ATTACHMENT_5_-_FS_Supplement.docx

DOCX document 154 KB Posted

Attached to
White Creek Fire Road Repair Federal contract opportunity
Solicitation number
AG-4670-S-17-0171
Issued by
Department of Agriculture Forest Service

About this file

ATTACHMENT 5 - FS Supplement

View the file

Other files for this federal contract opportunity

Other files attached to White Creek Fire Road Repair, newest first.
File Type Posted
ATTACHMENT_2_-_Statement_of_Work.pdf PDF
ATTACHMENT_4_-_White_Creek_Fire_Map_2of2.pdf PDF
ATTACHMENT_1_-_Schedule_of_Items.docx DOCX document
ATTACHMENT_3_-_White_Creek_Fire_Map_1of2.pdf PDF
ATTACHMENT_7_-_Relevant_Experience_Questionnaire.doc DOC document
AG-4670-S-17-0171_body_pp_3-32.doc DOC document
ATTACHMENT_6_-_DOL_Wage_Determination_AG-4670-S-17-0171.txt TXT text file
AG-4670-S-17-0171__SF-1442_pp_1-2.PDF PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-4670-S-17-0171

ATTACHMENT 5

Section C Description/Specification/Work Statement

C1.1 – SCOPE OF CONTRACT

The contractor shall provide all equipment, labor, supervision, transportation, materials, tools, and other incidentals and execute all work necessary to perform road maintenance on National Forest roads in accordance with the Performance Work Statement (PWS) specifications, exhibits and industry standards. The Forest Service does not know the exact condition of every road, therefore it is the Contractor’s responsibility to review roads listed on the Schedule of work. District maps showing road locations may be obtained at the District Ranger Office.

C1.2 – PERSONNEL

1.2.1 Contractor Representative. The contractor shall designate a representative in accordance with FAR 52.236-6 included in Section I of this contract. The name of this person shall be designated in writing and provided to the Contracting Officer.

1.2.1.1. Authority. The contractor representative shall have authority to act for the contractor on all contract matters relating to daily operation of this contract.

1.2.1.2. Response Time. The contractor representative shall be available during normal duty hours (i.e. Monday thru Friday 8am – 5pm) within 6 hours to meet, at the site of work, with Government personnel designated by the Contracting Officer to discuss and resolve performance issues. After normal duty hours the representative shall be available within 6 hours in case of emergency.

1.2.1.3. Language. The contractor representative must be able to read, write, speak, and understand English.

1.2.2. Public Safety and Traffic Control

1.2.2.1 The contractor shall exercise caution and care while pursuing the work in order to prevent unnecessary conflict with road users.

Appropriate warning signs shall be posted on each end of work areas or zones. Signs shall be of the size, quantity and colors as required by the current edition of the Manual on Uniform Traffic Control Devices (MUTCD). These signs shall be moved as needed to properly delineate and identify the sections of roads being maintained. Warning signs shall be placed within 1 mile of active operations, in no case shall warning signs be greater than 5miles apart. Additional signs may be placed to cover entire work area. See also “Maintenance and Control of Traffic” under Section J.

Excerpts from the 2009 MUTCD are included in this contract for reference. Online pdf version of the MUTCD is available for viewing at http://mutcd.fhwa.dot.gov/.

ALL personnel working on this contract, including equipment operators, sub-contractors and contractor’s representative, shall wear an ANSI approved Class II reflective vest.

1.2.3. ACCESS. In most cases, roads are open continuously. The Government will supply a key to the Contractor for roads closed by Forest Service gates. It is the contractor’s responsibility to obtain all keys for closed roads from the District Ranger Office prior to start of work and must be returned once the work included in the description of work is completed.

C1.3 – QUALITY CONTROL.

1.3.1. QUALITY CONTROL PLAN. The contractor shall establish and maintain a Quality Control Program to ensure the requirements of the contract are achieved. One copy of the contractor's Quality Control Plan shall be provided to the Contracting Officer/Contracting Officer’s Representative prior to the start of contract work.

1.3.2. PLAN CONTENTS.

1.3.2.1. Inspection System. An inspection system must cover all of the services listed in the “description” column of the Performance Requirements Summary (PRS). The inspection system need only cover items included in the description of work. It must specify the work items to be inspected on either a scheduled or unscheduled basis, how often inspections will be accomplished, or the title of the individual(s) who will perform the inspection. The inspection system must provide for a written record of inspections and results.

1.3.2.2. Methods. The proposed methods for identifying and preventing defects before the level of performance becomes unacceptable.

1.3.2.3. Records. The contractor shall maintain on-site records of all inspections and necessary corrective action(s) taken. This documentation shall be furnished at the time payment is requested, or when requested by the Contracting Officer’s Representative during the term of the contract. Project inspectors reserve the right to check contractor’s Quality Control Inspections at any time during the life of a contract.

1.3.3. GOVERNMENT REVIEW. The Government will review the Contractor Quality Control Plan to determine if it is adequate within 10 calendar days of submission. If the plan is found to be adequate, the Government will authorize the plan. If the plan is not adequate as submitted, the deficiencies will be identified to the contractor in writing. The contractor shall correct all identified deficiencies and submit a corrected Contractor Quality Control Plan prior to start of work.

C1.4. QUALITY ASSURANCE.

1.4.1. CONTRACTING OFFICER'S REPRESENTATIVE (COR). COR(s) will be appointed to monitor contractor performance and have the right to inspect and accept or reject the services as required by the contract. The name and telephone number of each COR under the contract will be furnished to the contractor in writing by the Contracting Officer.

1.4.2. PROJECT INSPECTOR. A Project Inspector will be appointed to monitor contractor performance and have the right to inspect and accept or reject the services as required by the contract. The inspector will monitor the contractor's performance under this contract using the method(s) of surveillance specified in the Quality Assurance Surveillance Plan (QASP). All monitoring observations will be recorded by the government. When an observation indicates defective performance, the inspector will request the contractor's representative to confirm defective work and perform corrective work.

1.4.3. PERFORMANCE EVALUATION MEETINGS. The contractor’s representative and/or project manager may be required to meet weekly with the COR or others during the first month of the contract. Meetings shall be as often as necessary thereafter as determined by the Contracting Officer. If requested by the Contractor, a meeting will be held whenever a Notice of Noncompliance is issued. The meetings shall focus on contractor performance and actual or potential problems. A mutual good faith effort shall be made by all parties to resolve all issues. The written minutes of these meetings shall be signed by the parties to the discussion. Should the contractor not concur with the minutes, the contractor shall so state any areas of non-concurrence in writing to the Contracting Officer within seven working days of receipt of the minutes.

1.4.4. CONTRACTOR NOTIFICATION RESPONSIBILITIES. To facilitate timely inspections, the contractor shall inform the Project Inspector of the proposed operation schedule on a weekly basis. It is the Contractor’s responsibility to notify the Inspector or COR if the schedule changes. Should the Contractor be unable to notify the Inspector, notify the COR or CO, in that order.

C1.5. Physical Security

1.5.1. KEY CONTROL. The contractor shall establish and implement methods of ensuring that all keys issued to the contractor by the Government are not lost or misplaced and are not used by unauthorized persons. No keys issued to the contractor by the Government shall be duplicated. The contractor shall develop procedures covering key control that shall be included in the quality control plan. ALL keys issues by the Government are to be returned prior to final payment request.

C1.6 PERIODS OF OPERATION

1.6.1. Work hours are generally limited to weekdays between dawn and dusk. Work outside of those times requires approval by the COR or Project Inspector. Work on federal holidays requires prior written approval from the Contracting Officer. No written approval is necessary for work done on weekends so long as the COR approves.

1.6.2. Actual grading periods are subject to temperature and moisture content restraints as specified in Section J.

C1.7. ENVIRONMENTAL PROTECTION.

1.7.1 The contractor shall instruct employees in environmental protection practices. The contractor shall be responsible for operating under conditions which preclude the waste of fuel or spoiling the environment which shall include:

1.7.2. Fuel. Fuel for equipment, trucks and vehicles shall not be wasted. Extended engine idling shall not be permitted.

1.7.3. Machine Fluids. Machine fluids (fuel, oils, coolants, etc.) shall not be drained on the ground or allowed to enter any watercourse. Inadvertent spills shall be contained immediately and the District Ranger, Project Inspector, and local authorities shall be notified immediately. Promptly remediate the spill unless otherwise directed by authorities.

C1.8. DOCUMENTATION AND RECORDS.

1.8.1. The contractor shall maintain records of accomplishment using the form shown in Exhibit C, Daily Accomplishment Report in Section J. Reports are to be updated Daily, COR/Inspector reserves the right to view these documents at any time during inspection visits. These reports shall be verified and signed by the Project Inspector and submitted to the Contracting Officer’s Representative along with the contractor’s invoice for payment and shall be become the property of the Government. No payment or acceptance shall be made prior to receipt of these records.

1.8.2. All documentation, records and schedules as described in the PWS that are the responsibility of the contractor, are the property of the Government and shall be turned over to the Government upon completion or termination of the contract. All records are subject to the Freedom of Information and/or Privacy Acts and any requests for release of any records shall be handled accordingly.

C1.9. PAYMENT PROCEDURES.

1.9.1. The Government may make progress payments as the work proceeds per the Contractor’s request. The Contractor shall make this request by submitting the following to the COR:

1. Itemized Invoice that includes your Name/Company Name, Address, City, State, Zip Code, Vendor Number, Delivery Order Number, Invoice Number, and Date. Purchase Order Numbers are not overall Contract Numbers and will be different for each contract issued. Delivery Order Numbers typically follow the format AG-XXXX-D-XX-XXXX.

2. Daily Accomplishment Reports for the days covered in the Invoice. Daily Accomplishment Reports are to be signed by the Contractor and Inspector prior to submission.

3. Quality Control Plan inspection records for all roads for which payment is being requested for.

4. A written receipt from the District Office stating that all keys issued to the Contractor have been Returned in order to process the Final Invoice.

1.9.2. The COR has 7 working days after the Invoice AND appropriate documentation has reached the billing office to determine if the Invoice is a proper Invoice, containing all information described in section C1.9.1. It is the Contractors responsibility to get the Invoice and appropriate paperwork to the billing office. The billing office for these contracts shall be the office address of the COR on file for each contract. If the Invoice is rejected the COR will return the Invoice with a letter stating deficiencies. Once the Invoice has been approved the government has 30 days from the date the COR received the invoice to pay the contractor via Electronic Funds Transfer.

SECTION C-2

DEFINITIONS

Whenever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows: (Reference to a specific standard or specification shall mean the latest addition or amendment thereto in effect on date of Request for Proposal.)

2.1. STANDARD DEFINITIONS.

ACCEPTABLE QUALITY LEVEL (AQL). The maximum allowable defects that may occur before the Government will affect the price computation system in accordance with the Performance Requirements Summary and the Inspection of Services Clause. An AQL does not allow a contractor to knowingly offer defective service, but limits reduced payment to circumstances in which defective performance results in a measurable reduction in the value of services rendered.

PERFORMANCE REQUIREMENTS SUMMARY (PRS). Identifies the key service outputs of the contract that will be evaluated by the Government to assure contract performance standards are met by the contractor.

QUALITY ASSURANCE. Those actions taken by the Government to assure services meet the requirements of the Performance Work Statement (PWS).

CONTRACTING OFFICER'S REPRESENTATIVE (COR). A Government person designated by the Contracting Officer with authority to act within the scope the delegated authority.

QUALITY ASSURANCE SURVEILLANCE AND COR ACTION PLAN (QASP). An organized written document used for quality assurance surveillance. The document contains specific methods to perform surveillance of the contractor.

QUALITY CONTROL. Actions taken by a contractor to control the performance of services so that services meet the requirements of the PWS.

2.2 TECHNICAL DEFINITIONS PECULIAR TO THIS PWS.

2.2.1 Graphic definitions and representations of road structural terms are shown on drawing Exhibit D.

Adjustment in Contract Price -“Equitable adjustment,” as used in the Federal Acquisition Regulations

Agreed or Approved - Official agreement or approval by use of a written document issued by the Government. Agreements also require signature of Contractor's Representative and are dated.

Aggregate Base Course (ABC ) - Gravel material meeting the requirements of the North Carolina Department of Transportation Standard Specifications for Roads and Structures, Division 10, for Aggregate Base Course (ABC). Section J Exhibit.

Aggregate Base Course (M) (ABC(M)) - Gravel material meeting the requirements of the North Carolina Department of Transportation Standard Specifications for Roads and Structures, Division 10, for Aggregate Base Course (ABC(M)). Section J Exhibit.

Berm - A curb or dike which controls traveled way and shoulder runoff water, or delineates traffic direction. Berms commonly parallel road centerline; however, on limited use roads may be placed diagonally across the roadbed. An unnecessary berm is a berm that prevents proper drainage or does not perform a desirable function.

Bid Schedule - Schedule containing a list of maintenance items, quantities, units of measure, unit price and amount.

Channel - A natural waterway leading into or away from a culvert or bridge.

Contract Quantities - Those estimated quantities shown in the Schedule of Items as awarded.

Contract Modification - A written supplemental agreement between the Government and the Contractor, documenting a modification to the contract and establishing an equitable adjustment if applicable.

Contractor - The individual, partnership, joint venture, or corporation undertaking the execution of the work under the terms of the contract.

Culvert - Any structure which provides a passageway, drain, or waterway under a road or embankment.

Ditch - A relatively long narrow excavation placed to collect or disperse water.

Drainage dip - A constructed depression within the roadbed to form a uniform depression that allows routine passage of vehicles while diverting water from the traveled way.

Drainage ditch - A ditch located parallel to and abutting the roadbed. Road Ditch. Roadside Ditch.

Drainage structure - A term identifying man-made devices placed to control water movements.

Drawings - Design sheets or fabrication, erection, or construction details submitted to the Government by the Contractor. Also refers to submissions and submittals.

Equipment - All machinery, operating supplies and tools necessary for the proper performance and acceptable completion of the work.

Excess Material - Material generated from the work of this contract which is unsuitable or in excess to that needed for maintenance work required by this contract.

Foreslope - The slope of the ditch section from the road shoulder to the ditch flowline.

Forest Service - The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Government - The Contracting Officer or the duly authorized Contracting Officer's Representative (COR) with authority to sign orders.

Grade (noun) - The vertical alignment of the top surface of the road, a ditch flowline, the ground or other surface. Grade can also mean slope.

High Clearance Vehicles - Vehicles such as, pickups, 4x4s, and log trucks.

Inspector - The Government's authorized representative designated in writing, assigned to make detailed inspections of contract performance, but not to sign orders to the Contractor.

Lead-off ditch -- A ditch used to remove water from roadside drainage ditches.

Materials - Any substances specified for use in the performance of the work.

Measurement - The process of identifying the dimensions, quantity, or capacity of an item.

Neat Line - A line defining the proposed or specified limits of an excavation or structure.

Order - A written order by the Government directing fulfillment of work requirements under the terms of the contract.

Paved Surface or Pavement - Denotes asphalt, concrete, or other stabilized materials excluding natural aggregates. Dust palliative treatments are not considered as pavement.

Pavement Structure - The combination of subbase, base, paving geotextiles, and surface courses placed on a subgrade to support and distribute the traffic load to the roadbed.

Plans - The contract plans furnished by the government showing the location, type, dimensions, and details of the work.

Protected Streamcourse - A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Reasonably Close Conformity - Compliance with customary maintenance tolerances where working tolerances are not specified.

Right-of-Way -- A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Roadbed - The graded portion of a road between the intersection of subgrade and side slopes excluding the portion of the ditch below subgrade.

Roadway - Top of cut to bottom of fill. Section J Exhibit E

Road Ditch - Drainage ditch. Roadside ditch.

Roadside Ditch – Road ditch. Drainage ditch.

Rolling Dip - A shallow, wide, ditch placed across the roadbed to remove water from the roadbed surface that can be driven across by high clearance vehicles; usually placed diagonal to the centerline. Drainage Dip.

Schedule of Items - Schedule containing a listing of maintenance items, quantities, units of measure, unit price, and amount.

Shoulder - Surface of the roadbed from the edge of the traveled way, outward to any one of the following: 1) the top of the ditch foreslope, 2) toe of cut slope, or 3) top of fill slope. Section J Exhibit E

Silt Trap - A constructed rectangular pit, approximately 2’-4’ wide, 2’deep, and 4’-8’ long (or longer), placed in the vicinity of a roadside ditch flowline or tail ditch, such that water flowing in the ditch enters the trap and allows silts and sands to “drop out” before exiting the trap and continuing down the ditch or to daylight. Roadside ditch silt traps are generally parallel to and adjacent to the roadway and clean the water flowing in the roadside ditch. Tail ditch silt traps are on the outfall side of a culvert, typically in the tail ditch (if present) and clean the water prior to discharge. It does not include a pit that catches water from sheet flow across a roadway.

Slough or Slide - Material fallen or slid on to the roadway or off or down an embankment slope that may need to be repositioned or removed.

Slump - A localized portion of the roadbed which has slipped or otherwise become lower than that of the adjacent roadbed and constitutes a hazard to traffic.

Special Project Specifications - Specifications which detail conditions and requirements specific to the individual project.

Tail Ditch - A ditch used to convey water away from a culvert outlet, Cattleguards, or similar drainage structure, typically and preferably to daylight.

Traveled Way - The portion of the roadway for the movement of vehicles. For purpose of this contract, traveled way includes turnouts and curve widening.

Turnouts - A short auxiliary lane on a road provided for passage of meeting vehicles or overtaking vehicles.

Unsuitable Material - Material removed during maintenance which must be disposed of in designated locations. This includes material with substantial amounts of debris, rocks, vegetation, muck, sod, organics or other objectionable material. See also excess material.

Water bar - A shallow ditch placed across the roadbed to remove water from the surface. Water bars are similar to Rolling dips, but are much shorter and abrupt.

Wing Ditch -- Lead-off ditch.

Work Schedule - The Contractor's current schedule for work progression.

SECTION C-3

Quantity Measurement Terms

U.S. Customary Units of measure are used in conjunction with these specifications.

The methods of measurement and computation will be those necessary to accurately determine the quantities of materials furnished and work performed.

All items, which are measured by the foot, will be measured along its longitudinal centerline, unless otherwise shown on the drawings.

A station when used as a definition of term or measurement will be one hundred feet, or a precise location along a survey line.

Miles will, in the absence of known distances from existing plans or surveys, be determined by the Government using a calibrated survey odometer or equal substitute operated on the traveled way at or parallel to road centerline.

The term "ton" means 2000 pounds. Trucks used to haul material measured by truck weight shall be weighed empty at least once daily, and each truck shall bear a plainly legible identification mark. Weight tickets furnished by the Contractor from certified scales will be used to determine weight measurements.

Materials measured by the cubic yard in the hauling vehicle shall be measured therein at the point of delivery. Vehicles may be of any legal size or type, provided that the box is of such shape that the actual volume may be readily and accurately determined.

Measurement by the acre will use the length and width treated. Measurement will be along the ground surface. Measurement of width will approximate significant slope breaks, but will not include minor deviations along the slopes.

Measure square yard along longitudinal and traverse slopes on transverse slopes steeper than 2:1.

The term "lump sum" when used in the Bid Schedule means the complete unit as required by or described in the contract.

Measurement will be made of each item or unit of work, as shown in the Bid Schedule, completed and accepted in accordance with the contract provisions, specifications, and drawings.

ABBREVIATIONS

AASHTO - American Association of State Highway and Transportation Officials.

ABC – Aggregate Base Course

AQL – Acceptable Quality Level

ASTM – American Society for Testing and Materials.

COR – Contracting Officer’s Representative

EPA - Environmental Protection Agency.

FAR - Federal Acquisition Regulation System.

FED SPEC - Federal Specifications.

FP-03 - Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects.

MSHA - Mine Safety Health Administration.

MUTCD - Manual of Uniform Traffic Control Devices.

NBS - National Bureau of Standards.

NCDOT – North Carolina Department of Transportation

OSHA - Occupational Safety and Health Administration.

PBSC – Performance Based Service Contract

PRS – Performance Requirements Summary

QA – Quality Assurance (Government Responsibility)

QC – Quality Control (Contractor Responsibility)

QASP – Quality Assurance Surveillance and COR Action Plan

SECTION C-3

GOVERNMENT FURNISHED

PROPERTY/MATERIAL

3.1. Government Keys The Government will provide a gate key to the contractor, if any of the road gates are locked. Refer to section C1.2.3.

3.2. Gravel The Government reserves the right to provide gravel on certain portions of roads, prior to grading. Gravel will be placed to a uniform thickness by tailgating or similar methods ahead of the blading operation. See also Section J.

SECTION C-4

CONTRACTOR FURNISHED

PROPERTY, SUPPLIES, MATERIALS, and EQUIPMENT

4.1 General. Except for those items or services specifically stated to be Government furnished in Section C-3 or other sections of this specification, the contractor shall furnish all equipment, materials, supplies, and incidentals required to perform the tasks identified in this contract in a skillful and workmanlike manner.

SECTION C-5

SPECIFIC TASKS

5.1 Grading Aggregate Surfaced and Non-surfaced Roads - Blading operations to remove ruts, potholes, corrugations and unnecessary berms.

5.1.1 Quality Standard

· Road bed is firm, smooth, and finished to the intended width and cross slope, including turnouts. Aggregate surface material (if present) is uniform depth. Surface is free of ruts, potholes, washes and wash boarding.

· Road surface drains completely. Cross slope or crown is a uniform 3% ± 1% or existing slope if steeper than 4%.

· Intersections are smoothly blended. No abrupt grade breaks.

· Ruts, potholes, washboards and wash outs are scarified to the bottom of the defect. No areas of high blading exist.

· No loose rocks larger than 3” in its largest dimension remain on the traveled way and shoulders.

· No debris, trash, or otherwise unsuitable material exists on the traveled way and shoulders.

· Leaves and pine needles generated from ditch(es), traveled way and shoulders are evenly spread over traveled way unless otherwise directed by the COR.

5.1.2 Measurement

Measure the Section 5.1 items listed in the bid schedule according to Section 5.1 and the following as applicable.

Measurement shall be made to the nearest tenth (0.1) of a mile using an odometer or distance measuring instrument calibrated over a measured mile.

5.1.3 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section C5.1 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this section.

Pay Item Pay Unit

C5.1 (1) Grading Aggregate Surfaced and Non-surfaced Roads Mile

5.2 Cleaning and Reshaping Ditches - Maintaining all ditches in their original location to the shape and grade required to ensure roadway drainage.

5.2.1 Quality Standard

· Ditches shall be cleaned to a minimum depth of 1 foot (12”) below the edge of shoulder or to rock and the slope of the ditch from the road shoulder to the bottom of the ditch is 2:1 or flatter. Transitions to culverts are smooth and transition from normal ditch depth to the invert of the culvert in 20’ +/- 5’. Ditch debris shall not be left piled at or around culvert entrances. In no case shall ditches deeper than 24” be cut into with a grader blade.

· Ditches shall not allow water to stand.

· Culvert inlets are unobstructed by grass, debris, dirt, brush, or trees less than 4” in diameter within a 3’ radius of culvert inlet. Relief ditches are exempt from this standard.

· Road prism is not cut into.

· Loose rocks that are impeding proper drainage, dirt, slough, debris and deposits are removed from the ditch, including foreslope and backslope. Additional tools may be necessary to clean ditches with depths greater than 24”.

· Backslopes match existing and have not been undercut.

· Silt Traps are cleaned to original dimensions and depth. Lead off ditches are included as part of this pay item.

5.2.2 Measurement

Measure the Section 5.2 items listed in the bid schedule according to Section 5.2 and the following as applicable.

Measurement shall be made to the nearest tenth (0.1) of a mile using an odometer or distance measuring instrument calibrated over a measured mile.

Road ditches shall be measured to the nearest tenth of a mile by vehicle odometer. Measurement shall be made for each side of the road. Leadoff ditches and roadside ditch silt traps shall be considered incidental to the pay item for cleaning and reshaping ditches.

5.2.3 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section C5.2 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this section.

Pay Item Pay Unit

C5.2 (1) Cleaning and Reshaping Ditches Mile

C5.2 (2) Wattles, ___________________ Each

5.3 Cleaning and Brushing of Culvert Inlets and Ditch Transitions– Culverts inspected and cleaned to remove dirt, silt, muck, debris and vegetative matter at and around culvert inlets. Transitions to culverts are smooth and transition from normal ditch depth to the invert of the culvert in 20’ +/- 5’.

5.3.1 Quality Standard

· Culverts barrels shall be cleaned at its immediate inlet to remove any dirt, silt, muck, debris, and vegetative matter that might cause culvert blockage.

· Culvert Inlets are unobstructed by grass, debris, brush, dirt, or trees less than 4” diameter within 3’ of its inlet.

· Loose rocks that are impeding proper drainage, dirt, slough, debris and deposits are removed from the Ditch Transition, including foreslope and backslope.

· Dispose of unsuitable material outside of the traveled way and shoulders, and in manner as to not impede any watercourses or as directed by the COR or Project Inspector.

5.3.2 Measurement

Measure the Section 5.5 items listed in the bid schedule according to Section 5.5 and the following as applicable.

Measurement shall be made of the roadway served by the culverts, to the nearest tenth of a mile using a vehicle odometer or distance measuring instrument calibrated over a measured mile.

5.3.3 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section C5.5 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this section.

Pay Item Pay Unit

C5.3 (1) Cleaning and Brushing of Culvert Inlets and Ditch Transitions Mile

5.4 Clean Culverts and Tail Ditches – Culverts inspected and cleaned to remove dirt, silt, muck, debris and vegetative matter to maintain an un-obstructed flow of water.

5.4.1 Quality Standard

· Culverts shall be cleaned throughout its length so that no more than 2” of debris is left in any culvert of 36” or less diameter. Culverts larger than 36” shall be cleaned of debris so that no more than ⅛ the diameter of the culvert is blocked.

· Culvert inlets are unobstructed by grass, debris, brush, dirt, or trees less than 4” diameter within 3’ of its inlet and outlet.

· Tail ditches at culvert outlets completely drain.

5.4.2 Measurement

Measure the Section 5.3 items listed in the bid schedule according to Section 5.3 and the following as applicable.

Measurement shall be made of the roadway served by the culverts, to the nearest tenth of a mile using a vehicle odometer or distance measuring instrument calibrated over a measured mile. Cleaning tail ditches and silt traps within tail ditches will not be measured separately, but will be considered incidental to cleaning culverts.

5.4.3 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section C5.3 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this section.

Pay Item Pay Unit

C5.4 (1) Clean Culverts and Tail Ditches Mile

5.5 Aggregate Surfacing, Type ABC - Replacement of surface aggregate lost due to traffic wear or erosion.

5.5.1 Quality Standard

· Road bed is firm, smooth, and finished to the intended width and cross slope, including turnouts. Aggregate surface material (if present) is uniform depth. Surface is free of ruts, potholes, washes and washboarding.

· Road surface drains completely. Cross slope or crown is a uniform 3% ± 1% or existing slope if steeper than 4%.

· Intersections are smoothly blended. No abrupt grade breaks.

· Ruts, potholes, washboards and wash outs are cut to the bottom of the defect. No areas of high blading exist.

· No loose rocks larger than 3” in its largest dimension remain on the traveled way and shoulders.

· No debris, trash, or otherwise unsuitable material exists on the traveled way and shoulders.

· Leaves and pine needles generated from ditch(es), traveled way and shoulders are evenly spread over traveled way unless otherwise directed by the COR.

5.5.2 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section C5.4 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this section.

Pay Item Pay Unit

C5.5 (1) Aggregate Surfacing, Type ABC TON

C5.5 (1) Aggregate Surfacing, Type ABC (M) TON

5.6 Spot Surfacing - Load, haul, and place surface material to repair or stabilize road surfaces.

5.6.1 Quality Standard

· Road bed is firm, smooth, and finished to the intended width and cross slope, including turnouts. Aggregate surface material is uniform depth. Surface is free of ruts, potholes, washes and washboarding.

· Spot surfacing is complete when the designated quantity of the ordered material has been placed, spread, smoothed and compacted by running equipment over the full width of the placement.

· Surface material depth is as specified.

· Surface Material is spread to the dimensions specified.

· Material is compacted so not displacement occurs under heavy equipment traffic.

· New material transitions to adjacent road surfaces without abrupt changes.

· Surface material meets specifications.

5.6.2 Measurement

Measure the Section 5.7 items listed in the bid schedule according to Section 5.7 and the following as applicable.

Verify material measured by the ton by certified weight tickets.

5.6.3 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section 813 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

Payment will be made under:

Pay Item Pay Unit

5.6(1)Spot Surfacing, Gradation ABCTon
5.6(2)Spot Surfacing, Gradation Railroad BallastTon
5.6(3)Spot Surfacing, Gradation _____Ton
5.6(4)Spot Surfacing, Imported FillCY

5.7 Equipment Rental – Furnish and operate equipment.

5.7.1 Quality Standard

Make equipment available for inspection and approval before use. Furnish the equipment specified in the table below:

Description
Max Age (years)**
Min HP
Min Reach (feet)
Weight (pounds)
Capacity
Attachments
Remarks
Excavator
15
135
20
1 CY
thumb
Similar to Cat 320
Backhoe/loader
15
80
14
15,000
thumb
Similar to Cat 420
Grader
15
140
N/A
30,000
12’ blade
Rippers/ Scarifiers
Similar to cat 12H
Crawler Tractor
15
140
N/A
34,000
U blade or similar

Similar to Cat D 6

Dump Truck - Tandem
15
300
N/A
N/A
15 tons
2 way radio
Dump Truck – tri axle
15
400
N/A
N/A
20 tons
2 way radio
Dump Truck – quad axle
15
500
N/A
N/A
25 tons
2 way radio
Boom mower
15
90
N/A
N/A

4 ft cutter head min.

Vibratory Roller
15
100
N/A
20,000
Min. drum width 5’6”

Similar to Cat CS-533

Low Boy Transporter
15

N/A

Skidder
15
150
N/A
35,000
N/A
Winch w/130’ ¾” cable
Similar to Cat 525

** Note: Equipment older than 15 years, in exceptionally good condition, meeting all current OSHA requirements may be allowed if approved by the Contracting Officer. Contractor shall submit all pertinent information demonstrating the condition, capabilities, and safety of the equipment and the reason for the request.

· Keep equipment clean and free of weed seeds. Keep equipment well maintained, free of leaks, capable of operating at least 90% of the time. Meet all state and federal regulations. Operate equipment with a fully trained, qualified, and competent operator at all times.

· Equipment meets state and federal regulations.

· Operator is trained, qualified and competent.

· Equipment is clean and free of weed seeds.

· Equipment is well-maintained and free of leaks.

C5.7.2 Measurement

Measure the Section 803 items listed in the bid schedule according to Section 801 and the following as applicable.

Round portions of an hour up to the next half hour. Measure time in excess of 40 hours per week at the same rate as the first 40 hours.

Do not measure time for non-operable equipment or equipment dependent on another piece of non-operable equipment.

Pay for moving of equipment at the established hourly rate.

C5.7.3 Payment

The accepted quantities will be paid at the contract price per unit of measurement for the Section C5.6 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

Payment will be made under:

PAY ITEM PAY UNIT

C5.7(1) Equipment, Type ________ Hour

C5.7(2) Excavator Hour

C5.7(3) Backhoe/loader Hour

C5.7(4) Grader Hour

C5.7(5) Crawler Tractor Hour

C5.7(6) Dump Truck, Single Axle Hour

C5.7(7) Dump Truck, Tandem Hour

C5.7(8) Dump Truck, Tri-axle Hour

C5.7(9) Boom Mower Hour

C5.7(10) Vibratory Roller Hour

C5.7(11) Low Boy Hour

C5.7(12) Skidder Hour

C5.12(01) Gate Installation

C5.13(01) Pipe Installation (Install 18” Type II Aluminized 14 ga. CMP)

Install new pipe or replace existing pipe; 18” Corrugated Steel Pipe, Aluminized Type 2, 14 gauge. Provide all labor and materials necessary to install culvert pipe with wall thickness, coating, and diameter shown above and length shown on schedule of work. If replacing existing pipe, removing and hauling existing pipe and any unsuitable material as a result of the pipe removal is considered incidental to this activity code. Culvert installation shall have a minimum of 12” of cover, 1% camber, 6” of bedding material and skewed as directed by COR. Bedding material shall be native material or stone screenings roughly shaped to fit bottom of pipe. The length of bedding shall not exceed the length of the pipe. Ensure that the final installed alignment of entire pipe allows no reverse grades, and does not permit horizontal and vertical alignments to vary from a straight line drawn from center of inlet to center of outlet by more than 2 percent of pipe center length or 1.0 feet, whichever is less. Join pipe sections together with coupling bands according to AASHTO M 36 or M 196. Limit the use of bell and spigot joints to slopes of 10% or less. Limit the use of bands with projections (dimpled) to slopes of 15% or less.

Method of Measurement: Measurement shall be made by the linear foot. Payment shall be made after inspection and acceptance under linear foot pay unit.

SECTION C-6

SPECIFIC TASKS OVERVIEW

TECHNICAL SPECIFICATIONS FOR ROAD MAINTENANCE

The Road Maintenance Schedule specifies the road number and required maintenance activity for each road. Adjustments to these schedules may be made in accordance with applicable FAR clauses. Any such adjustments require prior written documentation from the Contracting Officer.

Soil Moisture Conditions and Temperatures

Suitable moisture conditions for surface blading shall be within the range of five (5%) percent to fifteen (15%) percent by weight. Unless authorized, no surface blading may be performed while the moisture content is outside this range.

No grading or other maintenance operations shall be performed during periods of freeze/thaw or when the ground is frozen.

Aggregate Materials

Aggregate surfacing, if included as a pay item, shall be crushed stone with gradations being obtained by crushing, screening and mixing as necessary. Aggregates shall meet the requirements of NCDOT ABC or NCDOT ABC (M). Aggregate Base Course and shall meet all requirements for gradation, hardness, and durability. Certifications of Compliance is required from aggregate suppliers.

Maintenance and Control of Traffic

For all items of work provide safety signage, barricades, lane closures, flaggers, and other traffic control devices appropriate for the location of the work. Take all necessary precautions for the protection of workers and the public. At a minimum, erect warning signs in advance of any place on the project where operations may interfere with the use of the road or trail by traffic. The minimum may only be used on closed roads where public traffic is not expected, but administrative traffic or pedestrian use is possible. On any open road, more comprehensive warnings and traffic control is required. Maximum delay of any traffic on open roads is 10 minutes. See also, Section C-1.2.2.

Erosion and Sedimentation Control

If the work of the contract creates potential for soil erosion or silt migration over areas of mature vegetation or natural areas the contractor will be responsible for providing silt fence, straw bales or other suitable containment and will also be required to seed and mulch bare ground areas. Such works includes, but is not limited to culvert cleaning, excess dirt generation from ditch transition cleaning, and disposal of slide or silt trap material. This does not include the newly graded ditch line.

Blading Aggregate Surfaced and Non-Surfaced Roads

Scarify sections of roads where numerous or severe deep defects have developed. Scarification depth shall be to a depth of 6 inches or to the bottom of the defect, whichever is less.

All suitable dislodged aggregate shall be smoothly spread over the entire traveled way to produce proper cross slope or crown. (1/4” to 1/2” per foot of width).

All suitable aggregate which has been worked onto road shoulders by traffic or maintenance activities shall be reclaimed onto the traveled way. A definite, continuous, and smooth line between aggregate surface and road shoulder shall be obtained. Grass, pine needle, or leaf litter shall be evenly spread within the traveled way after sifting out the surface aggregate. Excessive amounts of grass or leaf litter may be evenly spread along the shoulder if approved by the Project Inspector prior to placement. Excessive amounts of grass or leaf litter containing aggregate may be placed in areas designated by the COR. Berming of litter and litter balls containing aggregate along the fill side shoulder will not be allowed. The contractor shall make as many passes as necessary to assure that the aggregate is sifted out of the grass and leaf litter.

The Forest Service may supply aggregate to be placed by tailgate spreading at any time and in any amount. Finish blading by the contractor is required when aggregate is hauled and spread ahead of the contractor’s blading operations. No additional compensation will be allowed for finish grading government-furnished aggregate as long as the material is deposited by tailgating ahead of the blading operation.

Dislodged rocks of more than 3” in dimension will be removed from the traveled way. EXCEPTION: On non-surfaced roads, where the traveled way material is made up of a substantial amount of rocks over three inches, the contractor will remove those rocks that are greater than 25% larger than the typical stone size on the road. In no case will rocks over 6” be allowed to remain.

If erosion has removed gradable material to the extent that there is not sufficient material within 300 feet to provide the surface smoothness or cross-section specified, notify the Project Inspector prior to proceeding. The inspector or COR may allow a modified cross-section and/or surface smoothness that effectively utilizes available material. The Contractor will not be held responsible for substandard work that results from the lack of suitable material.

Undercutting of road surface at the shoulder will not be allowed.

Blading operations shall include removing all foreign material and debris from bridge decks without allowing any material to fall into watercourses, below. It includes sweeping sand and fines from the bridge decks and depositing the removed material in a location along the roadway that will not allow it to enter waterways or stream courses.

All traveled way widths shall be perpetuated as existing. Dips and swales within the traveled way designed to control surface drainage shall be maintained.

Cleaning and Reshaping Ditches

All ditches shall be maintained in their original location to the shape and grade required to ensure roadway drainage. Drainage structures and road appurtenances shall not be damaged during this operation. Handwork required to properly connect ditch flow to drainage structure inlets is considered a part of this activity. Cleaning lead-off ditches to drain is included in this item of work. Cleaning silt traps that service the roadside ditch(es) or lead-off ditch(es) is included in this work. Restore silt traps to their original dimensions and depth.

If erosion or other existing condition, has removed gradable material to the extent that the specified ditch depth or cross section cannot be maintained, notify the Project Inspector prior to proceeding. The inspector or COR may allow a modified cross-section and/or ditch depth that effectively utilizes available material. The Contractor will not be held responsible for substandard work that results from the lack of suitable material.

All suitable material having the same character as the road surface excavated through ditch cleaning shall be reclaimed and used within the traveled way. Unsuitable material from ditches or silt traps shall be spread along road shoulders, in depressions, or on fill slopes in a manner which will not affect watercourses, traveled way or shoulders. Unless otherwise directed, required to meet culvert inverts, or required to maintain positive flow of water, ditches shall be cleaned to a depth of 1 foot (12”) below the shoulder of the road and the slope of the ditch from the road shoulder to the bottom of the ditch is 2:1 or flatter. Deeper ditches may be required to maintain positive drainage or to match culvert entrances. No debris from ditches shall remain in or around culvert entrances.

Cleaning Culverts and Tail Ditches

All culverts within the work limits shown in Exhibit B shall be inspected for dirt, silt, muck, debris and vegetative matter and cleaned to ensure an un-obstructed flow of water.

Culverts shall be cleaned throughout its length so that no more than 2” of debris is left in any culvert of 36” or less diameter. Culverts larger than 36” shall be cleaned of debris so that no more than 1/8 the diameter of the culvert is blocked.

Tail ditches at culvert outlets shall be cleaned, to their original length or to daylight if feasible, to ensure unrestricted adequate flow from culvert outlets. Clean silt traps that service the tail ditches to their original dimensions and depth. Unsuitable material from ditches or silt traps shall be spread in depressions or on fill slopes in a manner which will not affect watercourses or the roadway.

SECTION C-7

PUBLICATIONS AND CITED STANDARDS

The following publications are included in this specification by reference:

Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03) (https://flh.fhwa.dot.gov/resources/specs/fp-03/fp-03usc.pdf) as amended by the US Forest Service and the National Forests in North Carolina. In the case of conflict between the standard specifications and the specifications included herein, the specifications included herein will govern.

Graphic Definitions and Representations of Road Terms image1.wmf