1._10_Road_Supplemental_Specifications.pdf
PDF 181 KB Posted
- Attached to
- 10 Road Resurfacing Project Federal contract opportunity
- Solicitation number
- AG-9AC7-S-16-0062
About this file
Project Specs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG-9AC7-S-16-0062_Solicitation_pkg.pdf | ||
| 5._SF_24_BID_BOND.pdf | ||
| 3._PAL_Fire_Plan_complete.pdf | ||
| 2._Plans.pdf | ||
| 4._CA9 _mod_5_Dated_030416.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
10 ROAD RESURFACING CONSTRUCTION
SPECIAL PROJECT SPECIFICATIONS
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
107.02 Protection and Restoration of Property and Landscape
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
151 - Mobilization
155 - Schedules for Construction Contracts
155 Delete
156 - Public Traffic
156.03 Accommodating Traffic During Work
171 - Weed and Disease Prevention
409 - Asphalt Surface Treatment
409.02 Material
409.06 Weather
409.06 Date & Time
409.08 Asphalt Application
409.10 Fog Seal
409.11 Single Course Surface Treatments
Table 409-1 Approximate Quantities of Material-Single Course Surface Treatment
411 - Asphalt Prime Coat
411.06 Asphalt Application
414 - Asphalt Pavement Crack and Joint Sealing
414.02 Material
414.05 Crack Cleaning and Sealing
414.05 Asphalt Pavement Crack Sealing and Filling
635 - Temporary Traffic Control
635.03 General
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
Table 703-2 Correction
Table 703-2 Correction
703.10(e) Flakiness Index
703.10(i) Adherent Coating
Table 703-7 Target Value Ranges
712 - Joint Material
712.01 Sealants, Fillers, Seals, and Sleeves
712.01 Sealants, Fillers, Seals, and Sleeves
718 - Traffic Signing and Marking Material
718.02 Reserved
718.02 Protective Overlay Film and Edge Film
718.05 Aluminum Panels
718.08 (b)(2)(c)Signpost - Square tubular steel posts
718.14 (g)Waterborne Traffic Paint - Daylight reflectance
718.15 (a)Epoxy Markings Pigments
718.15 (g)Epoxy Marking - Drying Time
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005 101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
http://www.nist.gov/
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction.
Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
107.10_05_us_05_04_2007
107.02 Protection and Restoration of Property and Landscape
Add the following:
Meet the requirements chapters 10, 11, and 12.2 in their entirety of “Water Quality Management for National Forest System Lands in California Best Management Practices” dated September 2000
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
151 - Mobilization
151.03_nat_us_08_05_2005
151.03 Payment
Delete the entire subsection and add the following:
151.03 Payment
Mobilization is considered an indirect cost of this contract and will not be compensated as a separate work item.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.00_nat_us_04_17_2007
Delete Section 156 in its entirety and replace with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Construction sign panels 633 Retro-reflective sheeting 718.01 Temporary concrete barrier 618 Temporary plastic fence 710.11 Temporary traffic control devices 718.22
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags.
Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.
156.03_nat_us_02_24_2005
156.03 Accommodating Traffic During Work.
Delete the following from the last paragraph:
according to Subsection 106.07(b)
171 - Weed and Disease Prevention 171.00_nat_us_03_30_2005
Description
171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest System lands.
Material
171.02 Conform to the following Subsection:
Water 725.01
Construction Requirements
171.03 General . Notify the CO in writing at least 15 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Perform all work at a location designated on the plans or other locations approved in writing. Provide the CO with an opportunity to monitor the washing and inspection.
171.04 Equipment. Use a high pressure washing system.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment. Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
Measurement
171.08 Do not measure weed prevention for payment.
Payment
171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for Section 151-Mobilization.
409 - Asphalt Surface Treatment
409.02_nat_us_05_12_2004
409.02 Material.
Add the following:
When designated, conform to applicable State department of transportation asphalt cement or emulsified asphalt requirements.
409.06_nat_us_05_12_2004
409.06 Weather.
Delete the first paragraph and replace with the following:
Apply surface treatments with aggregate only when ambient air and surface temperatures are above 60 °F and rising in the shade, when the weather is not foggy or rainy, and when rain is not forecast for at least 24 hours after application.
409.06 Date & Time.
Add the following.
Construct fog seal and single-course surface treatments between _May 1_ (dates) and __Oct 1__ and multiple-course surface treatments between ______ and ______.
409.08_nat_us_06_21_2005
409.08 Asphalt Application.
Add the following to the 3rd paragraph:
Ensure the length of spread is no more than what can be covered with aggregate within 1 minute of the asphalt application.
409.10 Fog Seal.
Add the following to the first paragraph:
Dilute by adding an equal amount of water to the emulsified asphalt. Do not cut the emulsified asphalt more than once.
409.11 Single Course Surface Treatments.
Add the following:
Do not permit traffic to travel over any Asphalt Surface Treatment until completion of rolling.
409.10_nat_us_08_12_2004
Delete Table 409-1 and substitute the following:
Table 409-1 Approximate Quantities of Material-Single Course Surface Treatment
Table 409-1 Approximate Quantities of Material for
Single-Course Surface Treatment
D es ig na tio n Nominal
Maximum Size of
Aggregate
Aggregate Gradation (1)
Estimated Quantity of Aggregate (2) pounds/yd2
Estimated Quantity of Emulsified Asphalt (3) gallons/yd2
Estimated Quantity of
Asphalt Binder (3) gallons/yd2
1A 3/4 inch B 40 – 49 0.40 – 0.55 0.27 – 0.38 1B 1/2 inch C 26 – 29 0.31 – 0.44 0.20 – 0.31 1C 3/8 inch D 20 – 26 0.20 – 0.35 0.13 – 0.24 1D No. 4 E 15 – 20 0.15 – 0.22 0.11 – 0.18 1E Sand F 9 – 15 0.11 – 0.18 0.09 – 0.15
(1) See Table 703-7 for aggregate gradations.
(2) Aggregate masses are for aggregates having a bulk specific gravity of 2.65, as determined by AASHTO T 84 and T 85. Make proportionate corrections when the aggregate furnished has a bulk specific gravity above
2.75 or below 2.55.
(3) Adjust the asphalt content for the condition of the road.
411 - Asphalt Prime Coat
411.06_nat_us_05_12_2004
411.06 Asphalt Application.
Add to the fifth paragraph:
If emulsified asphalt is used, use choker aggregate.
414 - Asphalt Pavement Crack and Joint Sealing
414.02_nat_us_05_12_2004
414.02 Material.
Add the following:
Backer Rod 712.01(g) Low-modulus rubberized asphalt 712.01 (a) (7)
414.05_nat_us_05_12_2004
414.05 Crack Cleaning and Sealing.
Delete and replace with:
414.05 Asphalt Pavement Crack Sealing and Filling.
Crack seal and fill only when internal pavement temperatures are between 36 and 68 °F the road surface is dry, there is no frost in the road section, and the weather is not foggy or rainy.
Heat, mix, and apply the crack sealing and filling materials as recommended by the sealant manufacturer. Submit a copy of the manufacture’s recommendations to the CO prior to the start of work.
Prepare cracks between 1/4 inch and 1 inch and apply sealant by one of the following methods:
• Crack Sealing - Rout and clean all cracks between 1/4 inch and 1 inch wide. Rout cracks to produce a reservoir with straight ½ inch vertical walls and a 1 1/2 inch wide flat bottom. Use a low-modulus rubberized asphalt. Completely fill the routed cross section flush with the pavement surface.
• Crack Filling - Clean the crack between 1/4 inch and 1 inch wide. Prepare cracks to a depth of at least three times the crack width. Ensure crack sealing materials penetrates more than twice the crack width.
For cracks between 1/2 inch and 1 inch where sealant penetrates more than two times the crack width, use a backer rod.
For cracks with a width greater than or equal to 1 inch, clean and fill flush to the existing surface with asphalt mix according to Section 401, 402, 403, 404, or 417.
For cracks less than ¼ inch wide, clean and fill with CSS-1, SS-1, or joint sealant. Apply a sealant band less than 2 inches over the crack, such that the crack is centered under the band. Submit a copy of, and adhere to, the manufacture’s recommendations for heating and applying the joint sealant.
Clean cracks with a stream of air to remove all dirt, dust, or deleterious matter adhering to the crack walls or remaining in the crack cavity so that the crack is clean and dry when the sealant is applied.
Blow or brush dry material off the pavement surface. Avoid damage to the adjacent pavement.
Use approved methods to protect all seal materials from being picked up by traffic. Treat seal material tracked onto the road surface as directed by the CO.
635 - Temporary Traffic Control 635.03_nat_us_05_13_2004
635.03 General.
Add the following:
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
703 - Aggregate 703.05_nat_us_08_14_2009
Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
(3) Plastic limit, AASHTO T 90 Nonplastic
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89 35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12% 2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 75% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Do not furnish material that contains asbestos fibers.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradation Table 703-16
(2) Plastic Index, AASHTO T 90 Less than 9
(3) Los Angeles abrasion, AASHTO T 96 55% max.
(4) Free from organic matter and lumps or balls of clay.
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Delete Table 703-2 and replace with the following:
T ab le
-2
T ar ge t V al ue R an ge s f or
S ub ba se a nd
B as e G ra da tio n
Pe rc en t b y M as s P as si ng D es ig na te d Si ev e
(A A
SH
T
O T an d
T
1)
G ra di ng
D es ig na tio n
E (B as e)
(6
(6
(4
4.
7.
(3
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al ue s..
D (B
(6
(6
(6
(4
4.
7.
(3
C (B
(6
(6
4.
–7 .0
(3
B (S ub ba se
(8
4.
.0 (4
A (S ub ba se
(7
(6
(4
4.
8.
(3
Si ev e Si ze
2½ in ch
1½
3/
1/
N o.
N o.
Delete Table 703-3 and replace with the following:
T ab le
-3 ar ge t V al ue R an ge s f or
S ur fa ce
G ra da tio n Pe rc en t b y
M as s P as si ng
D es ig na te d
Si ev e (A
A
SH
T O
T an d T
1) ra di ng
D es ig na tio n
U
(6
(7
(5
8.
.0 (4
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al ue s.
If th e pl as tic ity in de x
(P I) is gr ea te r t ha n 0, th e
TV
ra ng e fo r t he N o.
si ev e siz e is
-1
(4
(7
(5
8.
.0 (4
S 10
(6
(7
(5
8.
.0 (4
H
(6
(6
(5
9.
.0 (4
(6
(6
(5
.0
6.
(4
F 10
-1
-8
-6
(6
-5
-3
(6
-2
(5
.0
-1 6.
(4
Si ev e Si ze
N o.
N o.
Add Table 703-16:
Table 703-16
Gradation Requirements for Screened Aggregate
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation L M N O P Q R
6 inch 100 100
4 inch 100 100
3 inch 100 100
2 inch 100
No. 4 15-45 15-45 15-45
703.07_nat_us_03_02_2005
Table 703-2 Correction Include the following substitution
In Table 703-2, delete the “436 – 74 (6)” percent by mass passing for grading E (base) No. 4 sieve size and substitute “36 – 74 (6).”
Table 703-2 Correction Include the following substitution
In Table 703-2, delete the “436 – 74 (6)” percent by mass passing for grading E (base) No. 4 sieve size and substitute “36 – 74 (6).”
703.10_nat_us_04_11_2011
703.10(e) Flakiness Index.
Delete and replace with the following:
Flakiness Index, FLH T 508 30% max.
703.10(i) Adherent Coating.
Add the following:
Adherent coating on the aggregate, FLH T 512 0.5% max.
703.10_nat_us_03_02_2005
Delete Table 703-7 and substitute the following:
Table 703-7 Target Value Ranges
Table 703-7 Target Value Ranges for
Single and Multiple Course Surface Treatment Aggregate Gradation
Sieve Percent by Mass Passing Designated Sieve
(AASHTO T 27 & T 11)
Size
Grading Designation
A B C D E F 1½ inch 100(1)
1 inch 90-100(3) 100(1) ¾ inch 0-35(5) 90-100(3) 100(1)
½ inch 0-8(3) 0-35(5) 90-100(3) 100(1)
⅜ inch — 0-12(3) 0-35(5) 85-100(3) 100(1) 100(1) No. 4 — — 0-12(3) 0-35(5) 85-100(3) 85-100(1)
No. 8 — — — 0-8(3) 0-23(4) —
No. 200 0-1(1) 0-1(1) 0-1(1) 0-1(1) 0-1(1) 0-10(1)
(1) Statistical procedures do not apply.
( ) The value in the parentheses is the allowable deviation (±) from the target values.
712 - Joint Material 712.01_nat_us_08_05_2009
712.01 Sealants, Fillers, Seals, and Sleeves.
(b) Preformed expansion joint fillers.
Add to the end of the first sentence:
except on abutment, pier cap or other bent more than one piece may be used.
712.01_nat_us_03_02_2005
712.01 Sealants, Fillers, Seals, and Sleeves.
(a) Joint sealants and crack fillers. Add the following:
(7) Low-Modulus Rubberized Asphalt. Conform to ASTM D 3405 and the following.
Cone Penetration, 75oF 100-150 Cone Penetration, -0oF 25 minimum Flow, 140oF, 5h 3/8 in. maximum Resilience 30-60% Bond, -20oF, 200% extension Pass 3 Cycles Recommended Pour Temperature 380oF Safe Heating Temperature 410oF Asphalt Compatibility Pass
718 - Traffic Signing and Marking Material 718.02_nat_us_03_02_2005
718.02 Reserved.
Replace this section with the following:
718.02 Protective Overlay Film and Edge Film.
Protective overlay film will be a high performance flouropolymer film such as 3M Scotchlite Premium Protective Overlay Film Series 1160 or approved equal.
Edge film will be a pressure-sensitive, premium-quality, clear, ultraviolet-resistant, 3 inches wide vinyl film.
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
718.08_nat_us_03_27_2007
718.08 (b)(2)(c)Signpost - Square tubular steel posts
Delete the existing subsection and substitute the following:
(c) Galvanizing after punching ASTM A 653M, (inside and outside of post) coating Z275 designation
718.14_nat_us_03_02_2005
718.14 (g)Waterborne Traffic Paint - Daylight reflectance
Delete the existing subsection and substitute the following:
(g) Daylight reflectance. (Without glass beads)
(1) White, ASTM E 1347 84% relative to magnesium oxide standard
(2) Yellow, ASTM E 1347 55% relative to magnesium oxide standard
718.15_nat_us_03_27_2007
718.15 (a)Epoxy Markings Pigments Delete the existing subsection and substitute the following:
(2) Yellow.
(a) Chrome yellow (PbCrO4), 23% min.
ASTM D 126, type III.
(b) Epoxy resin 70 to 77%
718.15_nat_us_03_27_2007
718.15 (g)Epoxy Marking - Drying Time Delete the existing subsection and substitute the following:
(g) Drying time. 15 mil film thickness with beads.
(1) Laboratory at 72o F, ASTM D 711 30 minutes maximum to no-pick-up condition
(2) Field at 77 oF, viewed from 50 feet 10 minutes maximum to no-pick-up condition
| Table of Contents |
| Preface |
| 101 - Terms, Format, and Definitions |
| 101.01 Meaning of Terms |
| 101.03 Abbreviations. |
| 101.04 Definitions. |
| 102 - Bid, Award, and Execution of Contract |
| 102 Bid, Award, and Execution of Contract |
| 103 - Scope of Work |
| Deletions |
| 104 - Control of Work |
| Deletions |
| 104.06 Use of Roads by Contractor |
| 105 - Control of Material |
| 105.02 Material Sources. |
| 105.02(a) Government-provided sources. |
| 105.05 Use of Material Found in the Work. |
| 106 - Acceptance of Work |
| 106.07 Delete |
| 107 - Legal Relations and Responsibility to the Public |
| 107.05 Responsibility for Damage Claims. |
| 107.06 Contractor’s Responsibility for Work. |
| 107.09 Legal Relationship of the Parties. |
| 107.10 Environmental Protection. |
| 107.02 Protection and Restoration of Property and Landscape |
| 108 - Prosecution and Progress |
| 108 Delete. |
| 109 - Measurement and Payment |
| 109 Deletions |
| 109.02 Measurement Terms and Definitions. |
| 151 - Mobilization |
| 155 - Schedules for Construction Contracts |
| 155 Delete. |
| 156 - Public Traffic |
| 156.03 Accommodating Traffic During Work. |
| 171 - Weed and Disease Prevention |
| 409 - Asphalt Surface Treatment |
| 409.02 Material. |
| 409.06 Weather. |
| 409.06 Date & Time. |
| 409.08 Asphalt Application. |
| 409.10 Fog Seal. |
| 409.11 Single Course Surface Treatments. |
| Table 409-1 Approximate Quantities of Material-Single Course Surface Treatment |
| 411 - Asphalt Prime Coat |
| 411.06 Asphalt Application. |
| 414 - Asphalt Pavement Crack and Joint Sealing |
| 414.02 Material. |
| 414.05 Crack Cleaning and Sealing. |
| 414.05 Asphalt Pavement Crack Sealing and Filling. |
| 635 - Temporary Traffic Control |
| 635.03 General. |
| 703 - Aggregate |
| 703.05 Subbase, Base, Surface Course, and Screened Aggregate. |
| Table 703-2 Correction |
| Table 703-2 Correction |
| 703.10(e) Flakiness Index. |
| 703.10(i) Adherent Coating. |
| Table 703-7 Target Value Ranges |
| 712 - Joint Material |
| 712.01 Sealants, Fillers, Seals, and Sleeves. |
| 718 - Traffic Signing and Marking Material |
| 718.02 Reserved. |
| 718.02 Protective Overlay Film and Edge Film. |
| 718.05 Aluminum Panels |
| 718.08 (b)(2)(c)Signpost - Square tubular steel posts |
| 718.14 (g)Waterborne Traffic Paint - Daylight reflectance |
| 718.15 (a)Epoxy Markings Pigments |
| 718.15 (g)Epoxy Marking - Drying Time |
File details come from the government source that posted it. Updated .