AG-82B1-S-10-0372 supplemental Specs.pdf

PDF 450 KB Posted

Attached to
Lakeview Reeder Road Decommissioning Project Federal contract opportunity
Solicitation number
AG-82B1-S-10-0372
Issued by
Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center Intermountain

About this file

AG-82B1-S-10-0372 supplemental Specs

View the file

Other files for this federal contract opportunity

Other files attached to Lakeview Reeder Road Decommissioning Project, newest first.
File Type Posted
WD 95-0228 .pdf PDF
AG-82B1-S-10-0372 Amendment 0002.pdf PDF
AG-82B1-S-10-0372 Amendment 0001.pdf PDF
Lakeview_Reeder_Road_Decomissioning Drawings.pdf PDF
AG-82B1-S-10-0372 body.pdf PDF
AG-82B1-S-10-0372 Expierence Questionnaire.pdf PDF
AG-82B1-S-10-0372 SF33.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOREST SERVICE SUPPLEMENTAL

SPECIFICATIONS

For

PRIEST LAKE

LAKEVIEW REEDER

ROAD DECOMMISSIONING

U.S.D.A. FOREST SERVICE

IDAHO PANHANDLE NATIONAL FOREST, PRIEST LAKE RANGER DISTRICT

BONNER & PEND COUNTIES, IDAHO

Table of Contents

Preface

101 - Terms, Format, and Definitions

101.01 Meaning of Terms

101.03 Abbreviations

101.03 SI Symbols

101.04 Definitions

102 - Bid, Award, and Execution of Contract

Deletions

103 - Scope of Work

Deletions

104 - Control of Work

Deletions

104.06 Use of Roads by Contractor

106 - Acceptance of Work

106.01 Conformity with Contract Requirements

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims

107.09 Legal Relationship of the Parties

107.10 Environmental Protection

108 - Prosecution and Progress

Deletions

109 - Measurement and Payment

109.02 Measurement Terms and Definitions

109 Deletions

151 - Mobilization

155 - Schedules for Construction Contracts

156 - Public Traffic

157 - Soil Erosion Control

157.03 General

203 - Removal of Structures and Obstructions

Description

203.03 Salvaging Material

203.05 Disposing of Material

Payment

211 – Rehabilitation of Abandoned Roadways

211.01 Delete

Description

Definition of Stream Channel Restoration Categories

Construction Requirements

Measurement

Payment

622 - Rental Equipment

622.02 Rental Equipment

625 - Turf Establishment

Construction

713 - Roadside Improvement Material

713.05 Mulch

FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS

PRIEST LAKE ROAD DECOMMISSIONING

REGION 1

IDAHO PANHANDLE NATIONAL FOREST

Preface

Preface_wo_03_15_2004_m

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of

National Forest System Roads.

IDAHO PANHANDLE NATIONAL FOREST

101 - Terms, Format, and Definitions

101.00_nat_08_12_2004

101.01_nat_05_11_2004

101.01 Meaning of Terms.

Add the following:

Delete all references in FP-03 to Transportation Acquisition Regulations (TAR). For

Timber Sales, delete all references in FP-03 to Federal Acquisition Regulations (FAR).

101.03_nat_05_17_2004

101.03_0117_01_05_2005

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

FSSS

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association

Forest Service Supplemental Specification

Mine Safety and Health Administration

National Institute of Standards and Technology

National Electrical Safety Code

West Coast Lumber Inspection Bureau

101.04_nat_07_16_2004

101.03 SI Symbols.

Add the following to (b) SI Symbols:

mp Milepost ppm Part Per Million

101.04_0117_1_5_2005

IDAHO PANHANDLE NATIONAL FOREST

Add the following:

(e) Abbreviations

& And

Avail Available

Coat Coating

Const Construction

Dwgs Drawings

Gov't Government

Incl Culv Exc Includes Culvert Excavation

Ind Removal /Trees Individual Removal of Trees

Lg Large

Log Logs

Med Medium

M.Gals.Mi. or MGM One Thousand Gallon Miles

Opt Options

P.M. Placement Method

S.T. Slash Treatment

Sm Small

Stl Steel

Str Structure

TH or Thick Thickness

Tbr Timber

W/ With

101.04_nat_07_16_2004

101.04_0117_01_15_2005

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the

“purchaser”.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse

IDAHO PANHANDLE NATIONAL FOREST

public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal

Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale

Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition

Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the

Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, methods of measurement, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

101.03_17_1_5_2005

Noxious Weeds or Weeds--Any exotic plant species established or that may be introduced in the State which may render land unfit for agriculture, forestry, livestock, wildlife, or other beneficial uses and which is designated by the State's Department of

Agriculture, or by the County's weed management district, or by other appropriate agencies having jurisdiction, or as listed on the current "All States Noxious Weed List".

Shop Drawings--Incidental design sheets and/or drawings which the Contractor is required to submit to the Forest Service. Shop drawings shall conform to the contract requirements, but they are not part of the contract drawings. They may be drawings, IDAHO PANHANDLE NATIONAL FOREST diagrams, schedules, performance charts, brochures, and similar data prepared by the

Contractor, subcontractor, manufacturer, suppliers, or distributors that illustrate how specific portions of the work are to be fabricated or installed.

Weed Management District--A weed management district is any area of land identified for the purpose of weed management or control. Such an identified land area may be, but is not limited to one of the following: a project or job site, a County, two or more

Counties, or a National Forest."

Figure 101-1—Illustration of road structure terms.

IDAHO PANHANDLE NATIONAL FOREST

R ig h t o f

W a y

R o a d si d e R o a d s id e

C le a ri n g W id th

R o a d w a y C le a ri n g L im it

X Y

G ro u n d

L in e

T ra v e le d

W a y

C L B e rm

S u rf a c e

C o u rs e B a s e

C o u rs e

F ill

S lo p e

B a c k S lo p e

D ra in a g e D itc h

G ro u n d L in e

S u b g ra d e

R o a d

B e d

S h a p e s a n d d im e n s io n s w ill v a ry t o f it lo c a l c o n d iti o n s

S e e d ra w in g s f o r ty p ic a l s e c tio n s

X a n d

Y d e n o te c le a ri n g o u ts id e o f ro a d w a y

N o te

Right - of - Way Line

Right - of - Way Line

Clearing Limit

Shoulder

Shoulder

102 - Bid, Award, and Execution of Contract

102.00_nat_05_17_2004

Deletions

Delete Section 102 in its entirety:

IDAHO PANHANDLE NATIONAL FOREST

103 - Scope of Work

103.00_nat_05_17_2004

This project is for the decommissioning of approximately 28.5 miles of Forest road, (BASE BID ITEM 1) with potential to add decommissioning of approximately 3.7 miles of Forest road, (OPTIONAL BID ITEM 2). All the roads are located on the Priest Lake

Ranger District, in Bonner County, Idaho and Pend Oreille County Washington.

The Contractor shall furnish all personnel, equipment, materials, tools, labor, and services necessary to complete the work.

The work consists of watershed restoration items on the central portion of the Priest Lake

Ranger District. These items include obliterating existing roads by recontouring or partial recontouring of the original roadbed, and restoration of stream channels by removing associated fills, removing culverts and construction of gradient control structures. The work may also include placing roads into long term storage by decompacting the surface and constructing water bars. Additional work consists of construction of sediment basins and seeding.

Delete the remaining subsections in this Section.

IDAHO PANHANDLE NATIONAL FOREST

104 - Control of Work

104.00_nat_us_02_17_2005

Delete sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005

Add the following subsection:

104.06 Use of Roads by Contractor

Any maintenance of existing roadways that may be necessary to provide equipment access for construction will be the responsibility of the Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

IDAHO PANHANDLE NATIONAL FOREST

106 - Acceptance of Work

106.01_nat_08_12_2004

106.01 Conformity with Contract Requirements.

Delete Subsection 106.01 and substitute the following:

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed.

Acceptable work conforming to the contract will be paid for at the contract unit bid price.

The method of determining conformity and accepting work is described in Subsection

106.02.

Correct all work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.

Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

(1) Have the work accepted at a reduced price; or

(2) Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.07_nat_05_11_2004

Delete subsections 106.03 through 106.07.

IDAHO PANHANDLE NATIONAL FOREST

107 - Legal Relations and Responsibility to the Public

107.05_nat_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.09_nat_05_11_2004

107.09 Legal Relationship of the Parties.

Delete the entire subsection:

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

• Exact time and location of spill including a description of the area involved.

• Containment procedures.

• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

IDAHO PANHANDLE NATIONAL FOREST

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

IDAHO PANHANDLE NATIONAL FOREST

108 - Prosecution and Progress

108.00_nat_05_11_2004

Delete Section 108 in its entirety.

IDAHO PANHANDLE NATIONAL FOREST

109 - Measurement and Payment

109.02_nat_05_11_2004

109.02 Measurement Terms and Definitions.

Add the following to this subsection:

One of the following methods of measurement for determining final payment is

DESIGNATED IN THE PAY SCHEDULE for each PAY ITEM:

Methods of Measurement:

(a) Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE

SCHEDULE OF ITEMS may be authorized under any of the following conditions:

(1) Changes in the work authorized by the CO.

(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.

(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.

(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to construction.

(c) Actual Quantities (AQ). These quantities are determined from measurements of completed work.

(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

IDAHO PANHANDLE NATIONAL FOREST

Add the following definition:

(p) Thousand Board Feet (MBF). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

109.00_nat_us_02_17_2005

109 Deletions

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

IDAHO PANHANDLE NATIONAL FOREST

151 - Mobilization

151.00_0117_01_15_2005

Add the following at the end of the last sentence:

“Work also includes cleaning of all equipment used at the project site. Clean all construction equipment prior to entry on the project site. Remove all dirt, plant parts and material that may carry noxious weed seeds into the area. Only construction equipment inspected by the Forest Service will be allowed to operate within the project area. Treat subsequent move-ins of equipment the same as the initial move-in. Clean truck beds and dump boxes hauling to the project site prior to entering the work area. Contractor shall give the Forest Service at least 24 hours advance notification when equipment is ready for inspection. Location for inspection shall be as agreed.”

155 - Schedules for Construction Contracts

155.00_nat_us_05_11_2004

Delete Section 155 in its entirety.

IDAHO PANHANDLE NATIONAL FOREST

156 - Public Traffic

156.00_0117_03_02_2009

Delete first paragraph and replace with the following:

Develop a construction sign plan identifying the type and location of all advanced warning signs necessary to safely restrict or pass public traffic. Install construction signs conforming to the Manual on Uniform Traffic Control Devices (MUTCD) prior to proceeding with any construction work. Furnish, maintain and remove all barricades and signs required for construction signing.

No payment will be made for this item. Include all costs associated with erecting, maintaining and removing traffic control construction signing and road maintenance in the unit price bid for Mobilization.

Delete the following from the last paragraph:

according to Subsection 106.07(b)

IDAHO PANHANDLE NATIONAL FOREST

157 - Soil Erosion Control

157.03_0117_03_02_2009

Construction Requirements

157.03 General

Delete the entire subsection and replace with the following:

Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted

30 days before intended use.

Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.

When erosion control measures are not functioning as intended, immediately take corrective action.

The erosion control plan reflects special concerns and measures necessary to protect resources. The Erosion Control Plan shall, at a minimum:

1. Describe the construction activities and sequence of implementation relating to specific erosion control measures.

2. Describe the location and type of permanent controls to be implemented during construction.

3. Describe the location and type of temporary controls to be implemented during construction.

4. For work in stream channels with flowing water, include a detailed dewatering plan.

5. Describe what monitoring will take place for the duration of the contract.

“Emergency Spill Kit. Keep sufficient quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum product spills. Use absorbent materials that are biodegradable, non-water absorbing and designed specifically for the types of spills associated with the Contractor’s operation.”

“Upon completion of construction at the site, all temporary dewatering materials and equipment are to be removed from Government property."

IDAHO PANHANDLE NATIONAL FOREST

203 - Removal of Structures and Obstructions

203.01_nat_05_12_2004

Description

Delete and replace with the following:

203.01 This work consists of disposing of clearing slash, salvaging, removing, and disposing of buildings, fences, structures, pavements, utilities, curbs, sidewalks, and other obstructions.

203.00_01_us_10_11_2006

203.03 Salvaging Material.

Delete this subsection and add the following:

Unless shown on the plans, remove all designated material from the project area and

National Forest land.

203.05 Disposing of Material.

(a) Remove from project.

All cattleguards, and gates to be removed shall become the property of the contractor and shall be removed from National Forest land. Dispose of all materials designated for removal off of National Forest System Lands in an environmentally safe and legal manner in accordance with all State and Federal requirements.

Payment

Delete and replace with the following:

203.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 203 pay items listed in the bid schedule. Payment is based upon the removal and disposal of all structures designated in the contract, and DOES include the

IDAHO PANHANDLE NATIONAL FOREST

excavation necessary to access these structures. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

IDAHO PANHANDLE NATIONAL FOREST

211 – Rehabilitation of Abandoned Roadways

211.01 Delete

Delete the standard specification “Section 211-ROADWAY OBLITERATION” and replace with the following:

211.00_ipnf_03_21_2005_usc

Description

211.01 Work. This work consists of decompaction, partial recontour, and/or full recontour to restore the roadway to a hydrologically stable condition. Decompaction is required on any specified road segment or surface area where embankment is to be placed. Leave no furrows that could concentrate or channelize water when decompacting the roadbed. The work also includes restoration of all designated stream crossings, which involves removing the existing drainage structures and associated fill and restoring the site back to its natural contour. This also includes the excavation of some stream channels without drainage structures, including springs, seeps and headwater swales. The work includes removing existing geotextiles, installation of gradient control devices in each channel, sediment basins, seeding, fertilizer and mulching of all excavated areas, and the construction of waterbars.

Definition of Stream Channel Restoration Categories:

Category I - Typical stream crossing in this category measures a fill length from the edge of the road’s shoulder to the downhill toe of fill of < 15 feet, may or may not require a drainage structure removal, and requires 3 gradient control structures to be installed unless otherwise approved by the CO. General difficulty level is low.

Category II - Typical stream crossing in this category measures a fill length from the edge of the road’s shoulder to the downhill toe of fill of > 15 feet < 25 feet, may or may not require a drainage structure removal, and requires 4 gradient control structures to be installed unless otherwise approved by the CO. General difficulty level is moderate.

Category III - Typical stream crossing in this category measures a fill length from the edge of the road’s shoulder to the downhill toe of fill of > 25 feet < 40 feet, may or may not require a drainage structure removal, and requires 5 gradient control structures to be installed unless otherwise approved by the CO. General difficulty level is high.

IDAHO PANHANDLE NATIONAL FOREST

Category IV - Typical stream crossing in this category measures a fill length from the edge of the road’s shoulder of the road to the downhill toe of fill of > 40 feet < 60 feet, may or may not require a drainage structure removal, and requires 6 gradient control structures to be installed unless otherwise approved by the CO. General difficulty level is high.

Category V - Typical stream crossing in this category measures a fill length from the edge of the road’s shoulder to the downhill toe of fill of > 60 feet, may or may not require a drainage structure removal, and requires 7 gradient control structures to be installed unless otherwise approved by the CO. General difficulty level is very high.

211.02 Performance. Work begins at either the road end or a location designated by the CO and progresses out towards the permanent road closure. Remove all designated drainage structures/appurtenances according to Section 203 or as directed by the CO.

Where decompaction is required, decompact a 200' test strip or a representative area designated by the CO. The test strip is to be determined by the CO if the method used adequately decompacts the upper layer of roadbed and can be used for each specified roadway within the same width, depth, soil and surface parameters.

Where roads are overgrown with brush and small regeneration, move and operate equipment over brush without grubbing, scarifying or otherwise destroying the established root system in the roadway except at designated work sites, and for safe passage(a service road) if needed for safety.

Do not incorporate existing roadway vegetation, windfalls, concentrations of woody debris, frozen soil, ice and/or snow into the excavated material. Scatter large woody debris as well as concentrations of slash on the newly recontoured areas.

211.03 Stream Channel Restoration. Before recontouring, decompact the inside half of the roadbed to a minimum depth as shown in the plans where material excavated from the stream channel is to be embanked. Remove all drainage structures in accordance with

Section 203. Recontour adjacent roadways to approximate adjacent side slopes. Unless otherwise approved by the CO, bury gradient control structures horizontally across the excavated floodplain at or just below the original stream channel level as shown in the plans. Use designated trees tagged by the CO for constructing gradient structures. These trees may require felling or bucking into the proper lengths. If an insufficient number of trees are tagged at any particular site, the CO can designate additional trees outside the riparian area to meet contract requirements. If the distance to find trees extends farther than 200’ of each side of the channel, the use of Section 622- Equipment Rental time may be used as directed by the CO.

211.04 Full Road Recontour. Decompact the roadbed to a depth as shown in the plans.

Start full recontour by removing the full roadway fill, placing the fill onto the decompacted roadbed, and contouring it to the adjacent natural side slopes as shown in the plans. Scatter large and small woody debris on the newly recontoured surface from available sources along the section of roadway being recontoured. Distances are staked and/or shown in the plans.

211.05 Partial Road Recontour. Decompact the roadbed to a depth as shown in the plans. Start partial road recontour by removing the outer third of the roadway fill, placing the fill onto the inner third of the roadway, and contouring it to the adjacent natural side slopes as shown in the plans. Scatter large and small woody debris on the newly recontoured surface from available sources along the section of roadway being recontoured. Distances are staked and/or shown in the plans.

211.06 Decompaction of Roadbed. Thoroughly decompact the full roadbed to a depth as shown in the plans. After decompaction, leave the road surface in a roughened condition with no furrows, which may concentrate or channelize water. Scatter large and small woody debris on the newly decompacted surface from available sources along the section of roadway being decompacted. Distances are staked and/or shown in the plans.

Obstruct the road by installing or constructing the designated barrier shown on the plans including any signs and posts.

211.07 Ditch Relief Culvert. Remove culverts other than those at stream crossings.

Dispose of culverts by burying at approved sites by the CO or removal from National

Forest System Lands. Maintain connection of the remaining trench to the inside ditch and outslope to provide drainage.

211.08 Waterbars. Construct as shown in the plans and spaced as staked by the CO.

211.09 Acceptance. Rehabilitation of abandon roadways will be evaluated under

Subsection 106.02.

Measurement

211.10 Measure the Section 211 items listed in the bid schedule according to Subsection

109.02 and the following.

Measure Sediment Basins under Section 157.

Do not measure gradient control structures incidental to Stream Channel Restorations.

Measure Seeding, Fertilizer and Mulch under Section 625.

IDAHO PANHANDLE NATIONAL FOREST

When measurement is by Lump Sum, include the following work in Decompaction of

Roadbed, Partial Road Recontour or Full Road Recontour and do not measure unless otherwise shown in the plans.

1) Stream Channel Restoration

2) Seeding and Fertilizing

3) Mulching

4) Sediment Basins

5) Gradient Control Structures

6) Removal of Culverts, Ditch Relief Culverts and Geotextiles

7) Water bars

Payment

211.11 Basis. The accepted quantities will be paid at the contract price per unit of measurement for the Section 211 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See subsection 109.05.

622 - Rental Equipment

622.02_0117_01_05_2005

622.02 Rental Equipment

Delete the first two sentences of the first paragraph and add the following:

Hydraulic Excavator Provide a track mounted hydraulic excavator in good working condition. Bucket must be equipped with a hydraulic "thumb". It is anticipated that an excavator of a size capable of performing the excavation needs for the project will be adequate for any work that the Contractor may be directed to perform under this contract.

Dump Truck Provide a dump truck in good working condition. It is anticipated that a dump truck of a size capable of performing the excavation needs for the project will be adequate for any work that the Contractor may be directed to perform under this contract.

Delete the third paragraph and replace with the following:

Obtain approval for the length of time and the type and amount of work required prior to starting each section of work using this pay item. Additional hours will not be paid without prior approval. Keep daily records of the number of unit-hours of operation.

625 - Turf Establishment

625.01_ipnf_us_11_20_2009

Description

625.01 Work.

All construction related disturbed areas as well as finished cut, fill slopes, decommissioned roads, construction staging areas and burn bays are to be treated. Seed, fertilizer and mulch may be applied in one application.

Construction 625.03_ipnf_us_11_20_2009

625.03 General.

"Time of application shall be as specified:

Keep application of seed, fertilizer and mulch current with progression of the work. Prior to October 1 of any calendar year, a maximum of 5000 lineal feet of treated road may remain unseeded. After October 1, a maximum of 1500 lineal feet of treated road may remain unseeded. Prior to winter shutdown, seed, fertilize and mulch all disturbed earth."

625.04_ipnf_us_11_20_2009

625.04 Preparing Seedbed.

Delete this subsection.

625.05_ipnf_us_11_20_2009

625.05 Watering

Delete this subsection.

625.06_ipnf_us_11_20_2009

IDAHO PANHANDLE NATIONAL FOREST

625.06 Fertilizing

Fertilizer shall be applied at the rate of 200 pounds per acre in one application(s) by the Dry method and have a chemical analysis as listed below:

Nutrient Percent Nutrient Percent

Nitrogen, N . . . 16 Potassium, K. . 16

Phosphorus, P205. 16 Sulphur, S. . .

625.07_ipnf_us_11_20_2009

625.07 Seeding

Delete this subsection and add the following.

The kinds of seed to be furnished and the amounts to be applied in terms of pure live seed (PLS) shall be as follows:

STANDARD DRY SITE MIX - appropriate for roadside application on low to middle elevation sites that tend to be droughty and well-drained.

SPECIES PLS LBS/AC

Slender wheatgrass "Pryor" or "Revenue" (Elymus trachycaulus ssp.

trachycaulus)

6.0

Hard fescue "Durar" (Festuca brevipila, synonym: Festuca ovina var.

duriuscula )

5.0

Streambank wheatgrass "Sodar" (Elymus lanceolatus ssp.

psammophilus)

3.0

Annual rye (Lolium multiflorum) 2.0

Canby bluegrass "Canbar" (Poa canbyi) 4.0

TOTAL 20.0

Acceptable substitutes:

Big bluegrass "Sherman" (Poa ampla) @ 4 PLS LBS/AC for Canby bluegrass

Grass seed mix: if a specified seed species is not available, contractor shall request a substitute in writing to be approved by the Contracting Officer.

Acceptable substitutes:

� Blue wildrye “Arlington or “Elkston” for slender wheatgrass

� Streambank wheatgrass “Sodar” for slender wheatgrass

IDAHO PANHANDLE NATIONAL FOREST

Pounds of seed to be furnished per acre shall be obtained by dividing the pounds of pure live seed (PLS) required per acre by the product of the percent purity and percent germination.

Example: 5(# PLS/acre) = 6.55 pounds commercial seed per acre.

0.90 x 0.85 (where purity=90% and germination=85%)

All seed purchased will be certified to be free of the noxious weed seeds from weeds listed on the current "All States Noxious Weeds List".

Test results from a certified seed analyst and seed analysis labels attached to the bags will be provided to the Forest Service. Lab testing for noxious weeds will be conducted prior to seed mixing. Only after a finding and documentation in writing of no weeds on the current "All States Noxious Weeds List" will the seed be accepted and used.

Seed shall be applied by the Dry method.

625.08_ipnf_us_11_20_2009

625.08 Mulching.

Add the following to this subsection:

Much shall be either a straw or hay mulch that is Idaho Certified weed free with the weed free certification attached. Uniformly apply mulch by the __Dry____ method at an application rate of 2,000 pounds per acre within 48 hours after completion of the seed and fertilizer applications.

713 - Roadside Improvement Material

713.05_nat_us_03_02_2005

713.05 Mulch.

Assure that mulch used on the project is certified noxious weed free by the appropriate authority in the jurisdiction of use.