1.1 PROJECT BACKGROUND
The USDA-NRCS is conducting floodplain forest and native grassland revegetation actions in Avon Township in Rock County, along the Sugar River.
The reforestation and native grassland design for this area site will include pre-planting site preparation, planting new vegetation in specified areas, installing tree mats and tree tubes, and providing post-planting maintenance.
1.2 PROJECT LOCATION
The Rock County floodplain forest and grassland re-establishment area is located in sections 25, 35 and 36 of Avon Township (T1N R10E). The site is approximately 9 miles southeast of Brodhead, Wisconsin, approximately 6 miles north of Durand, Illinois, and approximately 11 miles west of Beloit, Wisconsin.
1.3 MATERIALS
Supply site preparation and maintenance equipment and materials (herbicide & necessary application equipment and machinery for disking), native seed, nursery tree stock, tree mats and tubes as indicated in plans and specifications Certification of materials required before installation
1.4 EXECUTION
A. Documentation of pre-planting conference and pre-planting inspection with NRCS; obtain diggers hotline ticket number
B. Certification of materials
| Native seed source, PLS |
| Tree stock source, certification of age, transplant (if required in specification) |
| Tree mats and tubes |
C. Staking and Layout:
1. Staking and layout refers to locating and verifying all planting locations as shown on the plans and specifications.
D. Installation of materials
| 1. In May 2010, perform site preparation and planting (native seed, trees, tubes and mats) | indicated on plans and specifications. | |
| 2. In October 2010 perform inspection on tree mortality as indicated in plans and | specifications |
E. Maintenance
| 1. Throughout June, July and August 2010 perform maintenance (strip and field mowing) | activities as indicated in plans and specifications. | |
| 2. In October 2010 perform maintenance (strip spraying in tree plantation area) as indicated in | plans and specifications. | |
| 3. In 2011, perform maintenance (strip and field mowing) as indicated in plans and | specifications. |
1.5 PROTECTION
All planting materials shall be properly protected against harm from normal weather conditions and the public.
1.8 CLEANUP
Work areas are to be kept clean during progress of work and until completion. Remove surplus materials and rubbish from planting areas. Reclaim access roads and staging areas to pre-planting conditions after plant material installation.
END OF STATEMENT OF WORK
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Showing Notes Attendees.pdf | ||
| Revised Bid Schedule 3-22-10.docx | DOCX document | |
| contract clauses.docx | DOCX document | |
| avon_rock_plans_specs.pdf | ||
| SF-1449.pdf | ||
| 81-1253_sca.htm | HTM file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .