General Decision Number: MI100260 07/29/2011 MI260
State: Michigan
Construction Type: Building
Counties: Menominee and Ontonagon Counties in Michigan.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Modification Number Publication Date 0 04/01/2011 1 05/06/2011 2 06/03/2011 3 07/01/2011 4 07/15/2011 5 07/22/2011 6 07/29/2011
ASBE0049-005 06/01/2010
ONTONAGON COUNTY
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR........................$ 26.82 21.80
ASBE0127-005 05/31/2011
MENOMINEE COUNTY
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR........................$ 29.04 19.58
BOIL0169-002 08/01/2010
Rates Fringes
BOILERMAKER......................$ 32.34 22.18
BRMI0006-001 05/01/2011
Rates Fringes
BRICKLAYER.......................$ 24.40 15.51
TILE SETTER......................$ 24.40 15.51
* CARP1510-005 06/01/2011
Rates Fringes
MILLWRIGHT.......................$ 27.89 15.86
* CARP1510-007 06/01/2011
MENOMINEE COUNTY (except for that part south of County Road K at Amberg, Wisconsin, starting on the west at the Menominee River and ending on the east at the Bay of Green Bay) and
ONTONAGON COUNTY
Rates Fringes
CARPENTER (Including Acoustical Ceiling Installation, Drywall Finishing/Taping, Drywall Hanging, Form Work, and Soft Floor Layer - Carpet)............$ 23.37 15.65
ELEC0219-014 05/30/2011
ONTONAGON COUNTY
Rates Fringes
ELECTRICIAN (Excludes Low Voltage Wiring) Electrical contracts of $130,000 or less............$ 25.02 16.80 Electrical contracts over $130,000....................$ 29.41 16.97
ELEC0979-006 06/01/2010
MENOMINEE COUNTY (All Townships except Ingallston, Melon and Menominee)
Rates Fringes
ELECTRICIAN (Excludes Low Voltage Wiring)..................$ 29.84 15.09
ENGI0324-031 05/01/2011
Rates Fringes
POWER EQUIPMENT OPERATOR:
Crane operator, main boom & jib 120' or longer........$ 26.93 19.45 Crane operator, main boom & jib 140' or longer........$ 27.18 19.45 Crane operator, main boom & jib 220' or longer........$ 27.43 19.45
GROUP 1.....................$ 26.43 19.45
GROUP 2.....................$ 22.60 19.45
GROUP 3.....................$ 21.66 19.45
Hydraulic crane operator 75 tons and under:$.75 per hour additional. Hydraulic crane operator over 75 tons:$1.00 per hour additional. Lattice boom crane operator:$1.50 per hour additional. Premium rate: main boom and jib 300 feet or longer is $1.50 per hour above the 220 ft. boom and jib rate. Premium rate: main boom and jib 400 feet or longer is $3.00 per hour above the 220 ft. boom and jib rate.
Crane Operator with main boom and jib 300' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 220' of boom and jib wage rate.
Crane Operator with main boom and jib 400' or longer shall be paid an additional one dollar and fifty cents ($1.50) per hour above the 300 foot of boom wage rate ($3.00)
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: backhoe, bulldozer; crane, front end loader, excavator, paver, roller, and scraper (self-propelled and tractor drawn) GROUP 2: fork truck GROUP 3: oiler
IRON0008-008 06/07/2010
Rates Fringes
IRONWORKER, REINFORCING AND
STRUCTURAL
Contracts $10,000,000 or greater.....................$ 24.93 21.47 Contracts less than $10,000,000.................$ 21.84 21.47
LABO1329-005 05/01/2011
Rates Fringes
LABORER
Common or General; Mason Tender - Brick; Mason Tender - Cement/Concrete;
and Sandblaster.............$ 19.86 11.83 Pipelayer...................$ 20.26 11.83
PAIN1011-001 06/01/2010
Rates Fringes
PAINTER (Insulator Foam Only)....$ 25.78 9.17
PAIN1011-004 06/01/2010
Rates Fringes
PAINTER (Brush and Spray Only)...$ 19.61 8.92
PLAS0016-037 06/01/2010
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 24.82 12.83
PLUM0111-002 05/01/2011
Rates Fringes
PIPEFITTER (Excludes HVAC Pipe & System Installation)......$ 29.41 19.80 PIPEFITTER (HVAC Pipe Installation Only)...............$ 29.41 19.80 PLUMBER (Excluding HVAC Pipe & System Installation)...........$ 29.41 19.80
ROOF0149-014 05/01/2010
Rates Fringes
ROOFER...........................$ 16.16 10.27
SHEE0007-006 01/01/2011
Rates Fringes
SHEET METAL WORKER (Excluding HVAC Duct & System Installation)....................$ 28.80 19.04 SHEET METAL WORKER (HVAC Duct & System Installation)...........$ 28.80 19.04
SUMI2011-081 02/14/2011
Rates Fringes
GLAZIER..........................$ 17.50 2.27
LABORER: Irrigation & Landscape........................$ 14.95 0.00
OPERATOR: Grader/Blade..........$ 24.04 6.03
OPERATOR: Tractor...............$ 19.60 7.31
PAINTER: Roller Only............$ 16.58 2.84
TRUCK DRIVER: Flatbed Truck.....$ 17.44 4.51
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5(a)(1)(ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
| Branch of Construction Wage Determinations |
| Wage and Hour Division |
| U.S. Department of Labor |
| 200 Constitution Avenue, N.W. |
| Washington, DC 20210 |
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Write to:
| Wage and Hour Administrator |
| U.S. Department of Labor |
| 200 Constitution Avenue, N.W. |
| Washington, DC 20210 |
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
| Administrative Review Board |
| U.S. Department of Labor |
| 200 Constitution Avenue, N.W. |
| Washington, DC 20210 |
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 5 Experience Questionnaire.pdf | ||
| SF-1442 Continuation Solicitation .docx | DOCX document | |
| Attachment 2 vicinity maps.pdf | ||
| SF-1442 Solicitation.pdf | ||
| Attachment 1- Specifications - 3.docx | DOCX document | |
| Attachment 3 Photos.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .