pre-bid site visit notes

View the file

Other files for this federal contract opportunity

Other files attached to Forest Lodge Boathouse Phase 1, newest first.
File Type Posted
SF_30_amend_1.pdf PDF
AdditionalSoilBoringInfo_5-6-15.pdf PDF
solicitation_package.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Forest Lodge Boathouse Pre-Bid Items of May 19, 2015:

List of Attendees:

Chad Carlson, PDSI Contractors, 906-241-8828, ccarlson@pdsicontractors.com Nick Patterson, Marine Tech, 218-720-2833, npatterson@marinetechduluth.com Paul Wiedmeyer, Michels, 414-788-6271, pwiedmey@michels.us Roger Medema, ACG, Inc., 773-205-6650, rem@acgchi.com Jesse Proffitt, Kraemer NA, 608-393-8452, jproffitt@kraemerna.com Josh Moen, Ktaemer NA, 715-577-8473, jmoen@kraemerna.com Marques Jolma, M Jolma, Inc., 715-278-3344, mjinc@cheqnet.net Michael Lindow, Ballard Marine Construction, 312-771-2354, michael.lindow@ballardmc.com

Notes:

1. See letter dated May 6, 2015 from Twin Ports Testing regarding additional soil boring information.

2. It was noted that there are public boat launch sites on Lake Namakagon that the Contractor may use for launching boats and/or barges. It is the Contractor’s responsibility to investigate these sites to see if they are adequate and usable.

3. Any barges (including pumps) launched in Lake Namakagon shall be decontaminated before launching into the lake. The method of decontamination shall be approved and verified by the COR.

4. Sheet TOO1:

a. Note 8: The Owner has submitted the plans and applied for the Wisconsin DNR permit for this Contract. The Contractor is not required to apply or pay for this permit application, however, the Contractor shall comply with the permit conditions. No other permits are required.

5. Sheet C101, Access Road clarification:

a. The existing drive behind the Cow Palace and drive to the East towards the Boathouse are existing and do not require new gravel surfacing. A load will be required next to the pumphouse.

b. In the area of the Lakewater Pump House and Bowling Green up to the Boathouse, the Contractor shall lay down rubber mats. The rubber mats will be provided by the Forest Service for the Contractor’s use. The contractor can pick them up and return them in Park Falls, WI.

c. The Contractor shall furnish and install a new gravel staging area (if needed) and access road from behind the Cow Palace to the location of the Temporary Bridge at the lake shoreline. The new road will be restored following construction, and the salvaged aggregate will be placed on the existing main road adjacent to the cow place. No prep work required.

d. The Contractor shall confine all equipment, materials, services (dumpsters, port-a-jons, etc.) to the new gravel staging area as shown on the drawing. Unless otherwise approved by the COR.

e. The Contractor shall strip the lawn areas of the access road and stockpile the existing topsoil for reinstallation at the completion of the project.

f. The Contractor shall furnish and install 200 linear feet of silt fence at the shoreline in the location of the temporary bridge, 100 linear feet on each side of the bridge.

g. The Contractor shall confine his operations to the limits of the access roads and staging area as shown by the fence like symbol on Sheet C101. Unless otherwise approved by the COR.

h. No activity shall be allowed within 100 feet of the two bat houses as shown on the drawing.

i. Any bats found rousting in the process of this work shall be brought to the COR’s attention immediately and all work in that area will temporarily stop.

j. All downed trees at the site will be removed by the Owner before this Contract starts. Any additional tree removal for the access road will be the Contractor’s responsibility and will need to be approved by the COR. 6 trees will be remaining, the contractor will need to place them along the shore line in 2 groups of 3. This will occur between the steam shed and the temporary bridge. The butt ends will be on land when completed.

6. Sheet S201:

a. The successful Contractor will be required to submit a Support Plan for Lifting the Boathouse which the COR will have 14 business days to approve.

b. The Contractor is required to furnish and install all temporary bracing for the lifting and setting back down the structure. All temporary bracing (such as additional collar ties in the second story roof framing) shall be removed at the completion of the Contract.

c. Currently the structure is out of level and as a result of this work the structure will be reinstalled in a level condition. As a result the building is going to move and rack. The Contractor shall lift and set back down the structure in such a way as to limit damage to the structure and will not be held responsible for nonstructural interior and exterior repairs.

7. Sheet A201:

a. Replaced logs shall be 6-inch average diameter half logs, white cedar, hand peeled and kiln dried.

b. The only log, trim, window, and door work required is if any materials are removed for lifting of the building, reinstallation of the removed materials will be with new decay free materials. No other exterior finish work is required in this Contract. A Phase 2 Contract on the Boathouse will include exterior finish work, window & door work, roof shakes, gutters, metal handrail painting, elevator/lift, electrical, and possible DSL service.

c. Note 15: The splice cuts should be secured with fiberglass dowels set in epoxy. Metal connectors cannot be used.