- RECOVERY Palouse River Road Aggregate Resurfacing Federal contract opportunity
- Solicitation number
- AG-82B1-S-10-0103
About this file
Complete solicitation except Forest Service Supplemental Specifications and Drawings
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG-82B1-S-10-0103_abstract.pdf | ||
| AG-82B1-S-10-0103_fsss.pdf | ||
| AG-82B1-S-10-0103_drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTERMOUNTAIN EMERGENCY RECOVERY OPERATION CENTER INSTRUCTIONS
ISSUING OFFICE:
U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE
INTERMOUNTAIN EROC
740 SIMMS STREET
GOLDEN, CO 80401
FAX (303) 275-5299
SOLICITATION NO.: IFB AG-82B1-S-10-00103
OFFERS ARE SOLICITED FOR: RECOVERY PALOUSE RIVER ROAD AGGREGATE RESURFACE PROJECT
IMPORTANT – NOTICE TO OFFEROR:
OFFEROR SHALL SUBMIT THE FOLLOWING DOCUMENTS BACK WITH THEIR RESPONSE TO THIS SOLICITATION:
1. SF-1442 Solicitation, Offer, and Award (Complete, date, and sign)
2. Section B – Schedule of Items (Page 5). (Complete Unit Price and Amount)
3. Section K – Representations and Certifications (Pages 52-57). (Complete the Representations and
Certifications electronically via the Online Representations and Certifications Application (ORCA) website at http://orca.bpn.gov)
5. Bid Guarantee
6. Acknowledgement of Amendments
IT IS REQUIRED THAT YOU WRITE THE SOLICITATION NUMBER ON THE OUTSIDE OF YOUR ENVELOPE.
Return to: USDA, Forest Service Intermountain EROC 740 Simms Street Golden, CO 80401
IT IS REQUIRED THAT ALL CONTRACTOR’S BE REGISTERED IN THE CENTRAL CONTRACTOR REGISTRATION DATABASE PRIOR TO AWARD UNDER THIS SOLICITATION. SEE CLAUSE I-3 – FAR 52.204-7 CENTRAL
CONTRACTOR REGISTRATION FOR DETAILS ON HOW TO APPLY.
ALL SOLICITATIONS SHALL BE ISSUED THROUGH FEDBIZOPS. NO PAPER SOLICITATIONS SHALL BE ISSUED.
IT IS THE OFFERORS RESPONSIBILITY TO WATCH FOR ANY AND ALL AMENDMENTS TO THE SOLICITATION, WHICH SHALL BE ISSUED ELECTRONICALLY THROUGH FEDBIZOPS.
AG-82B1-S-10-0103 RECOVERY Palouse River Road Aggregate Resurface Project
TABLE OF CONTENTS
PART I – THE SCHEDULE
SECTION B – Supplies or Services and Prices/Costs SECTION C – Descriptions/Specifications/Statement of Work SECTION D – Packing and Marking SECTION E – Inspection and Acceptance SECTION F – Description and Performance SECTION G – Contract Administration Data SECTION H – Special Contract Requirements
PART II – CONTRACT CLAUSES
SECTION I – Contract Clauses
PART III – LIST OF DOCUMENTS,EXIBITS AND OTHER ATTACHMENTS
SECTION J – Exhibits, Attachments, and Appendices
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – Representations, Certifications and Other Statements of Offerors or Respondents SECTION L – Solicitation Provisions SECTION M – Evaluation Factors for Award
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
AG-82B1-S-10-0103
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
1/19/2010
PAGE OF PAGES
3 62
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
358426
6. PROJECT NO.
CIM-0105-01R
7. ISSUED BY CODE 8. ADDRESS OFFER TO
USDA, Forest Service Intermountain EROC 740 Simms Street Golden, CO 80401
USDA, Forest Service Intermountain EROC 740 Simms Street Golden, CO 80401
9. FOR INFORMATION
CALL:
A. NAME
Stephen M. Patton B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(907) 228-6240
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
TAS::12 1102::TAS RECOVERY Palouse River Road Aggregate Resurface Project, Clearwater National Forest
Price Range The estimated price range for the project is: between $250,000 and $500,000
This solicitation and any resulting contract will utilize funds provided by the American Recovery and Reinvestment Act (ARRA) of 2009. Inclusion of unique clauses and provisions required in implementing the Act, including those for significant reporting and transparency, will be required of the successful offeror(s).
11. The Contractor shall begin performance within 10 calendar days and complete it within 90 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. *(See Section F clause 52.211-10)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 3:00 p.m. MST (hour) local time 2/17/10 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required. (If “is required” see clause 52.228-1)
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
Duns No. ____________________________
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
Intermountain EROC 740 Simms Street Golden, CO 80401
USDA, National Finance Center P.O. Box 60000 New Orleans, LA 70160-0001
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract.
The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
PART 1 – THE SCHEDULE
SECTION B – SERVICES AND PRICES
PALOUSE RIVER ROAD AGGREGATE RESURFACE
CLEARWATER NATIONAL FOREST
PALOUSE RANGER DISTRICT
LATAH COUNTY, IDAHO
B.1 – SCHEDULE OF ITEMS
Item No. Item Description *MM Pay Unit Estimated Quantity Unit Price
Amount Bid
15101 Mobilization LSQ L.S. 1 $________
30322 Road Reconditioning, Compaction B CQ MILE 5.14 $_______ $________
32209
Aggregate Surface Course, Grading F, Compaction C AQ TON 23,700 $_______ $________
Total Bid Price (All Items) $________
*Designated Method of Measurement: AQ – Actual Quantities LSQ – Lump Sum Quantities CQ – Contract Quantities
NOTE: This solicitation contemplates a firm-fixed price type of contract, which under the definition in FAR 16.202-1, is a type of contract that ―provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.‖
B.1.1 Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.
B.1.2 Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
B.1.3 Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
SECTION C--DESCRIPTION/SPECIFICATIONS
C.1 - PROJECT DESCRIPTION AND LOCATION
a. Description of Work. Reconditioning and aggregate resurfacing of Palouse River Road 447 in accordance with the attached specifications and as shown on the drawings
c. Price Range. $250,000 - $500,000
d. Pre-Bid Tour. There will be no pre-bid tour. Prospective bidders desiring additional information about this project can contact Dave Brady at the Palouse Ranger District, Clearwater National Forest, Potlatch, Idaho.
Phone: (208) 875-1730.
e. Start Work and Period of Performance. See Clause F.2, FAR 52.212-3)
C.2 - GOVERNMENT FURNISHED PROPERTY
None
C.3 - STANDARD SPECIFICATIONS
"Standard Specifications for Construction of Roads & Bridges of Federal Highway Projects" (FP-03, U.S. Customary Units) are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract.
Copies of the "Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects", (FP-03, U.S.
Customary Unit), are available from the SUPERINTENDENT OF DOCUMENTS, U.S. GOVERNMENT PRINTING OFFICE, P.O. BOX 371954, PITTSBURGH, PA 15250-7954. The stock number to order is SN001-001-00660-2. Call (202) 512-1800 for the current price and to place telephone orders. You can FAX orders to (202) 512-2250. Credit card orders will be accepted.
Copies are also available electronically on the U.S. DEPARTMENT OF TRANSPORTATION Federal Highways Administration website at http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm.
C.4 - FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS
Forest Service Supplemental Specifications (FSSS) are included as a separate ATTACHMENT of this solicitation. The supplemental specifications applicable to this project are listed in SECTION J.
C.5 AGAR 452.211-72 STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
b. Project Location. Project is located 5.2 miles northeast of Harvard, Idaho. From the town of Harvard, proceed northeast on State Highway 6, a double lane asphalt surfaced road for 3.7 miles to the intersection with Palouse River Road 447. Turn right on to Palouse River Road 447 and proceed 1.5 miles to the beginning of project.
Harvard Quarry is located 0.8 miles south of Harvard, Idaho. From the town of Harvard, proceed 0.4 miles west on State Highway 6 to the intersection with State Highway 9 on the left. Proceed 0.5 miles on State Highway 9 to Harvard Quarry entry road on the left.
Harvard Quarry: 46° 54’ 43.43‖ N, 116° 44’ 23.20‖ W Beginning of project: 46° 56’ 37.08‖N, 116° 38’ 41.93‖ W End of project: 46° 57’ 57.37‖ N, 116° 34’ 01.29‖ W http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm
C.6 AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D – PACKAGING AND MARKING
D.1 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of Award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ and the Agriculture Acquisition Regulations may be accessed at www.usda.gov/da/procure/agar/subchaph.html#11.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996) http://www.arnet.gov/far/
SECTION F--DELIVERIES OR PERFORMANCE
F.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/
52.242-14 Suspension of Work (APR 1984)
F.2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises
The Forest Service anticipates issuing the Notice to Proceed on or about June 15, 2010.
SECTION G--CONTRACT ADMINISTRATION DATA
G- 1 - Contract Administration
(a) CONTRACTING OFFICER means a person with the authority to enter into, administer and/or terminate contracts and make related determinations and findings. The Contracting Officer signs all contractual documents, approves and signs all modifications to contracts, processes and approves payment requests, reviews and makes final decisions on contractual discrepancies, and administers the contract.
The Contracting Officer is the only authorized individual to make changes to a contract.
(b) CONTRACTING OFFICER'S REPRESENTATIVE. The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the pre-work conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the contract shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.
(c) CONTRACTOR'S REPRESENTATIVE. Any representative of the Contractor shall be designated in writing. The designation shall clearly indicate the name and limitations of authority, if any, of the representative.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 BARRICADES, WARNING SIGNS, AND OTHER DEVICES
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public.
Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail.
All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform to Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
As a minimum, it is anticipated that the following type and number of signs will be required:
Location
Designation
Quantity Palouse River Road, M.P. 1.5 HEAVY TRUCK TRAFFIC 1
Road 768, M.P. 0.05 TRUCK CROSSING 1 Road 292, M.P. 0.05 TRUCK CROSSING 1 Road 381, M.P. 0.05 TRUCK CROSSING 1 Road 767, M.P. 0.05 TRUCK CROSSING 1 Palouse River Road, M.P. 5.2 HEAVY TRUCK TRAFFIC 1
H.2 52.236-4 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are The result of site investigations by Forest Service specialists making physical determination based on surface observations.
(b) Weather Conditions. Normal snow conditions indicate a work season from approximately May 15 to October 15.
(c) Transportation Facilities. Access to the project from Harvard, Idaho is via State Highway 6 and State Highway 9, these are double lane roads with asphalt surfacing and Palouse River Road 447, the first 1.5 miles from the intersection with State Highway 6 has a bituminous surface treatment.
(d) Material Source. The material source for item 32209 – Aggregate Surface Course is a Potlatch Corporation owned quarry. The Forest Service has entered into a Rock Pit Lease Agreement with Potlatch Corporation. The Contractor shall abide by all terms and conditions set forth in this lease agreement. A copy of this lease agreement is available from the Forest Supervisor’s Office, Clearwater National Forest, 12730 Highway 12, Orofino, Idaho 83544.
H.3 Conformity With Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
H.4 ENVIRONMENTAL PROTECTION
Prevention of Oil Spills. The contractor is required to have a spill plan. When storage facilities for oil or oil products are on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or any other body of water. If a spill of petroleum product should occur in water, immediately notify the Contracting Officer and appropriate state agencies.
Service all equipment only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Meet all applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.
Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29 CFR 1910.120). Notify the Forest Service of all hazardous material that may be brought onto the National Forest.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. The contractor must clean up spills or leaks in a manner that complies with Federal, state, and local laws and regulations and to the satisfaction of the CO. When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
H.4 FIRE CONTROL (FS 236-1)
(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.
(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.
Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area. An equitable adjustment in contract time may be made for this period.
(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.
(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and
(4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.
(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating.
One - shovel, round point #0 lady or equal.
One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.
One - water container (at least 1-gallon capacity), not required with stationary equipment.
(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.
(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:
One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.
One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.
Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.
(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.
(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.
(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site when all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.
(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan.
Such fires must not be left burning unattended.
(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.
(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.
When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
(i) All high fire risk operations could be terminated at 1300 local time.
(ii) All burning could be stopped, including debris burning fires.
(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
(12) Pump and Trailer. NOT USED
(13) Burning. Before starting any open burning, the Contractor shall comply with the following:
(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.
(ii) Submit a burning permit from the District Ranger.
(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.
(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.
(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.
(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his discretion, prohibit all open burning for definite periods within specific areas of the National Forest.
H.5 LANDSCAPE PRESERVATION
(a) Do not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. Confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Retrieve material which falls outside of these limits and dispose of, or incorporate in the work as directed by the Contracting Officer.
Preserve the scenic and natural environment along this construction project.
(b) Do not allow objectionable material to enter any stream, river, lake, or other body of water. Retrieve material which falls in these areas and dispose of, or incorporate in the work as directed by the Contracting Officer, and repair damage to vegetation or structures outside the project limits as directed by the Contracting Officer.
(c) Do not operate equipment or otherwise disturb the natural vegetation and soil beyond the construction limits.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ and the Agriculture Acquisition Regulations may be accessed at www.usda.gov/procurement/policy/agar.html
52.202-1 Definitions (JUL 2004) ALT I (MAY 2001) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (APR 1984) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (JUL 1995) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(JAN 1997)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (SEP 2006) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.214-26 Audit and Records – Sealed Bidding (OCT 1997) 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (JUL 2005) 52.219-8 Utilization of Small Business Concerns (MAY 2004) 52.219-28 Post-Award Small Business Program Rerepresentation (APR 2009)
52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation (JUL 2005) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-8 Payrolls and Basic Records (FEB 1988) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other
Eligible Veterans (SEP 2006) 52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998) http://www.usda.gov/procurement/policy/agar.html
52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (SEP 2006)
52.222-50 Combating Trafficking in Persons (AUG 2007) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
(DEC 2007)
52.223-6 Drug-Free Workplace (MAY 2001) 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
(MAY 2008)
52.224-1 Privacy Act Notification (APR 1984) 52.224-2 Privacy Act (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-4 Patent Indemnity - Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance-Work on a Government Installation (JAN 1997) 52.228-11 Pledges of Assets (SEP 2009) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999) 52.228-15 Performance and Payment Bonds – Construction (NOV 2006) 52.229-3 Federal, State, and Local Taxes (APR 2003) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-9 Limitation on Withholding of Payments (APR 1984) 52.232-17 Interest (OCT 2008) 52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003) 52.233-1 Disputes (JUL 2002) ALT I (DEC 1991) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by The Contractor (APR 1984) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) ALT I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (AUB 2009) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering - Construction (SEP 2006)
52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004) ALT I (SEP 1996)
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.252-6 Authorized Deviations in Clauses (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.224-70 Confidentiality of Information (FEB 1988) 452.236-73 Archeological or Historic Sites (FEB 1988) 452-236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
I.2 - FAR 52.203-15 Whistleblower Protections Under The American Recovery And Reinvestment Act of 2009 (Mar 2009)
(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5).
(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.
I.3 - FAR 52.204-7 Central Contractor Registration (APR 2008)
(a) Definitions. As used in this clause—
―Central Contractor Registration (CCR) database‖ means the primary Government repository for Contractor information required for the conduct of business with the Government.
―Data Universal Numbering System (DUNS) number‖ means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
―Data Universal Numbering System +4 (DUNS+4) number‖ means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
―Registered in the CCR database‖ means that—
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and
(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record
―Active‖. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.
http://www.arnet.gov/far/current/html/Subpart%2032_11.html#wp1043964
(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ―DUNS‖ or ―DUNS +4‖ followed by the DUNS or DUNS +4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number—
(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.
The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company Physical Street Address, City, State, and ZIP Code.
(iv) Company Mailing Address, City, State and ZIP Code (if separate from physical).
(v) Company Telephone Number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
http://fedgov.dnb.com/webform
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering.
Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(g) (1)
(i) If a Contractor has legally changed its business name, ―doing business as‖ name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to (A) change the name in the CCR database;
(B) comply with the requirements of Subpart 42.12 of the FAR; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the ―Suspension of Payment‖ paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database.
Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the ―Suspension of payment‖ paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.
I.4 - FAR 52.204-11 American Recovery and Reinvestment Act—Reporting Requirements (MAR 2009)
(a) Definitions. As used in this clause—
―Contract‖, as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering http://www.arnet.gov/far/current/html/Subpart%2042_12.html#wp1084217 http://www.arnet.gov/far/current/html/Subpart%2042_12.html#wp1084217 http://www.arnet.gov/far/current/html/Subpart%2032_8.html#wp1029202 http://www.ccr.gov/ http://www.arnet.gov/far/current/html/Subpart%202_1.html#wp1145508 agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.
―First-tier subcontract‖ means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.
―Jobs created‖ means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as ―full-time equivalent‖
(FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
―Jobs retained‖ means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as ―full-time equivalent‖ (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
―Total compensation‖ means the cash and noncash dollar value earned by the executive during the contractor’s past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):
(1) Salary and bonus.
(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting Standards No. 123 (Revised 2004) (FAS 123R), Shared Based Payments.
(3) Earnings for services under non-equity incentive plans. Does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.
(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.
(5) Above-market earnings on deferred compensation which is not tax-qualified.
(6) Other compensation. For example, severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property if the value for the executive exceeds $10,000.
(b) This contract requires the contractor to provide products and/or services that are funded under the American Recovery and Reinvestment Act of 2009 (Recovery Act). Section 1512(c) of the Recovery Act requires each contractor to report on its use of Recovery Act funds under this contract. These reports will be made available to the public.
http://uscode.house.gov/lawrevisioncounsel.shtml http://www.arnet.gov/far/current/html/FARTOCP16.html#wp226194
(c) Reports from contractors for all work funded, in whole or in part, by the Recovery Act, and for which an invoice is submitted prior to June 30, 2009, are due no later than July 10, 2009. Thereafter, reports shall be submitted no later than the 10th day after the end of each calendar quarter.
(d) The Contractor shall report the following information, using the online reporting tool available at www.FederalReporting.gov.
(1) The Government contract and order number, as applicable.
(2) The amount of Recovery Act funds invoiced by the contractor for the reporting period. A cumulative amount from all the reports submitted for this action will be maintained by the government’s on-line reporting tool.
(3) A list of all significant services performed or supplies delivered, including construction, for which the contractor invoiced in this calendar quarter.
(4) Program or project title, if any.
(5) A description of the overall purpose and expected outcomes or results of the contract, including significant deliverables and, if appropriate, associated units of measure.
(6) An assessment of the contractor’s progress towards the completion of the overall purpose and expected outcomes or results of the contract (i.e., not started, less than 50 percent completed, completed 50 percent or more, or fully completed). This covers the contract (or portion thereof) funded by the Recovery Act.
(7) A narrative description of the employment impact of work funded by the Recovery Act. This narrative should be cumulative for each calendar quarter and only address the impact on the contractor’s workforce. At a minimum, the contractor shall provide—
(i) A brief description of the types of jobs created and jobs retained in the United States and outlying areas (see definition in FAR 2.101). This description may rely on job titles, broader labor categories, or the contractor’s existing practice for describing jobs as long as the terms used are widely understood and describe the general nature of the work; and
(ii) An estimate of the number of jobs created and jobs retained by the prime contractor, in the United States and outlying areas. A job cannot be reported as both created and retained.