IAVC_Door_Specifications.pdf
PDF 679 KB Posted
- Attached to
- Door Reconstruction, INYO National Forest Federal contract opportunity
- Solicitation number
- AG-9JGP-S-16-0024
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend_02_S160024.pdf | ||
| Amendment_01__S160024.pdf | ||
| IAVC_Door_Drawings.pdf | ||
| Davis_Bacon_WD_Nov.pdf | ||
| AG-9JGP-S-16-0024_IAVC_Doors.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
IAVC Door Reconstruction Inyo National Forest
US 395 & CA HWY 136
Lone Pine, California 93545 for
USDA Forest Service Central California Acquisitions
631 Coyote Street Nevada City, CA 95959
March 2015
Architect
SIEGEL & STRAIN ARCHITECTS
1295 59th Street Emeryville, California 94608
Tel: 510-547-8092; Fax: 510-547-2604
Inyo National Forest IAVC Door Reconstruction
SECTION 00 01 10
TABLE OF CONTENTS
DIVISION 0 – INTRODUCTORY INFORMATION
Section 00 01 10 Table of Contents 00 21 11 Terms and Definitions 00 21 12 Mobilization Procurement Requirements/Bidding Requirements (see other sections not included in the specification package)
DIVISION 1 – GENERAL REQUIREMENTS
Section 01 10 00 Summary 01 33 00 Submittals 01 60 00 Basic Product Requirements 01 74 00 Project Cleanup 01 77 00 Closeout Procedures
DIVISION 3 – CONCRETE
Section 03 10 00 Concrete Formwork 03 20 00 Concrete Reinforcing 03 33 00 Cast-in-place Concrete
DIVISION 8 – OPENINGS
Section 08 06 71 Door Hardware Schedule 08 14 00 Wood Doors 08 41 13 Aluminum-Framed Entrances and Storefronts 08 71 00 Door Hardware 08 71 13 Automatic Door Operators 08 80 00 Glazing
DIVISION 9 – FINISHES
Section 09 21 16 Gypsum Board Assemblies 09 90 00 Painting and Coating
END OF SECTION
Division 0 00 01 10 - 1 Table of Contents
SECTION 00 21 11
TERMS AND DEFINITIONS
PART 1 - GENERAL
1.01 Scope
This section refers to the terms and definitions used throughout the contract drawings and specifications, unless specifically noted otherwise.
1.02 Terms
The specifications are generally written in the imperative mood. In sentences using the imperative mood, the subject, “the Contractor,” is implied. Also implied in this language is “shall,” “shall be,” or similar words and phrases. In material specifications, the subject may also be the supplier, fabricator, or manufacturer supplying material, products, or equipment for use on the project.
Wherever “directed,” “required,” “prescribed,” or similar words are used, the “direction,” “requirement,” or “order” of the Contracting Officer (CO) is intended. Similarly, wherever “approved,” “acceptable,” “suitable,” “satisfactory,” or similar words are used, they mean “approved by,” “acceptable to,” or “satisfactory to” the CO.
The word “will” generally pertains to decisions or actions of the CO.
Whenever in these specifications, or in other contract documents, the following terms (or pronouns in place of them) are used, the intent and meaning shall be interpreted as follows: reference to a specific standard, test, testing method, or specification shall mean the latest published edition or amendment that is in effect at the solicitation issue date for the contract, unless otherwise noted.
1.03 Definitions
Wherever the following terms, or pronouns in place of them, are used in these specifications or in other contract documents, the intent and meaning are as follows:
Adjustment in Contract Price. “Equitable adjustment,” as used in the Federal Acquisition Regulations.
Base Course. The layer or layers of specified or selected material of designed thickness placed on a subbase or subgrade to support a surface course.
Bearings. The portion of a beam, girder, or truss that transmits the bridge superstructure load to the substructure.
Berm. Curb or dike constructed to control roadway runoff water.
Best Management Practice. A series of water quality protection practices and procedures approved or certified by the State water quality agency under the provisions of sections 319 and 402 of the Clean Water Act, as amended.
Certificate of Compliance. A signed statement by a person with legal authority to bind a company or supplier to its product. The certificate states that the material or assemblies furnished fully comply with the requirements of the contract.
Division 0 00 21 11 - 1 Table of Contents
Change. “Change” means “change order” as used in the Federal Acquisition Regulations.
Clearing Limits. The limits of clearing as designated on the ground or on the drawings.
Cofferdam. A cofferdam is an enclosed single or double wall braced structure with walls sheeted with timber, concrete, or steel, and extending well below the bottom of excavation, when practical. Earthen or rockfill dikes, dams, or embankments are not considered cribs or cofferdams for this purpose.
Conduit. A pipe for carrying fluids, wire, rope, gas, etc.
Contracting Officer (CO). The person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the CO acting within the limits of their authority as delegated by the CO. Authorized representatives include the Contracting Officer’s Representative, and Inspector.
Contractor. The individual, partnership, joint venture, or corporation undertaking the execution of the work under the terms of the contract and acting directly or through agents, employees, or subcontractors, as used in specifications and drawings.
Defect. A failure to meet a requirement with respect to a single quality characteristic.
Drawings. The documents, including plan and profile sheets, plans, cross sections, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials showing details for construction of a facility.
Embankment. A structure of soil, aggregate, or rock material placed on the prepared ground surface and constructed to subgrade.
Equipment. All machinery and equipment, together with the necessary supplies for upkeep and maintenance, as well as tools and apparatus necessary for the proper construction and acceptable completion of the work.
Excess Excavation. Material in excess of that needed for construction of designated improvements.
Falsework. Any temporary construction work used to support the permanent structure until it becomes self-supporting. Falsework includes steel or timber beams, girders, columns, piles, foundations, and any proprietary equipment including modular shoring frames, post shores, and adjustable horizontal shoring.
Forest Service. The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Government Land. National Forest System lands, and other lands controlled or administered by the Forest Service or other Federal agencies.
Inspector. The Government-authorized representative designated in writing by the Contracting Officer, or Contracting Officer’s Representative responsible for detailed inspection.
Invert. The lowest point of the internal cross section of pipe.
Job-Mix Formula. The percentage of each material in a mixture intended for a particular use.
Division 0 00 21 11 - 2 Table of Contents
Laboratory. A testing laboratory of the Government, or any other testing laboratory approved by the Contracting Officer.
Lot. An isolated quantity of material from a single source; a measured amount of construction assumed to be produced by the same process.
Materials. Any substance specified for use in the construction of the project and its appurtenances.
Maximum Density. The highest density that can be obtained for a specific material using the stated test procedure.
Measurement. Determining and expressing the quantities of work or materials.
Neat Line. A line defining the proposed or specified limits of an excavation or structure.
Nominal Dimensions or Weights. The numerical values shown on the drawings or in the specifications as measurements of material to be used in the construction.
Nominal Maximum Particle Size. The largest sieve size listed in the applicable specification upon which any material is permitted to be retained.
Pass. A pass shall consist of one complete coverage of the surface.
Pavement Structure. Subbase, base, or surface course, or combination thereof, placed on a subgrade to support the traffic load and distribute it to the roadbed.
Profile Grade. The trace of a vertical plane, as shown on the drawings, intersecting the top surface at the centerline of the proposed facility construction.
Random Sampling. A sample of material chosen such that each increment of a population of material has an equal probability of being selected.
Reasonably Close Conformity. Compliance with reasonable and customary manufacturing and construction tolerances, performing all work and furnishing all materials in “reasonably close conformity” with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground.
Right-of-Way. A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) land, appurtenances thereto, or interest therein, usually in a strip, acquired for public or private passageway.
Schedule of Items. A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, methods of measurement, unit price, and amount.
Second Samples. A sample taken when the initial sample indicates that the material is defective.
Shoulder. The portion of the roadway or walkway contiguous to the traveled way for accommodation of stopped vehicles, emergency use, and lateral support of pavement structure.
Sidewalk. The portion of the roadway constructed primarily for pedestrian use.
Division 0 00 21 11 - 3 Table of Contents
Specifications. A description of the technical requirements for a material, product, or service that includes criteria for determining whether these requirements are met.
Station. (1) A measure of distance used for highways and railroads equal to 100 feet.
(2) A precise location along a survey line.
Subbase. The layers of specified or selected material of designed thickness placed on a subgrade to support a base course.
Subgrade. The prepared surface, including widening for curves, turnouts, and other areas upon which a subbase, base, or surface course is constructed.
Surface Course. The top layer of a pavement structure, sometimes called the wearing course, usually designed to resist skidding, traffic abrasion, and the disintegrating effects of climate.
Target Value. Values that are established according to contract, and from which allowable variations are measured.
Traveled Way. The portion of the roadway for the movement of vehicles, exclusive of shoulders and auxiliary lanes. (See Figure 102-1.)
Unit of Measurement. The unit and fractions of units DESIGNATED IN THE SCHEDULE OF ITEMS.
Unsuitable Material. The material excavated during construction that is not usable in embankment and must be disposed of, or that can be used only in certain locations or for limited purposes.
1.04 Measurement and Payment
Compensation provided for in the contract is full payment for performing all contract work in a complete and acceptable manner. All risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the contract.
Work required by the contract will not be paid for directly unless a PAY ITEM for the work is
DESIGNATED IN THE SCHEDULE OF ITEMS.
Work referenced for measurement under another section will not be paid for directly unless a PAY ITEM for the work is DESIGNATED IN THE SCHEDULE OF ITEMS for the referenced section.
Work not paid for directly is considered to be included under the other contract PAY ITEMS.
Unless otherwise shown, work measured and paid for under one PAY ITEM will not be paid for under any other PAY ITEM.
The quantity to be paid for is the quantity DESIGNATED IN THE SCHEDULE OF ITEMS. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.
When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any PAY ITEM, suffixes will be added to the item number to differentiate between the items.
1.05 Determination of Quantities
Division 0 00 21 11 - 4 Table of Contents
The following measurements and calculations are used to determine contract quantities.
For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding shall be along slope lines.
Structures shall be measured according to neat lines SHOWN ON THE DRAWINGS, or as altered by the CO in writing to fit field conditions.
For items that have linear measurements, such as pipe, measurements shall be made parallel to the base or foundation upon which the structures are placed. Pipe shall be measured along center of invert.
For standard manufactured items (such as fence, wire, plates, rolled shapes, and pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer’s tolerances shall be accepted.
1.06 Units of Measurement
Payment will be by units defined and determined according to measure. Unless otherwise specified, the meanings of the following terms are as follows:
(a) Cubic Yard in Place (CY). Measure solid volumes by the multiplying completed length by width by height/depth; or other methods involving three-dimensional measurements may be used.
(b) Cubic Yard in the Hauling Vehicle (CY). Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purposes if the conversion factors are mutually agreed to in writing.
(c) Each (EA). One entire unit, which may consist of one or more parts. The quantity is the actual number of units completed and accepted.
(d) Acre (AC). 43,560 ft2. Make longitudinal and transverse measurements for area computations horizontally. Do not make deductions from the area computation for individual exclusions having an area of 500 ft2 or less.
(e) Hour (HR). Measurement will be for the actual number of hours ordered and performed by the Contractor.
(f) Pound (LB). If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.
(g) Gallon (GAL). The quantity may be measured by any of the following methods:
(1) Measured volume container.
(2) Metered volume. Use an approved metering system.
(3) Commercially packaged volumes.
(h) Lump Sum (LS). Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.
Division 0 00 21 11 - 5 Table of Contents
(i) Linear Foot (LF). Measure from end to end, parallel to the base or foundation being measured, or horizontal.
(j) Station (STA). 100 feet measured horizontally.
(k) Square Yard (SY). Measure on a plane parallel to the surface being measured or horizontal.
(l) Ton (T). 2,000 pounds.
No adjustment in contract unit price will be made for variations in quantity due to differences in the specific gravity or moisture content.
Use net certified scale weights, or weights based on certified volumes.
1.07 Methods of Measurement
One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM:
(a) Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:
(1) Changes in the work authorized by the CO.
(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.
(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.
(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to construction.
(c) Actual Quantities (AQ). These quantities are determined from measurements of completed work.
(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.
(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.
PART 2 - PRODUCTS (Not Used)
PART 3 – EXECUTION (Not Used)
Division 0 00 21 11 - 6 Table of Contents
Division 0 00 21 11 - 7 Table of Contents
SECTION 00 21 12
MOBILIZATION
This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.02 Method of Measurement shall be lump sum for mobilization.
1.03 Basis of Payment
The lump sum price shall include full compensation for mobilization. Progress payments for mobilization will be made as follows:
A. Bond premiums will be reimbursed according to FAR Clause 52.235-5, Payments Under
Fixed-Price Construction Contracts, after receipt of evidence of payment.
B. When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5% of the original contract amount, whichever is less, will be paid.
C. When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
D. Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
E. Upon completion of all work on the project, any unpaid amount for Item 00 21 12
Mobilization, will be paid.
The total of all payments will not exceed the original contract amount for Item 00 21 12 Mobilization.
PART 3 - EXECUTION (Not Used)
Division 0 00 21 12 - 1 Mobilization
SECTION 01 10 00
SUMMARY OF WORK
The work of this contract consists of replacement of several sets of 10 ft tall doors with shorter doors and transoms at the Interagency Visitor Center in Lone Pine, CA. Two sets of double doors will be replaced along with two single doors. In addition, one set of double doors will be converted to a full-height window with operable units to match existing full-height windows, and set on a new 6" concrete curb. Automatic door operators and small push button style ADA accessible door actuators will be added at two doors. A concrete pad will be added at the employee entrance (Door 3) to allow for ease of access.
1.02 Intent of Contract
The intent of the contract is to provide for the complete construction of the project described in the drawings and specifications. Unless otherwise specified, furnish all labor, materials, equipment, tools, transportation, and supplies to perform all work required to complete the project in conformity with drawings, specifications, and provisions of the contract.
1.03 Base Bid and Bid Options
A. All work in the scope is included in the base bid. There are no optional items in this contract.
1.04 Location
The project is located east of the Sierra Nevada Mountains, at the junction of US Highway 395 and State Highway 136, south of Lone Pine, California at the Eastern Sierra Interagency Visitor Center
(IAVC).
1.05 Special Construction Requirements
The IAVC will be in full operation during the construction. The hours of operation are from 0800 to 1700, 7 days per week. Public safety shall be a top priority of the Contractor. Safety barricades and caution tape will be employed to restrict access into construction areas to authorized personnel only.
1.06 Application of the Contract Documents
A. The provisions of the General Conditions of the Contract, Supplementary Conditions, and Division 1 - General Requirements of the Specifications apply to the work specified in each Section of the Specifications.
B. The Contractor is hereby specifically directed to notify and apprise all subcontractors and other parties engaged in the Work as to the contents of the General Conditions, Supplementary Conditions, and Division 1 - General Requirements.
C. No contractual adjustment shall be due or become exigent as a result of failure to fully understand the General Conditions, Supplementary Conditions, and Division 1 - General Requirements.
Division 1 01 10 00 - 1 Summary
D. The Work shall conform to the specifications and the Contract Drawings identified on the Sheet Index on Sheet G1.00 of the Drawings.
1.07 Contract Method
Construct the Work as shown on the Schedule of Items, as established by the Contract.
1.08 Work Schedule
A. Working Hours: Perform all work on the site between the hours of 6:00 AM and 6:00 PM Monday through Friday. Work during other hours, or on legal holidays or weekends shall not be permitted unless otherwise authorized by the Government.
B. Utility Outages: Existing utility services to existing Visitor Center operations shall not be interrupted at any time by Contractor, except with prior written approval of the Contracting Officer. Schedule all required utility interruptions including power, domestic water, sanitary sewer, gas, and telephone 3 working days prior to expected shutdown with the Contracting Officer. Final confirmation of interruptions to utility service shall be done at least 48 hours in advance.
PART 3 – EXECUTION (Not Used)
Division 1 01 10 00 - 2 Summary
SECTION 01 33 00
SUBMITTALS
PART 1 - GENERAL
1.1 SCOPE
A. This section describes general procedural requirements for ongoing submittals.
1. Construction progress schedules.
2. Shop drawings.
3. Product data.
4. Samples.
5. Manufacturers’ certificates
6. As-built drawings.
7. Substitution requests.
B. Related Requirements (none)
1.2 MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work specified in this section.
1.3 PRELIMINARY LIST OF SUBMITTALS REQUIRED FOR THIE PROJECT
Includes, but is not limited to the following:
1. Construction Progress Schedule: Contractor shall thoroughly review specification sections and submit a final submittal schedule listing all items to be submitted incorporated into the Construction Progress Schedule.
2. Section 03 33 00 Cast-in-place Concrete
3. Section 08 14 00 Wood Doors
4. Section 08 41 13 Aluminum-Framed Entrances and Storefronts
5. Section 08 80 00 Glazing
6. Section 08 06 71 Door Hardware Schedule
7. Section 08 71 00 Door Hardware
8. Section 08 71 13 Door Openers
9. Section 09 90 00 Painting and Coating
PART 2 - PRODUCTS
Not Applicable.
Division 1 01 33 00 - 1 Submittals
PART 3 - EXECUTION
3.1 PROCEDURES
A. Submittals: Transmit each submittal including requests for information (RFI’s) through Contracting Officer using acceptable form; submit samples to COR for approval prior to use.
1. Identify Project, Contractor, subcontractor, major supplier.
a. Attach sequential identification number for each new submittal.
b. Identify each resubmittal using original submittal number and sequential identification clearly indicating the item is resubmitted.
2. Identify pertinent Drawing sheet and detail number and Specification section number as appropriate.
3. Identify deviations from Contract Documents.
4. Provide space for Contractor and Contracting Officer review stamps.
5. Contractor: Review and stamp submittals from subcontractors prior to submitting to Contracting Officer.
a. Review submittals and indicate where conflicts occur with Contract Documents and with work of other subcontractors.
b. Return submittals that vary significantly from Contract Documents for correction and resubmittal prior to submitting to Contracting Officer.
c. Submittals that vary significantly from Contract Documents and that fail to indicate through Contractor review prior to submission to Contracting Officer will be returned without review.
d. Cursory review and stamping of subcontractor submittal by Contractor shall not be acceptable.
B. Initial Schedules: Submit initial progress schedule within 15 days after the award of the Contract or 15 days prior to the Notice to Proceed being issued.
1. After review by Contracting Officer, revise and resubmit when required.
C. Comply with progress schedule for submittals related to Work progress. Coordinate submittal of related items.
D. After Contracting Officer review of submittal, revise and resubmit as required, identify changes made since previous submittal.
E. Distribute copies of reviewed submittal to concerned persons. Instruct recipients to promptly report any inability to comply.
Division 1 01 33 00 - 2 Submittals
3.2 CONSTRUCTION PROGRESS SCHEDULES
A. Submit construction progress schedule with separate item for each major trade and operation, identifying the first day of each week.
1. Show complete sequence of construction by activity, identifying work of separate stages and logically grouped activities.
2. Show projected percentage of completion for each item of Work as of the time of each progress Application for Payment.
3. “Submittal Schedule”: Show Contractor submittal dates required for shop drawings, product data and samples, and product delivery dates.
a. “Submittal Schedule” may be incorporated into construction progress schedule or may be separate, Contractor option.
b. Contracting Officer’s Review Period: Contracting Officer will be expedient in review, however, Contractor shall schedule submittals recognizing the possibility that Contracting Officer may reject and may require a resubmittal.
c. Contract extension shall not be allowed for Contractor’s failure to properly schedule submittals to allow for Contracting Officer required resubmittals.
B. Progress Schedule Format: Submit as a horizontal bar chart.
3.3 SHOP DRAWINGS
A. Submit electronic files of shop drawings that are full size at 11×17 or smaller.
1. Comments will be returned to Contractor as electronic files for distribution.
B. Shop drawings larger than 11×17 at full size shall be submitted as a paper copy.
1. Submit two (2) paper copies to be notated with one being returned to Contractor for distribution and one kept by Contracting Officer.
C. After review, distribute as appropriate.
D. All shop drawings shall be certified by a Professional Engineer or Architect, licensed by the State of California, practicing within the scope of his license.
3.4 PRODUCT DATA/MANUFACTURERS’ LITERATURE
A. Submit electronic files capable of being electronically notated.
1. Mark to identify applicable Products, models, options, and other data;
supplement manufacturers’ standard data to provide information unique to the Work.
B. Include manufacturers’ installation instructions only when required by Specifications or specifically requested by Contracting Officer.
Division 1 01 33 00 - 3 Submittals
1. Maintain electronic copy of manufacturer installation instruction and recommendations in Contractor’s field office computer for review.
3.5 SAMPLES
A. Submit specified product including color, texture, and patterns as applicable for product when relevant information has been specified.
B. Submit full range of manufacturers’ standard colors, textures, and patterns for Contracting Officer’s selection when specific color, texture, or pattern has not been specified.
C. Submit samples to illustrate functional characteristics of Product with integral parts and attached devices.
D. Coordinate submittal of different categories for interfacing work.
E. Include identification on each sample, giving full information.
F. Submit number of samples required by Contract Documents.
1. Maintain one set of approved samples at Project Field Office.
G. Sizes: Provide the following sizes, unless otherwise specified.
1. Flat or Sheet Products: Minimum 6” square, maximum 12” square.
2. Linear Products: Minimum 6”, maximum 12” long.
3. Bulk Products: Minimum one pint, maximum one gallon.
H. Full size samples may be used in the Work upon approval.
3.6 MANUFACTURERS’ CERTIFICATES
A. Submit electronic certificates in accordance with requirements of each Specification section.
3.7 SUBSTITUTION REQUESTS
A. Within a period of 35 days after award of Contract, or 15 days prior to the Notice to Proceed, Contracting Officer will consider formal requests for substitutions only from the Contractor.
1. Requests not including a proposed cost or time reduction will not be considered unless Contractor submits supporting information indicating specified materials are not available.
2. Contracting Officer will consider one request for substitution for each material;
where requests are denied Contractor shall be required to provide specified material.
3. After initial period, requests will be considered only when a product becomes unavailable through no fault of the Contractor; more than one request for substitution will be considered if necessary.
Division 1 01 33 00 - 4 Submittals
B. Submit each request with sequentially number “Substitution Request Transmittal” acceptable to the Contracting Officer; submit separate request for each product and support each request with:
1. Product identification with manufacturer’s literature and samples where applicable.
2. Name and address of similar projects on which product has been used, and date of installation.
C. Submit itemized comparison of proposed substitution with product specified and list significant variations.
D. Submit data relating to changes in construction schedule.
E. Include accurate cost data comparing proposed substitution with product and amount of net change in Contract price.
1. Include costs to other contractors and costs for revisions to Drawings, details or Specifications.
F. Substitution will not be considered for acceptance when:
1. Then are indicated or implied on submittals without a formal request from Contractor.
2. They are requested directly by a subcontractor or supplier.
3. Acceptance will require substantial revision of Contract Documents.
G. Substitute products shall not be ordered without written acceptance of Contracting Officer.
H. Contracting Officer will determine acceptability of proposed substitutions and reserves right to reject proposals due to insufficient information.
3.8 AS-BUILT DRAWINGS
A. Upon completion of the project, the Contractor shall submit two (2) printed complete sets of full size as-built drawings of the project.
B. A complete set of drawings shall include all contract drawings and shop drawings.
C. The final As-built drawings shall also be provided in an electronic format that is suitable for reproduction.
D. The As-built drawings shall clearly indicate the final revision date of the drawings and clearly labeled that they are As-built drawings.
E. The As-built drawings shall include the stamp of a Professional Engineer or Architect, licensed by the State of California, practicing within the scope of his license.
F. Clearly mark in red any changes or deviations from the contract and shop drawings. Include changes in location, material, substitutions, and any other information pertinent to the Work that was performed.
Division 1 01 33 00 - 5 Submittals
Division 1 01 33 00 - 6 Submittals
SECTION 01 60 00
PRODUCT REQUIREMENTS
A. Section Includes: General requirements for products; delivery, storage, and handling;
protection; product warranties; and systems demonstration.
1.02 Definitions
A. Products: Items purchased for incorporation into the Work, whether purchased for the Project or taken from previously purchased stock. The term "product" includes the terms "material", "equipment", "system", and terms of similar intent.
1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation, shown or listed in manufacturer's published product literature, that is current as of date of the Contract Documents.
2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.
3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.
B. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
C. Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer for a particular product and specifically endorsed by manufacturer to Government.
D. Special Warranty: Written warranty required by or incorporated into the Contract Documents, either to extend time limit provided by manufacturer's warranty or to provide more rights for Government.
1.03 Delivery, Storage, and Handling
A. General: Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.
B. Scheduling:
1. Place order for products in time to avoid job delay or hindrance.
2. Schedule deliveries to coincide with the construction schedule as nearly as possible and in order to minimize long-term storage at the Project site and to prevent overcrowding of construction spaces.
3. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.
Division 1 01 60 00 - 1 Basic Product Requirements
C. Packaging: Minimize packaging for delivery, storage and handling.
1. Design packaging, when necessary to protect products, to maximize reuse of containers by material suppliers or product manufacturers.
D. Delivery:
1. Deliver manufactured products in their original, unbroken containers or bundles, dry, and clearly labeled with manufacturer's name, brand, and grade seal or model number.
2. Transport and handle in accordance with manufacturer’s written instructions.
3. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage to products and their finishes.
E. Inspect products on delivery to ensure that products comply with Contract Document requirements, that quantities are correct, and that products are undamaged and properly protected. Promptly remove damaged or defective products from site and replace.
F. Storage:
1. Store and protect products in accordance with manufacturer's written instructions, with seals and labels intact and legible.
2. Store sensitive products in weather-tight, climate controlled enclosures. Maintain within temperature and humidity ranges required by manufacturer's instructions.
3. For exterior storage of fabricated products, place on sloped supports above ground. Cover products subject to deterioration with impervious sheet covering. Provide adequate ventilation to avoid condensation.
4. Provide off-site storage and protection when site does not permit on-site storage or protection.
5. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.
6. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.
7. Arrange storage of products to permit access for inspection and measurement of quantity or counting of units. Periodically inspect to verify products are undamaged, and are maintained under specified conditions. Do not use products that are damaged from any cause.
1.04 Product Warranties
A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.
B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution.
1. Specified Form: Refer to Section 01 77 00 for warranty form.
2. Refer to Divisions 2 through 16 for specific content requirements and particular requirements for submitting special warranties.
C. Submittal Time: Comply with requirements in Section 01 77 00 - Closeout Procedures.
PART 2 - PRODUCTS
Division 1 01 60 00 - 2 Basic Product Requirements
2.01 Products
A. Products are defined to mean new materials, machinery, components, equipment, fixtures, and systems comprising the Work. Products do not include machinery and equipment used for preparation, fabrication, conveying or erection of the Work. Products may also include existing materials or components required for reuse.
B. Use only new, unused products suitable for the intended use, unless specifically noted otherwise.
C. Comply with Specifications and referenced standards as minimum requirements.
D. Components required to be supplied in quantity within a Specification section shall be of the same type, made by the same manufacturer, and shall be interchangeable.
E. Follow the installation and/or maintenance directions provided by the manufacturer for all products, except as specifically noted otherwise.
F. Clean existing materials to be reused and reinstall at locations shown on the Drawings.
G. UL Labels: Provide UL labels on all materials and equipment for which Underwriters
Laboratories, Inc. standards have been established.
H. Verification Of Non-Contamination: For each of the following materials provided, submit a letter from the manufacturer certifying that products are totally free of all forms of polychlorinated biphenyl (PCB) or asbestos, including actinolite, amosite, anthophyllite, chrysotile, crocidolite, and tremolite.
1. Low density fill.
2. Firestopping.
3. Waterproofing.
4. Sealants.
5. Mechanical insulation.
6. Electrical isolators.
7. Other products indicated in the specification.
3.01 Demonstration
A. Prior to final inspection, demonstrate operation of each system to Contracting Officer and Government.
B. Instruct Government's personnel in operation, adjustment, and maintenance of equipment and systems, using the operation and maintenance data as the basis of instruction. Provide instruction manuals where required per Section 01 77 00 – Closeout Procedures.
Division 1 01 60 00 - 3 Basic Product Requirements
Division 1 01 60 00 - 4 Basic Product Requirements
SECTION 01 74 00
PROJECT CLEANUP
A. Section Includes: The disposal of excess material from clearing and grubbing, excavation, building construction, cleaning, and any other operation in which waste is generated.
B. Measurement and Payment: No separate payment shall be made for work specified in this Section. Compensation for this work will be considered included in the payment for the completed Project.
PART 2 - PRODUCTS (Not used)
3.01 Workmanship
A. Site shall be restored to as near its original condition as possible. All debris and unused material shall be removed from the site. All debris shall be disposed off the jobsite, in accordance with local regulations. Local Inyo County landfills are open as follows:
a. Lone Pine Landfill is open Friday, Saturday and Monday from 7:00 am to 3:00 pm.
b. Independence is open Sunday from 7:00 am to 3:00 pm and Thursday 7:30 am to 3:30 pm.
More information can be found by calling 760-937-5491 or at http://www.inyocountysolidwaste.com/inyo_waste_locations.html
B. Concrete trucks shall not be washed out in the Project area. Burning of material is not allowed.
3.02 Final Cleaning
A. Execute final cleaning prior to request for final inspection. Restore or refinish surfaces that are damaged due to work of this contract to original condition.
B. Clean shall be interpreted as meaning the level of cleanliness generally provided by skilled professional cleaners using commercial-quality building maintenance equipment and materials.
C. Use only cleaning materials and equipment that are compatible with the surface being cleaned, as recommended by the manufacturer of the material being cleaned.
D. Building:
1. Clean interior and exterior glass and surfaces exposed to view adjacent to construction area.
2. Remove temporary labels, stains, and foreign substances.
3. Polish transparent and glossy surfaces adjacent to construction area.
Division 1 01 74 00 - 1 Project Cleanup http://www.inyocountysolidwaste.com/inyo_waste_locations.html
4. Sweep and vacuum all floor surfaces, windowsills, etc. adjacent to construction areas.
5. Clean equipment and fixtures to a sanitary condition.
E. Site:
1. Sweep sidewalks, walkways, and patios, and existing paved areas used to access the construction area.
2. Rake clean landscape surfaces adjacent to construction area.
F. Remove tools, waste and surplus materials, equipment, temporary buildings, sheds, scraps, temporary utilities, construction debris, rubbish, and construction facilities from the site.
G. Adjust operating products and equipment to ensure smooth and unhindered operation.
Division 1 01 74 00 - 2 Project Cleanup
SECTION 01 77 00
CLOSEOUT PROCEDURES
A. Section Includes: Closeout procedures, adjusting, project record documents, operation and maintenance data, spare parts and maintenance materials, and warranties and bonds.
1.02 Closeout Procedures
A. Comply with procedures stated in General Conditions of the Contract for issuance of Certificate of Substantial Completion.
B. When Contractor considers Work has reached final completion, submit written certification that
Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Contracting Officer's inspection.
C. In addition to submittals required by the Conditions of the Contract, provide submittals to
Contracting Officer that are required by governing authorities.
D. Submit a final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.
E. Contracting Officer will issue a final Change Order reflecting approved adjustments to Contract
Sum not previously made by Change Order.
1.03 Project Record Documents
A. Maintain on the site one set of the following Record Documents to record actual revisions to the Work.
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other Modifications to the Contract.
5. Approved shop drawings and product data.
B. Store Record Documents separate from documents used for construction. Information to be recorded shall be concurrent with construction progress.
C. Record Drawings: Do not permanently conceal any work until required information has been recorded. Legibly mark each item to record actual construction including:
1. Measured depths of foundations in relation to finish first floor datum.
2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.
4. Field changes of dimension and detail.
5. Details not on original Contract Drawings.
Division 1 01 77 00 - 1 Project Cleanup
6. Deviations from sizes, locations, and other changes to installation as shown on the Contract Documents.
7. Established locations of underground work, points of connection with existing utilities, changes in direction of underground lines, locations of valves, manholes, etc.
8. Locations of all items not concealed which Contractor elects to vary from Contract Documents, with Contracting Officer's prior review/approval.
9. Provide numbering of each electrical circuit.
D. Specifications: Legibly mark and record at each Product section a description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and Modifications with corresponding Addenda or
Modification number.
E. Submit all Record Documents to Contracting Officer with claim for Substantial Completion inspection. Submit documents with a transmittal letter containing date, Project title, Contractor's name and address, list of documents, and signature of Contractor.
F. Contracting Officer will return Contract Drawings Record Documents to the Contractor for final
Record Document preparation. Two complete, accurate sets of As-builts shall be submitted to the Contracting Officer printed in full sized sheets on ANSI D sized paper. These drawings will also be provided on CD’s in Autocad 2012 or later format. The Contractor shall use a separate drawing layer (or layers as necessary) labeled “As Builts”, and include the term “As Built” in the sheet title block. The Contracting Officer shall provide a CD of the solicitation drawings to the Contractor for this purpose.
G. Government will not make Final Payment to Contractor until the Record Documents are provided by the Contractor.
1.04 Operation and Maintenance Data
A. Submit two complete sets in final form 10 days prior to final inspection. Normal sheet size shall be 8-1/2 x 11 inch text pages, in three D side-ring binders with durable plastic covers. Punch holes shall not obscure any data. Fold oversize sheets and insert them in 8-1/2 x 11 inch clear pocket sleeves place in the binder. This copy will be returned after final inspection, with Contracting Officer comments. Revise content of documents as required prior to final submittal.
B. Prepare binder covers with printed title "OPERATION AND MAINTENANCE
INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.
C. Internally subdivide the binder contents with permanent page dividers, logically organized as described below; with tab title clearly printed under reinforced laminated plastic tabs.
D. Contents:
Entire content shall be completely legible or it will be rejected.
1. Prepare a Table of Contents for each volume, with each Product or system description identified, type on 30-pound white paper.
Division 1 01 77 00 - 2 Project Cleanup
2. Part 1: Directory, listing names, addresses, and telephone numbers of Architect, Contractor, Subcontractors, and major equipment suppliers.
3. Part 2: Operation and maintenance instructions, arranged by system and subdivided by specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following:
a. Significant design criteria.
b. List of equipment.
c. Parts list for each component.
d. Operating instructions.
e. Maintenance instructions for equipment and systems.
f. Maintenance instructions for finishes, including recommended cleaning methods and materials and special precautions identifying detrimental agents.
4. Part 3: Project documents and certificates, including the following:
a. Shop drawings and product data.
b. Air and water balance reports.
c. Certificates.
d. Photocopies of warranties and bonds.
e. Test data and results
1.05 Spare Parts and Maintenance Materials
A. Provide products, spare parts, extra materials, and maintenance materials in quantities specified in individual specification Sections.
B. Coordinate delivery with Government; deliver to Project site and obtain receipt prior to final payment.
C. Keys: Turn over keys to Contracting Officer for locked doors, panels, gates, etc., all properly tagged and organized. Obtain a signed receipt for them, returning a copy of receipt to the Contracting Officer.
D. Provide services of skilled and competent supervisory personnel to instruct the Government's personnel in the operation and maintenance of all operating equipment and systems provided as part of the Contract. Schedule the demonstration and instruction through the Contracting Officer.
1.06 Warranties and Bonds
A. Provide duplicate notarized copies. Execute and assemble documents from Contractor's submittals and documents executed by subcontractors, suppliers, and manufacturers. Provide table of contents and assemble in commercial quality, hard back, three D side ring binder, 2 inch maximum, with durable plastic cover.
B. Submit material prior to final Application for Payment. For equipment put into use with
Government's permission during construction, submit within 10 days after first operation. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within ten days after acceptance, listing date of acceptance as start of warranty period.
C. The General Conditions of the Contract cover the Contractor's responsibility to remedy defects due to faulty workmanship and materials which appear within one year from the Date of Acceptance. Warranties for more than one year, where indicated in the various sections of the
Division 1 01 77 00 - 3 Project Cleanup
Specifications, shall be in the form of a warranty written on the letterhead of the Contractor, subcontractor, or supplier doing the work or supplying the item to be warranted, as follows:
WARRANTY FOR :
We hereby warrant that the which we have installed in InterAgency Visitor Center, Lone Pine, California for USDA FOREST SERVICE, Inyo National Forest , has been done in accordance with the Drawings and Specifications, and that the work, as installed, will fulfill the requirements of the warranty included in the Specifications.