amend 1.pdf

PDF 16 KB Posted

Attached to
HANDY MAN - RIO GRANDE FOREST Federal contract opportunity
Solicitation number
AG-82X9-S-10-0051
Issued by
Department of Agriculture Forest Service R2-Rocky Mountain Region

About this file

Amendment 1 - questions and answers

View the file

Other files for this federal contract opportunity

Other files attached to HANDY MAN - RIO GRANDE FOREST, newest first.
File Type Posted
amend 2 due date.pdf PDF
return.pdf PDF
building_rg_handyman_31210.htm HTM file
solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

1 1

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

Amendment 1 5/10/2010

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

ROCKY MOUNTAIN ACQUISITION SERVICE TEAM -

DURANGO OFFICE

15 BURNETT COURT

DURANGO, CO 81301

SAME AS BLOCK 6

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

XX

AG-82X9-S-10-0051

9B. DATED (SEE ITEM 11)

4/26/2010

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning _1_ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

NFXF3609 -$10,890

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return __1__ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

See attached page for questions asked and answers given.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

JOE MILBURN

Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer) 5/10/10

Q1: What facilities are involved on each District and where are they located?

A1: A partial list of the facilities include the following: potable water systems, waste water systems, offices, warehouses, picnic areas, campgrounds, bunkhouses, ranger houses, remote guard stations, garages, sheds, barns, shops, storage buildings, toilets stations.

These type of facilities are located all over the entire Rio Grande National Forest.

Estimated total facilities on Divide: 55 Estimated total facilities on Conejos Peak: 30 Estimated total facilities on Saguache: 30

Q2: How will the electrical inspection and plumbing inspections be handled, and does the handy man need to be licensed in the previously mentioned fields of work?

A2: Inspections - License is not a requirement, however Inspections are to be to current code standards and are the responsibility of the Handyman contractor solely. As stated in the contract, All work performed under this statement of work shall be in compliance with all appropriate local, state, and federal rules, regulations, codes and laws, such as the International Plumbing Code, National Fire Code, American Disability Act, National Electrical Code as examples.

The Contractor shall ensure Contractor personnel are adequately trained or certified to meet the requirements of this statement of work.

Q3: What type of warranty is required for new construction work?

A3: A 1 year workmanship warranty is required for all new construction. The warranty period begins when all work has been accepted.