AMENDMENT TO CORRECT WAGE DETERMINATION AND EXTEDN RESPONSE DUE DATE

View the file

Other files for this federal contract opportunity

Other files attached to CAVE CREEK RD GATE INSTALLATION, newest first.
File Type Posted
AMEND_0001.pdf PDF
SOLICITATION_S-14-0016.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

AG-8180-S-14-0016

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PHOENIX AZ 85006

2324 E MCDOWELL ROAD

TONTO NATIONAL FOREST

07/10/2014000002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/24/2014

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

AMENDMENT OF SOLICITATION AG-8180-S-14-0016 FOR THE PURPOSE OF:

1. WAGE DETERMINATION CORRECTION.

2. EXTENDING RESPONSE DUE DATE FOR PROPOSALS TO TUESDAY, JULY 22, 2014 AT 1:00PM MT.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

KELLY HULL

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

General Decision Number: AZ140018 06/27/2014 AZ18

Superseded General Decision Number: AZ20130018

State: Arizona

Construction Type: Heavy HEAVY CONSTRUCTION, Includes Water and Sewer Lines, Heavy Construction on Treatment Plant Sites and Pipeline Construction

County: Maricopa County in Arizona.

HEAVY CONSTRUCTION PROJECTS (DOES NOT INCLUDE DAM CONSTRUCTION)

Modification Number Publication Date 0 01/03/2014 1 01/17/2014 2 02/14/2014 3 04/18/2014 4 04/25/2014 5 06/20/2014 6 06/27/2014

BOIL0627-004 01/01/2013

Rates Fringes

BOILERMAKER......................$ 32.51 26.16

BRAZ0003-010 07/01/2013

Rates Fringes

BRICKLAYER.......................$ 22.35 9.12

ELEC0640-006 09/01/2012

Rates Fringes

ELECTRICIAN......................$ 25.64 3%+7.71

ELEC0769-002 05/01/2013

Rates Fringes

Line Construction:

Lineman.....................$ 40.42 20%+5.04

ENGI0428-008 06/01/2014

Rates Fringes

POWER EQUIPMENT OPERATOR

Group 1.....................$ 22.09 9.59 Group 2.....................$ 25.36 9.59 Group 3.....................$ 26.44 9.59 Group 4.....................$ 27.47 9.59

AG-8180-S-14-0016- AMENDMENT 0001 CCRD REC GATES INSTALLATION 2 of 7

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Small Self-Propelled Compactor (with blade), Bobcat/Skidsteer/Skid Loader, Oiler

GROUP 2: Self-Propelled Compactor (with blade), Grader/Blade (rough), Scraper, Tractor, Crane (less than 15 tons)

GROUP 3: Grade/Blade (Finish),Crawler-Type Tractor, Crane (over 15 tons & less than 100 ton), Tower Crane

GROUP 4: Crane (100 ton)

* ENGI0428-015 02/01/2013

Rates Fringes

POWER EQUIPMENT OPERATOR:

(PIPELINE)

Group 1.....................$ 37.95 14.51 Group 3.....................$ 19.77 14.51

Group 1: Backhoe, Boring Machine, Boom Operator, Bulldozer, Trackhoe

Group 3: Oiler

IRON0075-009 01/01/2014

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 26.52 21.02

Zone 1: 0 to 50 miles from City Hall in Phoenix or Tucson Zone 2: 050 to 100 miles - Add $4.00 Zone 3: 100 to 150 miles - Add $5.00 Zone 4: 150 miles & over - Add $6.50

PAIN0086-002 04/01/2013

Rates Fringes

PAINTER (Brush Only).............$ 19.35 4.75

PLUM0469-004 07/01/2013

Rates Fringes

PLUMBER..........................$ 39.55 17.05

SUAZ2012-006 05/17/2012

Rates Fringes

CARPENTER (Form Work Only).......$ 20.80 4.07

CARPENTER, Excludes Form Work....$ 21.98 5.38

AG-8180-S-14-0016- AMENDMENT 0001 CCRD REC GATES INSTALLATION 3 of 7

CEMENT MASON/CONCRETE FINISHER...$ 18.76 2.12

INSTALLER - SIGN.................$ 25.42 0.00

IRONWORKER, REINFORCING..........$ 20.66 13.59

LABORER: Asphalt Raker/Shoveler/Spreader..........$ 15.76 4.42

LABORER: Common or General......$ 14.36 3.97

LABORER: Concrete Saw (Hand Held/Walk Behind)................$ 17.00 4.55

LABORER: Fence Erection.........$ 10.32 2.24

LABORER: Grade Checker..........$ 18.14 4.55

LABORER: Landscape & Irrigation.......................$ 11.01 0.37

LABORER: Mason Tender - Brick...$ 14.55 4.20

LABORER: Mason Tender - Cement/Concrete..................$ 15.34 4.20

LABORER: Pipelayer..............$ 14.94 3.51

LABORER: Power Tool Operator....$ 16.57 4.20

LABORER: Railroad Construction Laborer.............$ 16.80 4.20

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 19.37 3.59

OPERATOR: Bulldozer.............$ 20.57 6.16

OPERATOR: Drill.................$ 20.57 4.78

OPERATOR: Forklift..............$ 20.38 4.75

OPERATOR: Grade Checker.........$ 21.68 6.31

OPERATOR: Loader (Front End)....$ 20.31 3.84

OPERATOR: Mechanic..............$ 22.23 5.78

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 17.07 3.20

OPERATOR: Roller................$ 21.34 8.36

OPERATOR: Rotomill..............$ 21.88 6.39

OPERATOR: Screed................$ 16.82 2.52

OPERATOR: Trencher..............$ 14.21 0.94

AG-8180-S-14-0016- AMENDMENT 0001 CCRD REC GATES INSTALLATION 4 of 7

OPERATOR: Broom/Sweeper..........$ 15.40 2.45

PAINTER: Pavement Marking/Parking Lot Striping.....$ 19.94 4.10

PAINTER: Roller and Spray.......$ 20.65 4.45

PIPEFITTER.......................$ 23.97 6.78

TRUCK DRIVER: 3 Axle Truck......$ 27.53 1.16

TRUCK DRIVER: Dump Truck........$ 14.37 1.16

TRUCK DRIVER: Flatbed Truck.....$ 12.50 1.48

TRUCK DRIVER: Hydroseeder.......$ 17.32 0.00

TRUCK DRIVER: Water Truck.......$ 16.46 3.42

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any

AG-8180-S-14-0016- AMENDMENT 0001 CCRD REC GATES INSTALLATION 5 of 7 changes in the collective bargaining agreements governing the rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

AG-8180-S-14-0016- AMENDMENT 0001 CCRD REC GATES INSTALLATION 6 of 7

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.