Amendment No 1.docx

DOCX document 14 KB Posted

Attached to
Recovery-historical overview and context narrative Federal contract opportunity
Solicitation number
AG-82B1-S-10-0465
Issued by
Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center Intermountain

About this file

Q A

View the file

Other files for this federal contract opportunity

Other files attached to Recovery-historical overview and context narrative, newest first.
File Type Posted
0465 amendment 1 sf 30.pdf PDF
revised SF 18.pdf PDF
rfq pkg.docx DOCX document
Expierence Questionnaire.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment No. 1 to AG-82B1-S-10-0465 On the SF-18 block 6 change from 05/01/2010 to 09/31/2011 In block 5b for additional information contact add Tess Foster (202) 275-5860 Block 11(b) Delete delivery: 05/01/2010 and ignore the 40000 DO in the quantity and unit blocks, 11(c) & 11(d).

All questions must be received by 08/16/2010.

Quotes are due 08/23/2010 at 1700 MDT, mail to: Intermountain – EROC

740 Simms Street
Golden, CO 80401

Be sure to include the solicitation no. AG-82B1-S-10-0465 on the outside of the envelope.

FAXed quotes are not allowed.

Refer to Section 7 - Period of Performance under the Statement of Work: The draft is due 60 days from the completion of the field work.

1. The RFQ doesn't definitively describe the full boundary of the inventory area. Most importantly, should the eastern boundary of the area be considered to be the roadway intersection at the beginning of the canyon, the intersection with US 212, or another point?

A: The project area is within the west Fork of Rock Creek Drainage on FS administered lands outside of the wilderness boundary.

Does the study area extend upstream beyond the current end of the road?

A: See answer above.

What natural or other features should be considered as the north and south boundaries of the survey corridor? A map delineating the boundary of the inventory area would be extremely helpful.

A: See above answer.

2. Is it correct to assume that property types should correspond to resource types found within the study area, rather than resource types found only in the broader geographic area?

A: Yes

3. Is field inventory required for linear resources that may be identified in historic research, but which no longer exist as functional travel routes?

A: Yes

4. If extended oral history interviews are conducted, would it be acceptable to index rather than transcribe them?

A: No

5. Is it correct to assume that small-scale structural elements of a linear resource (such as retaining walls and culverts along a road) should be recorded as component features of the primary linear resource, rather than as separate sites?

A: Component features of the primary linear resource

6. If the project's background research and fieldwork determine to the agreement of all parties that an MPD submittal is not the most appropriate documentation for the study area, will the development of an alternate product be acceptable?

A: Yes with agreement of all parties

7. Is the size of the project area (e.g., in acres or square miles), and a list the Township, Range, and Sections covered by the project, or an outline of the project area on a USGS 1:24,000' map available?

A: The project area is on FS lands within the west Fork of Rock Creek Drainage outside of the Wilderness boundary.

8. Also, how many cultural properties have been inventoried in the project area to date?

A: There are over 25 recorded sites within the project area and one NRHP District.