Amendment_1.pdf
PDF 488 KB Posted
- Attached to
- Fresno Air Attack Base Surface Treatment Federal contract opportunity
- Solicitation number
- AG-9AB5-S-17-0050
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MapsDrawings.pdf | ||
| Wage_Determination.pdf | ||
| Sol_AG-9AB5-S-17-0050.pdf | ||
| Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 5
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
Amendment 1 06/01/2017
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA Forest Service Southern California Service Area 1600 Tollhouse Road Clovis, CA 93611
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
AG-9AB5-S-17-0050
9B. DATED (SEE ITEM 11)
04/27/2017
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning _1__ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return Original copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Fresno Air Attack Base Resurfacing, Sierra National Forest, is amended as follows:
1. Extend the closing date/time to June 6, 2017 by 1:00 pm.
2. Replace the Schedule of Items pages with the attached Revised Schedule of Items pages.
3. Replace Drawing P-3 with the attached Revised Drawing P-3 “Fog Seal Plan”
4. The attached Q&A document is hereby included as part of any resulting contract.
5. The estimated start work date has been changed to November 1, 2017.
6. Section M.2: Evaluation Criteria (03) – Capacity is deleted and replaced with the following Evaluation Criteria (03)
Technical Approach:
“Criteria (03) – Technical Approach: Describe your ability to accomplish this project in its required timeframe including a technical narrative and tabular work schedule.”
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
MARY CANTRELL, Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
AG-9AB5-S-17-0050 Amendment 1
B - SECTION B - Supplies or Services and Prices/Costs Schedule of Items (REVISED)
ITEM
NO
DESCRIPTION UNIT UNIT COST QTY TOTAL
Quality Control and Quantity Measurement
LS $______________ 1 $_________________
Hot Bituminous Liquid Asphalt Emulsified Asphalt – Fog Seal
TON $______________ 12 $_________________
3 Mobilization LS $______________ 1 $_________________
Traffic Markings Single Reflectorized Solid Color White 4”
LF $______________ 305 $_________________
Traffic Markings Single Reflectorized Broken Color White 4”
LF $______________ 30 $_________________
Traffic Markings Single Reflectorized Solid Color Yellow 6”
LF $______________ 3060 $_________________
Traffic Markings Single Reflectorized Solid Color Yellow 12” (Between containment area)
LF $______________ 0 $_________________
Traffic Markings Single Reflectorized Broken Color Yellow 12” (Between containment area)
LF $______________ 0 $_________________
Traffic Markings Single Reflectorized Solid Color Yellow 6” (Containment area, taxi way border)
LF $______________ 2210 $_________________
Traffic Markings Reflectorized Hazard Warning Solid Color Yellow and Black 12”
LF $______________ 900 $_________________
Traffic Markings Reflectorized Bar Solid Color Yellow 36” (within containment areas)
EA $______________ 20 $_________________
Traffic Markings Reflectorized, Symbols and Letters Color White, Yellow and Blue (numbers, letters, arrows)
LS $______________ 235 $_________________
Aircraft Loading Pads Identification Blocks 7’ X 7’ Reflectorized, Colors Orange, Green, Red, Blue and Yellow
EA $______________ 15 $_________________
TOTAL – BASE ITEMS $_________________
ITEM
NO
DESCRIPTION UNIT UNIT COST QTY TOTAL
OPTION ITEM
2A Hot Bituminous Liquid Asphalt Emulsified Asphalt – Fog Seal
TON $______________ 5 $_________________
4A Traffic Markings Single Reflectorized Solid Color White 4” (parking, loading, buses, gate)
LF $______________ 2100 $_________________
5A Traffic Markings Single Reflectorized Broken Color White 4” (entrance centerline)
LF $______________ 200 $_________________
12A
Traffic Markings Reflectorized, Symbols and Letters Color White, Yellow and Blue (accessibility symbols, arrows, letters)
EA $______________ 50 $_________________
Traffic Markings Single Reflectorized Solid Color Blue, 4” (accessible parking)
LF $______________ 200 $_________________
Traffic Markings Double Reflectorized Solid Color Yellow 4” (centerline)
LF $______________ 185 $_________________
Traffic Markings Single Reflectorized Solid Color White 12” (stop bars)
LF $______________ 200 $_________________
TOTAL OPTION ITEMS $_________________
GRAND TOTAL (BASE +
OPTIONS)
Signature Date
Company Name DUNS
Email Phone
FAAB Resurfacing Job Walk Q&A
1. Please clarify if the Forest Service (FS) would like SS1H or a Seal coat applied to both Base Bid and Option 1, if so please provide the specification, application and spread rate? FP‐03 Specification Section 409
– Asphalt Surface Treatment. Change Seal Coat to Fog Seal. SS1H is the product, a slow setting emulsified asphalt diluted with water at a 50/50 ratio. Application shall be with a distributor spray bar, rate shall be 0.10‐0.15 gallons per square yard, a test strip shall determine exact application rate and may be adjusted thru out the project. Pay item is to remain in TONS.
2. Will the Forest Service require an onsite QC technician at all time? There shall be a QC technician on site and they may serve in dual roles.
3. Does the schedule of items referring to Pavement Markings Items reflect two coats of paint or one? Two
Coats
4. Will the contractor be responsible for providing low profile barricades around the construction limits on the airfield? YES
Will FS require these barricades to be lit with solar red lights? No. 28” Cones will be sufficient.
5. During the site visit there appeared to be black painted borders on all taxiway edge lines, hold bars, and centerline striping. Will this need to be reinstalled as the existing? NO, black borders are not required.
6. All existing striping symbols and painted markings shall be painted two coats unless otherwise noted, is there a time period between each coat? The wait time between coats shall be per manufacturer’s recommendation. Will each coat require reflective media? No, only the top coat shall have reflective media (glass beads).
7. Will the FS require any asbuilts of the existing striping prior to seal coating? The Contractor shall build according to plans and specifications. Contractor shall provide in their proposal the technical approach. See amendment 1.
8. In Option 1 (Parking Lot) is not ADA compliant. The contractor shall build according to plans and specifications (no changes).
9. Plan Sheet P‐4 Indicated with a revision bubble the directional arrows and number
1, 2 and 3 shall be moved to the East of the 12” yellow dashed double line.
10. Plan Sheet P‐4 Indicated with a revision bubble, the area south of the main entrance driveway from Clovis Ave. is included in the base bid (area behind fence in secure area).