—Separately Priced Line Item. (Mar 1989) As prescribed in 17.208(e), insert a clause substantially the same as the following:
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within [insert in the clause the period of time in which the Contracting Officer has to exercise the option]. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
52.219-14 Limitations on Subcontracting (Nov 2011)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Applicability. This clause applies only to—
(1) Contracts that have been set aside or reserved for small business concerns or 8(a) concerns;
(2) Part or parts of a multiple-award contract that have been set aside for small business concerns or 8(a) concerns; and
(3) Orders set aside for small business or 8(a) concerns under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).
(c) By submission of an offer and execution of a contract, the Offeror/Contractor agrees that in performance of the contract in the case of a contract for—
(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the concern.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). The concern shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials.
(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.
(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.
52.222-40 – Notification of Employee Rights Under the National Labor Relations Act (Dec 2010)
(a) During the term of this contract, the Contractor shall post an employee notice, of such size and in such form, and containing such content as prescribed by the Secretary of Labor, in conspicuous places in and about its plants and offices where employees covered by the national Labor Relations Act engage in activities relating to the performance of the contract, including all places where notices to employees are customarily posted both physically and electronically, in the languages employees speak, in accordance with 29 CFR 471.2(d) and (f).
(1) Physical posting of the employee notice shall be in conspicuous places in and about the Contractor’s plants and offices so that the notice is prominent and readily seen by employees who are covered by the National Labor Relations Act and engage in activities related to the performance of the contact.
(2) If the Contractor customarily posts notices to employees electronically, then the Contractor shall also post the required notice electronically by displaying prominently, on any Web site that is maintained by the Contractor and is customarily used for notices to employees about terms and conditions of employment, a link to the Department of Labor’s Web site that contains the full text of the poster. The link to the Department’s Web site, as referenced in (b)(3) of this section, must read, “Important Notice about Employee Rights to Organize and Bargain Collectively with Their Employers.”
(b) This required employee notice, printed by the Department of Labor, may be—
(1) Obtained from the Division of Interpretations and Standards, Office of Labor-Management Standards, U.S. Department of Labor, 200 Constitution Avenue, NW., Room N-5609, Washington, DC 20210, (202) 693-0123, or from any field office of the Office of Labor-Management Standards or Office of Federal Contract Compliance Programs;
(2) Provided by the Federal contracting agency if requested;
(3) Downloaded from the Office of Labor-management Standards Web site at http://www.dol.gov/olms/regs/compliance/EO13496.htm ; or
(4) Reproduced and used as exact duplicate copies of the Department of Labor’s official poster.
(c) The required text of the employee notice referred to in this clause is located at Appendix A, Subpart A, 29 CFR Part 471.
(d) The Contractor shall comply with all provisions of the employee notice and related rules, regulations, and orders of the Secretary of Labor.
(e) In the event that the Contractor does not comply with the requirements set forth in paragraphs (a) through (d) of this clause, this contract may be terminated or suspended in whole or in part, and the Contractor may be suspended or debarred in accordance with 29 CFR 471.14 and subpart 9.4 Such other sanctions or remedies may be imposed as are provided by 29 CFR part 471, which implements Executive Order 13496 or as otherwise provided by law.
(f) Subcontracts.
(1) The Contractor shall include the substance of this clause, including this paragraph (f), in every subcontract that exceeds $10,000 and will be performed wholly or partially in the Unites States, unless exempted by the rules, regulations, or orders of the Secretary of Labor issued pursuant to section 3 of Executive Order 13496 of January 30, 2009, so that such provisions will be binding upon each subcontractor.
(2) The Contractor shall not procure supplies or services in a way designed to avoid the applicability of Executive Order 13496 or this clause.
(3) The Contractor shall take such action with respect to any such subcontract as may be directed by the Secretary of Labor as a means of enforcing such provisions, including the imposition of sanctions for noncompliance.
(4) However, if the Contractor becomes involved in litigation with a subcontractor, or is threatened with such involvement, as a result of such direction, the Contractor ma request the United States, through the Secretary of Labor, to enter into such litigation to protect the interests of the United States.
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (September 2013).
(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United States Department of Agriculture (USDA) designated items unless
(1) The product cannot be acquired
(i) Competitively within a time frame providing for compliance with the contract performance schedule;
(ii) Meeting contract performance requirements; or
(iii) At a reasonable price.
(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:
(i) Spacecraft system and launch support equipment.
(ii) Military equipment, i.e., a product or system designed or procured for combat or combat-related missions.
(b) Information about this requirement and these products is available at http://www.biopreferred.gov.
(c) In the performance of this contract, the Contractor shall
(1) Report to http://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and
(2) Submit this report no later than
(i) October 31 of each year during contract performance.
52.225-9 Buy American—Construction Materials. (May 2014)
(a) Definitions. As used in this clause—
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means—
(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate “none”]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
| Construction Material Description |
| Unit of Measure |
| Quantity |
| Price (Dollars)* |
Item 1:
| Foreign construction material |
| _______ |
| _______ |
| _______ |
| Domestic construction material |
| _______ |
| _______ |
| _______ |
| Item 2: |
| _______ |
| _______ |
| _______ |
| Foreign construction material |
| _______ |
| _______ |
| _______ |
Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
52.225-10 Notice of Buy American Requirement—Construction Materials. (May 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American—Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the…