Boxelder AOP Culvert Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Boxelder_AOP_Culverts_Black_Hills_NF, newest first.
File Type Posted
AG67T0S170018_PreProposalMtgNotes.docx DOCX document
AG67T0S170018_Boxelder_Specifications-v1.pdf PDF
AG67T0S170018_Boxelder_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-67T0-S-17-0018

2. TYPE OF SOLICITATION

|_| SEALED BID (IFB)

|X| NEGOTIATED (RFP)

3. DATE ISSUED

5/9/2017

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

843940

6. PROJECT NO.

7. ISSUED BYCODE
67T0
8. ADDRESS OFFER TO

USDA FOREST SERVICE

R2, AQM NT-RMAST

1019 N FIFTH ST

CUSTER SD 57730-8214

(605) 673-9200

ATTN: BRENDA ANDERSON

9. FOR INFORMATION
CALL:
A. NAME

Brenda Anderson B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(605) 673-9323

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

The project consists of replacement of two existing metal culverts with concrete box culverts. The work will be on the Black Hills National Forest. Site is located approximately 1.0 miles from Nemo SD. The contractor shall provide any and all labor, equipment, supplies, services, permits, licensing, supervision, workman’s compensation, unemployment insurance, and transportation to accomplish all work necessary for project.

Price Range: The Government's estimate is: below $400,000.

To be eligible for award under this contract, you must be actively registered in the System for Award Management (SAM.gov) – this is a free service – you do not need to pay to register in this system. If your registration is not active, you will not be considered for award.

11. The Contractor shall begin performance within 10 calendar days and complete it within 90 calendar days after receiving |_| award, |X| notice to proceed. This performance period is |X| mandatory, |_| negotiable.

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

|X| YES|_| NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A.Sealed offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by 1600 (hour) local time June 9, 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B.An offer guarantee|X| is,|_| is not required.
C.All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D.Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.
DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
|_| 10 U.S.C. 2304(c)( )|_| 41 U.S.C. 253(c)( )
26. ADMINISTERED BYCODE
27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

|_|28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
|_|29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

AG-67T0-S-17-0018

Boxelder AOP Culvert Replacement Black Hills National Forests

AG-67T0-S-17-0018

Boxelder AOP Culvert Replacement Black Hills National Forests

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS

Proposals shall be valid for 30 days after the date of receipt for the solicitation. If additional time is needed, an extension will be requested. Refer to Section L for instructions on preparing your proposal and pricing.

B.2 Notes:

1. Unit prices prevail.

2. All Contractors must be registered in the System for Award Management (https:://SAM.gov) to be eligible for award under this soliciation. This is a free service. If not Contractor is not actively registered by time of proposal evaluation, you will be found non-responsive. You will be removed from consideration.

3. Payment for bond premiums shall not be in addition to the contract price. Include bond premiums under 151.01 Mobilization. Reference FAR 52.232-5 Payments under Fixed-Price Construction Contracts.

4. Unit Definitions:

· AQ – Actual Quantity

· CY – Cubic Yard

· CQ – Contract Quantity

· DQ – Design Quantity

· EA- Each

· FT – Foot

· LF – Linear Foot

· LSQ, LS – Lump Sum Quantity

· SY – Square Yard

· TN – Net Ton (2000 LB) Non Discrimination Statement The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual’s income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means of communication of program information (Braille, large print, audiotape, ect.) should contact USDA’s TARGET Center at (202) 720-2600 (voice and TDD). To file a complaint, write to USDA, Director, Office of Civil Rights, 1400 Independence Avenue, S.W., Washington, D.C 20250-9410, or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer.

B.3 Schedule of Items Boxelder AOP Culvert Replacement

Item No
Description
Method of Measurement
Unit
Quantity
Unit Price
Total
151(01)
Mobilization
L.S.Q.
L.S.
1
152(05)
Culvert and wall survey and staking
L.S.Q.
L.S.
1
157(02)
Water Control and Diversion and Erosion and Pollution Control
L.S.Q.
L.S.
1
203(01)
Removal of Structures
L.S.Q.
L.S.
1
209(02)
Structural Excavation
C.Q.
C.Y.
1500
209(50)
Structural Backfill, Pipe bedding
C.Q.
C.Y.
20
251(01)
Rip Rap Class 4, Government furnished includes sorting, loading, hauling and placing
C.Q.
C.Y.
554
322(11)G
Aggregate surface course, Grading G, compaction method A
C.Q.
C.Y.
200
322(11)Q
Aggregate surface course, Grading Q, compaction method C
C.Q.
C.Y.
135
552(04)
Structural Concrete, Class C(AE) for wall
C.Q.
C.Y.
19
602(05)
14' span, 8' rise precast reinforced concrete box culvert
C.Q.
L.F.
90
602(78)
End section for 14' span, 8' rise precast reinforced concrete box culvert. 12' end section only
C.Q.
Each
4
633(06)
Object markers, furnish and install
C.Q.
L.S.
8

Total Items

SECTION C – DESCRIPTION/ SPECIFICATIONS/STATEMENTOF WORK

C.1 Scope of Contract This project is to replace two existing metal culverts with precast concrete box culverts. Associated work includes: removal and disposal of existing metal pipes, constructing a temporary diversion of Boxelder Creek, furnishing and installing riprap along the stream channel, and constructing a stream channel bed in the new box culverts using large rock and streambed material salvaged on site.

C.2 Project Location Project is located approximately 15 miles northwest of Rapid City SD near Nemo SD on the Black Hills National Forest. From the town of Nemo take NFSR 140.1 for 1.0 miles to the site. Work is in Meade County South Dakota.

C.3 Contract Definitions.

C.3.1 Biobased Products: A product determined by the Secretary of Agriculture(USDA) to be a commercial or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products or renewable domestic agricultural materials (including plant, animal, and marine materials) or forestry materials. Information on biobased/biopreferred products can be found at http://www.usda.gov/biopreferred. In addition to the biobased products designated by the U.S. Department of Agriculture in the BioPreferred Program, the Contractor is encouraged to use other biobased products. The Contractor shall comply with the provision at FAR 52.223-1, Biobased Product Certification. The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

C.3.2 Contract time. See Period of Performance.

C.3.3 Contracting Officer (CO). Individual with authority to bind the government with their signature on the contract.

C.3.4 Contracting Officer Representative (COR).Individual(s) designated to act on the behalf of the CO within the delegation given them in writing.

C.3.5 Period of performance (also Performance period or Contract time). All calendar days allowed for completion of contract work. Includes all days of the week including weekends and holidays.

C.3.6 Quality Assurance. Those actions taken by the government to check goods or services to determine that they meet the requirements of the specifications.

C.3.7 Quality Control. Those actions taken by a contractor to control the production of goods or services so that they will meet the requirements of the specifications. Refer to FAR Clause 52.246-12 Inspection of Construction.

C.3.8 Standard. An acknowledged measure of comparison.

C.3.1 Technical Definitions. See Specifications and Drawings.

C-4 Government-Furnished Property

Description of Property
Value
Quantity
Return/Consumable
Rip Rap
$2,770.00
554 CY
Consumable

C.5 Contractor Furnished Property and Services Furnish all necessary labor, supervision, transportation, equipment, materials not specifically identified to be Government furnished, and incidentals nessary to provide work in accordance with the specifications, supplemental specifications, wage rates, terms and conditions.

C.6 Sustainable Products The Contractor shall comply with Section 9002 of the Farm Security and Rural Investment Act of 2002 (FSRIA), Executive Order (EO) 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” and the Federal Acquisition Regulation to provide biobased products.

The Contractor shall utilize products and material made from biobased materials (e.g. biobased greases, biobased hydraulic fluids, biobased absorbents) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer.

C.6.1 In the performance of this contract, the Contractor shall make maximum use of biobased oils and lubricants that are designated by the United States Department of Agriculture unless the product cannot be acquired:

· Competitively within a time frame providing for compliance with the contract performance schedule;

· Meeting contract performance requirements; or

· At a reasonable price.

· Information about this requirement and these products is available at http://sftool.gov/green-products/1/construction-materials C.6.2 The Federal Acquisition Regulation (FAR) requires Contractors to report the purchase of biobased products under service and construction contracts during the previous Government fiscal year (October 1 thru September 30) and to submit this report no later than:

1. October 31 of each year during contract performance; and

2. At the end of contract performance.

3. Information about this requirement is available at http://www.biopreferred.gov/FARReporting/FARReporting.xhtml C.6.3 Sustainable products identified for this solicitation:

The following is an example list of products that may be used in this contract for operations and maintenance for which biobased products are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

C.6.3.1 Diesel Fuel Additives

(1) Any substance, other than one composed solely of carbon and/or hydrogen, that is intentionally added to diesel fuel (including any added to a motor vehicle's fuel system) and that is not intentionally removed prior to sale or use.

(2) Neat biodiesel, also referred to as B100, when used as an additive. Diesel fuel additive does not mean neat biodiesel when used as a fuel or blended biodiesel fuel (e.g., B20). 90% - Minimum Biobased Content.

C.6.3.2 Hydraulic Fluids - Mobile Equipment Hydraulic fluids formulated for general use in nonstationary equipment, such as tractors, end loaders, or backhoes. 44% - Minimum Biobased Content.

C.6.3.3 Fuel Conditioners Products formulated to improve the performance and efficiency of engines by providing benefits such as removing accumulated deposits, increasing lubricity, removing moisture, increasing the cetane number, and/or preventing microbial growths within the fuel system. 64% - Minimum Biobased Content.

C.6.3.4 Erosion Control Woven or non-woven fiber materials manufactured for use on construction, demolition, or other sites to prevent wind or water erosion of loose earth surfaces, which may be combined with seed and/or fertilizer to promote growth. 77% - Minimum Biobased Content.

C.6.4 EPA Designated Products:

Plastic trash bags, printer ribbons, toner cartridges, print & writing papers, Traffic Barricades, Traffic Cones, Engine Coolants, Rebuilt Vehicular Parts, Re-refined lubricating oils, retread tires, manual grade strapping, signage, sorbents.

C-7 Specifications

1)All work related to this project shall be done in accordance with all applicable OSHA and State of South Dakota regulations.
2)Construction of the Boxelder Creek Culvert Replacement Replacement shall conform to the specifications in the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, U.S. Customary Units” publication FP-03, 2003 Edition. This publication may be obtained from: https://flh.fhwa.dot.gov/resources/specs/fp-03/
3)The following Specifications can be found in the Appendices. The Table of contents is provided for continuity of the contract documents.

SECTION D -- PACKAGING AND MARKING

{No clauses in this section.}

SECTION E -- INSPECTION AND ACCEPTANCE

E-1. FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://acquisition.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number
Title
Date
52.246-12
Inspection of Construction
AUG 1996

SECTION F - DELIVERIES OR PERFORMANCE

F.1 . Suspensions for Other Than Government’s Convenience The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to become muddy or unsuitable; or (2) Failure of the Contractor to comply with Specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by his/her operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for equitable adjustment.

F-2. FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://acquisition.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number
Title
Date
52.242-14
Suspension of Work
APR 1984

F.3 FAR 52.211-10 COMMENCEMENT PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days. The time stated for completion shall include final cleanup of the premises.

F.4 SCHEDULES FOR CONTRACTS

If Contractor's progress falls behind progress work schedule, the Contractor shall take such action as necessary to improve his progress; in addition, the Contracting Officer may require Contractor to submit a revised schedule and proposed plan of work to ensure completion of the work within the time(s) set forth in the contract.

Contractor shall schedule work to allow enough time for final inspections and any possible reworks to be completed by the contract end date.

SECTION G -- CONTRACT ADMINISTRATION DATA

G.1 PAYMENT

Payment will be made for identified line items meeting contract specifications. Progress payment(s) may be authorized by the Contracting Officer.

G.1.1 Construction work under this contract incorporates the Construction Rates. Weekly payrolls are mandatory and original signatures on certified payrolls must be turned into the Contracting Officer Representative for review and approval. Construction invoices will not be processed until acceptable payrolls have been received.

G.1.2 Invoice Submittals A signed payment certification must be uploaded with a breakdown of your invoice for payment to be authorized. See Attachment 1 in Section J.

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed. All invoices are to be submitted via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Please make sure that your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account.

If you have questions, contact your Contracting Officer.

G.1.3 Final payment Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.

A Contract release shall be submitted with the final invoice.

G.2 UNACCEPTABLE WORK.

G.2.1 When the Contractor provides unacceptable work, the Government may:

(i) Accept the work at a reduced price.

(ii) Require the area to be reworked at no additional expense to the Government, or

(iii) Reject the work in its entirety. If the work quality is unacceptable, the Contractor’s right to proceed is subject to termination for default clause.

G.2.2 The Government will permit the Contractor to rework an area only if the existing deficiencies can be corrected.

G.2.3 Any Government quality assurance assessment needed due to the Contractor reworking an area, either at the Contractor's request or because of unacceptable work, will be at the Contractor's expense. The Contractor may be assessed actual damages that are incurred while administering the contract during the rework.

G.2.5. The Government shall document unacceptable work quality in the performance assessment.

G.3 DAMAGES

The charge Government-furnished property that is not returned, or returned in a non-usable condition, is as listed in Section C.4.

The table below lists charge rates for Government re-inspection of work.

Activity
Charge rate
Government wages (per employee performing re-inspection)
$50.00/hour
*Government mileage
$0.535/mile

*Mileage reimbursement rate in effect January 1, 2017 is $.535 per mile. Mileage rates change periodically and the most current mileage rates for assessed damages at the time will be used. Most current mileage rates can be found at the General Services Administration website http://www.gsa.gov/portal/category/104715.

G.4 DESIGNATION OF GOVERNMENT REPRESENTATIVE

G.4.1 The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly.

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

G.5 CONTRACTOR’S REPRESENTATIVES

At all times during performance of this contract and until work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite competent representatives who are satisfactory to the CO and has authority to act for the Contractor.

All work will be performed in an organized and systematic manner.

The Government may, at its option, suspend work with full count of contract time continuing, if the Contractor fails to provide a contract representatives (1) conversant in the English language and (2) able to read and understand the contract.

G-6 NOTIFICATION OF SUBCONTRACTING

The Contractor shall promptly notify the Contracting Officer upon entering into any subcontract arrangement. The subcontractor shall have the experience and be equipped for such work. Subcontractor documentation will be submitted on a completed SF-1142 for construction.

Subcontracting any portion of the contract shall not relieve the Prime Contractor of any responsibility under this contract. Any subcontract agreement shall contain all terms and conditions required on the SF-1142.

G-7 NOTICE TO PROCEED

A Notice to Proceed will be issued in writing by the Contracting Officer. No work shall begin until receipt of this notice. Supplies should not be purchased prior to the Notice to Proceed or the Contractor will not be reimbursed in the case of a Termination of the contract. Contract time shall commence on the day indicated on the Notice to Proceed.

SECTION H – SPECIAL CONTRACT REQUIRMENTS

H.1 EMERGENCY CONTROL - FIRE PLAN

The Great Plains Dispatch Center includes public and private land in the Black Hills in South Dakota, in east/northeastern Wyoming and western Nebraska.

Local, State and Federal agencies have combined fire restriction information on one website at: www.blackhillsfirerestrictions.com. Great Plains Dispatch Center 1(800) 275-4955, Public Fire (605) 923-8868.

Great Plains Fire Information/PIO Contact Information:

· Phone Number - (605) 923-8868

· Email - greatplainsfireinfo@gmail.com

· Blog - http://gpfireinfo.blogspot.com/

· Twitter - @GPFireInfo It is important to note that people who wish to receive fire information within the Great Plains initial attack zone, should subscribe to the blog, follow the Twitter account or subscribe to the Atom Feed (available on blog) as news releases are no longer sent out via the Google e-mail account.

If a post has been made on the blog, one automatic e-mail a day will be sent to those who subscribe with all of the daily fire updates. The blog link may also be checked anytime of the day to see any updates that have been made on initial attack fires.

To subscribe to the blog:

1. Click on http://gpfireinfo.blogspot.com/

1. In the “Follow by E-mail” box on the right side of the webpage, enter your e-mail address that you wish to receive updates at.

1. Hit “Submit”

1. A pop-up box will appear asking you to enter a word in a box to verify that your e-mail is not spam.

1. Enter the word that is shown and then click “Complete Subscription Request”

1. Done For questions, please call the PIO phone number at (605) 923-8868 or e-mail greatplainsfireinfo@gmail.com.

(a) Tools and equipment.

The Contractor shall furnish and maintain in a serviceable condition one shovel, size O or larger, for each employee working in the project area. The shovels may be stored in the employees private vehicle or the contractor's vehicles, but must be readily available to each employee while in the project area.

For each yarder, loader, jammer, chipper, crawler tractor, skidder, hauling truck, portable welder, or comparable type equipment, the Contractor shall furnish one shovel, size O or larger, attached to each unit and one two and one-half pound or larger dry chemical or four pound or larger carbon dioxide type fire extinguisher attached to each unit.

For each power saw, soil auger, portable pump, or like powered equipment, the Contractor shall furnish one shovel, size 0 or larger, and one dry chemical fire extinguisher, 8 ounce or larger, immediately available to the operator of the equipment. The fire extinguisher shall be with the operator of the equipment; the shovel may be with the fuel can used to refuel the equipment.

Refueling of the equipment shall be done in an area cleared and void of flammable materials. Power saws shall be moved from the spot of refueling before starting.

(b) Fire Prevention.

The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site. The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.

Blasting - Advance approval in writing is required from the District Ranger. The use of fuses shall not be permitted, except near power lines where the danger of accidental detonation is present. Use of prima cord will not be allowed in clearing operations where flammable materials are present. A watchman will remain on site for at least one hour after detonation in areas of blasting where flammable fuels are present. Explosives will be stored at all times in a locked box marked "Explosives." All Federal, State, and local laws concerning the use and storage of explosives shall be followed.

Fire Orders/moratoriums – Any fire order issued during the contract will become a requirement of the contract.

Gas and Oil Use and Storage - Gasoline will be stored and transported only in metal containers with tight caps or seals. Gas and oil drum storage areas will be cleared of all flammable material for a distance of 50 feet around the drums. Storage areas will be posted with "No Smoking" signs. Oil filters, oil cans, oily rags, etc., will be removed from the project area and discarded in proper waste disposal receptacles or sites.

Open Fires - In accordance with State and local regulations.

Pursuant to 16 USC 551 and 36 CFR 261.50 (a) and (b) the following is prohibited on each National Forest or National Grasslands in the Rocky Mountain Region:

Operating or using any internal or external combustion engine on any timber, brush or grass covered land, including trails traversing such land, without a spark arrester, maintained in effective working order, meeting either (i) Department of Agriculture, Forest Service Standard 5100-1a; or (ii) the 80 percent efficiency level determined according to the appropriate Society of Automotive Engineers (SAE) recommended Practices J335 and J350.

Violation of this regulation and the general prohibitions of 16 USC 551 and 18 USC 3559 and 3571 (b) (6) is punishable as a Class B misdemeanor, by a fine of not more than $5,000.00 for an individual or $10,000.00 for an organication or imprisonment for not more than 6 months, or both.

Smoking - Smoking is prohibited while operating tractors or open-type vehicles, or while walking or working in an area with flammable fuels.

Welding - All flammable materials will be cleared for a minimum distance of 10 feet around any welding operation. Fire extinguishers and fire tools are required as shown in Section B-1(b).

H.2 Safety Plan

1. The Contractor shall provide a copy of their safety plan at the pre-work meeting. This copy of the Safety plan shall be kept in the contract folder for OSHA’s review.

2. The Safety Plan should be available to all employees and subcontractors working on the contract.

3. The Safety Plan should cover at a minimum:

a. Safety briefings covering the work area, equipment being used, and any special considerations for the work under the contract.

b. Personal Protective Equipment required for the work under the contract.

c. Identify appropriate OSHA requirements for the type of work under the contract.

d. Weather considerations for the time of year of the contract.

e. Communication issues and locations of the nearest medical facilities.

f. Name and point of contact information of supervisor responsible for enforcing Safety Plan.

g. Name, position title and point of contact information of company executive responsible for approving the Safety Plan.

h. Specific contingency plans for emergencies such as medical, fire, hazard material spills and any other contract assessed hazard prevention and abatement requirement needs that apply to this project.

i. Any use of cranes will require a separate crane safety section.

H.3 PRODUCT SUBSTITUTION

Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

H.4 CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS) PROGRAM

This contract may be subject to reporting in the Contractor Performance Assessment System (CPARS) program. Contractors will need to provide a point of contact with email address upon award of contract. Contractors are encouraged to take training and register in this program. Information can be found at:

· Contractor Overview (1.5 hours). View Schedule - This training will give the student an understanding of the Contractor Representative and Contractor Corporate Senior Management levels of access, the policies and regulations governing ACASS/CCASS and CPARS, and the electronic workflow with particular attention to the Contractor comment function.

· Target Audience: This session is specifically targeted to Contractor users who provide Past Performance Evaluation comments or who manage the ACASS/CCASS and CPARS process for their company.

Online course: https://www.cpars.gov/ H.5 Submittals, Shop Drawings, Material Certifications and Testing Reports List of Required Submittals shall include, but are not limited to, the following:

Title
Referenced by Specification No.
Time of Government Approval After Submittal
Concrete Culvert Certification
602(05)
5 days
Aggregate Certification
322(11)G
5 days
Concrete Certification
552(04)
5 days
Safety Plan, Accident Prevention Plan
H.6
At Prework
Bio-preferred Report
C.6
Annual – online – give a copy to the Contracting Officer

H-5. CONTRACTOR’S USE OF EXISTING ROADS

The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. The authorization is limited to roads necessary for direct access between the construction area and storage sites, disposal areas, and other work areas designated in the contract.

The roads authorized for use will be subject to the following general conditions:

(1) State laws governing traffic rules and equipment requirements on State and County Highways.

(2) Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use in excess of State Codes for weight and size, damaging a road while using it, and blocking a road open to use by others.

Load Limits --All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, overwidth permits. Forest Service overload permits for this project may be obtained from the Forest Engineer.

(3) Federal Regulations contained in 36 CFR 261.54 as applied to the area by an order issued under 36 CFR 261.50. These regulations authorized the Forest Service, as a sovereign act, to issue additional restrictions and closures any time conditions warrant. Such closures will be in addition to those shown in the current Road Rules Document and will be posted on the road.

The Contractor shall be responsible for and perform road maintenance commensurate with his use of Forest Service roads in the construction area.

H-6. TRAFFIC CONTROL

The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

The Contractor shall furnish, erect, maintain, and remove when notified any project identification signs shown on the drawings.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

H.7. UTILITY SERVICES

No utilities are available under this contract..

SECTION I -- CONTRACT CLAUSES

I.1 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number
Title
Date
52.202-1
Definitions
(NOV 2013)
52.203-3
Gratuities
(APR 1984)
52.203-5
Covenant Against Contingent Fees
(MAY 2014)
52.203-6
Restrictions on Subcontractor Sales to the Government
(SEPT 2006)
52.203-7
Anti-Kickback Procedures
(MAY 2014)
52.203-8
Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10
Price or Fee Adjustment for Illegal or Improper Activity
(MAY 2014)
52.203-12
Limitation on Payments to Influence Certain Federal Transactions
(OCT 2010)
52.203-17
Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
(Apr 2014)
52.204-4
Printed or Copied Double-Sided on Recycled Paper
(MAY 2011)
52.204-7
System for Award Management
(JUL 2013)
52.204-10
Reporting Executive Compensation and First-Tier Subcontract Awards
(OCT 2016)
52.204-13
System for Award Management Maintenance
(OCT 2016)
52.204-18
Commercial and Government Entity Code Maintenance
(JUL 2016)
52.204-19
Incorporation by Reference of Representations and Certifications
(DEC 2014)
52.209-6
Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment
(OCT 2015)
52.209-10
Prohibition on Contracting with Inverted Domestic Corporations
(NOV 2015)
52.215-2
Audit and Records -- Negotiation
(OCT 2010)
52.219-1
Small Business Program Representations
(OCT 2014)
52.219-6
Notice of Total Small Business Set-Aside
(NOV 2011)
52.219-8
Utilization of Small Business Concerns
(NOV 2016)
52.219-14
Limitations on Subcontracting
(NOV 2011)
52.219-28
Post-Award Small Business Program Representation
(JUL 2013)
52.222-3
Convict Labor
(JUN 2003)
52.222-4
Contract Work Hours and Safety Standards -- Overtime Compensation
(MAY 2014)
52.222-6
Construction Wage Rate Requirements
(MAY 2014)
52.222-7
Withholding of Funds
(MAY 2014)
52.222-8
Payrolls and Basic Records
(MAY 2014)
52.222-9
Apprentices and Trainees
(JULY 2005)
52.222-10
Compliance with Copeland Act Requirements
(FEB 1988)
52.222-11
Subcontracts (Labor Standards)
(MAY 2014)
52.222-12
Contract Termination - Debarment
(MAY 2014)
52.222-13
Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
52.222-14
Disputes Concerning Labor Standards
(FEB 1988)
52.222-15
Certification of Eligibility
(MAY 2014)
52.222-21
Prohibition of Segregated Facilities
(APR 2015)
52.222-26
Equal Opportunity
(SEPT 2016)
52.222-27
Affirmative Action Compliance Requirements for Construction
(APR 2015)
52.222-35
Equal Opportunity for Veterans
(OCT 2015)
52.222-36
Affirmative Action for Workers with Disabilities
(JUL 2014)
52.222-37
Employment Reports on Veterans
(FEB 2016)
52.222-40
Notification of Employee Rights under the National Labor Relations Act
(DEC 2010)
52.222-50
Combating Trafficking in Persons
(MAR 2015)
52.222-55
Minimum Wages Under Executive Order 13658
(DEC 2015)
52.222-60
Paycheck Tranparency
(OCT 2016)
52.222-62
Paid Sick Leave Under Executive Order 13706
(JAN 2017)
52.223-2
Affirmative Procurement of Biobased Products under Service and Construction Contracts
(SEP 2013)
52.223-4
Recovered Material Certification
(MAY 2008)
52.223-6
Drug-Free Workplace
(MAY 2001)
52.223-9
Estimate of Percentage of Recovered Material Content For EPA-Designated Items
(May 2008
52.223-17
Affirmative Procurement of EPA-designated Items in Service and Construction Contracts
(MAY 2008)
52.223-18
Encouraging Contractor Policies to Ban Text Messaging While Driving
(AUG 2011)
52.223-20
Aerosols
(JUN 2016)
52.223-21
Foams
(JUN 2016)
52.225-13
Restrictions on Certain Foreign Purchases
(JUN 2008)
52.228-1
Bid Guarantee
(SEPT 1996)
52.228-2
Additional Bond Security
(OCT 1997)
52.228-11
Pledges of Assets
(JAN 2012)
52.228-12
Prospective Subcontractor Requests for Bonds
(MAY 2014)
52.228-14
Irrevocable Letter of Credit
(NOV 2014)
52.228-15
Performance and Payment Bonds – Construction
(OCT 2010)
52.229-3
Federal, State, and Local Taxes
(FEB 2013)
52.232-5
Payments under Fixed-Price Construction Contracts
(MAY 2014)
52.232-17
Interest
(MAY 2014)
52.232-23
Assignment of Claims
(MAY 2014)
52.232-27
Prompt Payment for Construction Contracts
(JAN 2017)
52.232-33
Payment by Electronic Funds Transfer – Central Contractor Registration
(JUL 2013)
52.232-39
Unenforceability of unauthorized obligations
(JUN 2013)
52.232-40
Providing Accelerated Payments to Small Business Subcontractors
(DEC 2013)
52.233-1
Disputes
(MAY 2014)
52.233-3
Protest after Award
(AUG 1996)
52.233-4
Applicable Law for Breach of Contract Claim
(OCT 2004)
52.236-2
Differing Site Conditions
(APR 1984)
52.236-3
Site Investigation and Conditions Affecting the Work
(APR 1984)
52.236-5
Material and Workmanship
(APR 1984)
52.236-6
Superintendence by the Contractor
(APR 1984)
52.236-7
Permits and Responsibilities
(NOV 1991)
52.236-9
Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10
Operations and Storage Areas
(APR 1984)
52.236-11
Use and Possession Prior to Completion
(APR 1984)
52.236-12
Cleaning Up
(APR 1984)
52.236-13*A1
Accident Prevention, Alternate I
(NOV 1991)
52.236-15
Schedules for Construction Contracts
(APR 1984)
52.236-17
Layout of Work
(APR 1984)
52.236-26
Preconstruction Conference
(FEB 1995)
52.242-13
Bankruptcy
(JUL 1995)
52.243-4
Changes
(JUN 2007)
52.244-6
Subcontracts for Commercial Items
(JAN 2017)
52.245-1
Government Property
(JAN 2017)
52.246-21
Warranty of Construction
(MAR 1994)
52.248-3
Value Engineering – Construction
(OCT 2015)
52.249-2 *A1
Termination for Convenience of the Government (Fixed-Price)Alternate I
(SEP 1996)
52.249-10
Default (Fixed-Price Construction)
(APR 1984)
52.253-1
Computer Generated Forms
(JAN 1991)

FAR 52.215-8 ORDER of Precedence – UNIFORM CONTRACT FORMAT (OCT 1997) Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

1. The Schedule (excluding the specifications)

1. Representations and Other Instructions

1. Contract Clauses

1. Other Documents, Exhibits, and Attachments

1. The Specifications

1. Drawings (End of Clause)

FAR 52.225-9 BUY AMERICAN ACT-CONSTRUCTION MATERIALS (MAY 2014)

a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

[“none”]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of…