1042_culvert_package_Map_Drawings_Specs.pdf
PDF 1 MB Posted
- Attached to
- CHATTAHOOCHEE-OCONEE NATIONAL FORESTS -Oconee Ranger District Culvert Replacement Federal contract opportunity
- Solicitation number
- AG-435H-S-17-0011
About this file
Maps Drawings Specs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFQ_ORD_FS_Road_1042_Culvert_Replacement.pdf | ||
| RETURN_PACKAGE_ORD_FS_Road_1042_Culvert_Replacement_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CHATTAHOOCHEE – OCONEE NATIONAL FOREST
OCONEE RANGER DISTRICT
NOTE ROAD
FS 1042
FS 1042
Forest Service
Specified Road Reconstruction
F.S. Road 1042
0+00 Begin project in accordance with typical sections and
FS Specifications.
Begin 2” #4 stone
1+00 Remove and replace existing CSP with new CSP 106” x 83”x 46’ per drawings.
(96” arched)
Place 60 tons Class III rip rap placed on inlet and outlet.
Clear downstream of any debris for 75’.
2+00 Stop stone
End Project
GENERAL NOTES
1. The basic road width for the reconstruction of this road is 12 feet. Basic ROW clearing is 30 feet. All debris (new and old) within the clearing limits will be scattered outside of clearing limits.
2. All disturbed soils shall be seeded and mulched. Mulch will not be required where aggregate is placed.
3. All pipe removed will be removed from Forest Service property.
4. Debris on the downstream end of the pipe will be cleared for 75 feet, price included with linear grading.
Table of Contents
Table of Contents ......................................................................... Error! Bookmark not defined.
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
155 - Schedules for Construction Contracts
155 Delete
202 - Additional Clearing and Grubbing
202.04 Selective Clearing
203 - Removal of Structures and Obstructions
203.05 Disposing of Material
204 - Excavation and Embankment
204.11 Compaction
209 - Structure Excavation and Backfill
209.11 Compacting
Table 209-1 Sampling and Testing Requirements
212 - Linear Grading
308 - Minor Crushed Aggregate
602 - Culverts and Drains
602.03 General
625 - Turf Establishment ............................................................. Error! Bookmark not defined.
625 - Turf Establishment
650 - Road Closure Devices
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
http://www.nist.gov/
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-
96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
Exact time and location of spill including a description of the area involved.
Containment procedures.
Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
202 - Additional Clearing and Grubbing
202.04_1005_us_08_01_2005
202.04 Selective Clearing.
Dead trees over 6 inches in diameter measured at 12 inches above the ground that lean toward the road and are tall enough to reach the roadbed are designated for cutting.
When marked in advance, remove hazard trees or unstable live trees over 6 inches in diameter measured at 12 inches above the ground that lean toward the road and are tall enough to reach the roadbed.
203 - Removal of Structures and Obstructions
203.05_nat_us_02_18_2005
203.05 Disposing of Material.
Add the following:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees.
Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches.
Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
204 - Excavation and Embankment
204.11_nat_us_04_11_2005
204.11 Compaction.
Delete the first paragraph and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d) or (e) no sieve test is required.
Add the following compaction methods:
(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
(e) Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
209 - Structure Excavation and Backfill
209.11_nat_us_02_24_2005
209.11 Compacting.
Delete the subsection and add the following:
Compact backfill using designated compaction method A, B, or C:
Method A. Ensure that backfill density exceeds the density of the surrounding embankment.
Method B. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each layer using appropriate compaction equipment until visual displacement ceases. For compaction under sections 252, 254, 255, 257, 258 and 262 compact with a vibratory steel wheeled roller with a mass of at least 8 tons.
Method C. Determine optimum moisture content and maximum density according to
AASHTO T 99 method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact material placed in all layers to at least 95 percent of the maximum density. Determine the in place density and moisture content according to
AASHTO T 310 or other approved test procedures.
Table 209-1 Sampling and Testing Requirements
(2) Compaction methods (A) and (B) do not require AASHTO T-99 or T-310 test methods for foundation fill.
212 - Linear Grading
212.00_nat_us_05_19_2005
Delete the entire specification and replace it with the following:
Description
212.01 This work consists of clearing and grubbing, excavation and embankment, and erosion control to construct roadways and associated features.
Construction Requirements
212.02 Clearing & Disposal. Protect construction stakes and construction control markers.
Remove or treat all trees, snags, downed timber, brush, and stumps within the clearing limits.
Immediately remove slash deposited in stream courses.
Fell all dead trees that are outside the clearing limits and that lean toward the road and are tall enough to reach the roadbed.
Leave stump heights less than 12 inches or one-third of the stump diameter; whichever is greater, measured on the side adjacent to the highest ground. Leave felled trees outside the clearing limits in place, and treat them no further unless otherwise designated.
Utilization standards for merchantable timber are listed below. Fall and buck merchantable material into lengths not to exceed _________ feet. Pieces (logs) will be considered as meeting utilization standards when such pieces would have met Utilization Standards if bucking lengths were varied to include such material.
Minimum Utilization Standards
Diameter (Inside Bark)
Length at Small End
8 feet _____________ inches 33-1/3 Net Scale in % of Gross 2 Cubic Feet
Do not cut vegetation less than 3 feet in height and less than 3 inches in diameter that is within the clearing limits but beyond the roadway and not in a decking area and that does not interfere with sight distance along the road.
Merchantable Timber
Insert appropriate treatment method from 201.
Unmerchantable Timber and Large Construction Slash
Insert appropriate treatment method from 203.
212.03 Pioneering. Do not undercut the final back slope during pioneering operations. Deposit material inside the roadbed limits. Do not restrict drainage.
212.04 Grubbing. Within the clearing limits remove stumps with less than 6 inches of cover.
212.05 Excavation & Embankment. Construct the roadway to the required template. Protect backslopes from being undercut. Embankment may be placed by side casting and end dumping.
Locate and use borrow material, and remove and treat unsuitable or excess material.
Place rocks that are too large to be incorporated in the embankment outside the traveled way on the downhill side so that they will not roll, obstruct drainage, or hinder roadbed use and maintenance.
Leave slopes that are to be seeded in a roughened condition.
Use a crawler tractor with a dozer blade to shape and finish the roadbed. Provide for drainage of surface water, unless otherwise designated. Do not permit individual rocks in the roadbed to protrude more than 4 inches above the subgrade. A motor grader finish is not required.
Do not encroach on stream channels, wetlands, or extend beyond right-of-way or easement limits. Do not make alignment or profile grade adjustments that adversely affect drainage.
Construct the roadbed within the following grading tolerances:
(a) Alignment (centerline). Alignment may be shifted a maximum of 10 feet left or right of the planned centerline. Curve radii may be reduced by up to 50 percent. Do not construct curves with radii less than 100 feet. Compound curves are permitted. Traveled way tolerance is (+) 2 feet unless otherwise designated.
(b) Profile grade. Profile grade may be shifted a maximum of 5 feet up or down from the plan elevation provided the new grade tangent does not vary more than 2 percent from the plan grade tangent. Connect revised forward and back grade tangents with a uniform vertical curve consistent with the design.
212.06 Drainage. Install culverts and other drainage structures according to Section 602 and
Section 209.
212.07 Erosion Control. Install erosion control measures and seeding according to the drawings and Section 625.
212.08 Acceptance. Linear grading will be evaluated under Subsections 106.02 and 106.04.
Clearing and slash and timber treatment will be evaluated under Sections 201 and 203.
Measurement
212.09 Measure the Section 212 items listed in the bid schedule according to Subsection
109.02 and the following.
Do not measure changes in the clearing and grubbing quantity caused by alignment adjustments under Subsection 212.04.
Payment
212.10 The accepted quantities, measured as provided in Subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 212 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See
Subsection 109.05.
308 - Minor Crushed Aggregate
308.00_01_us_10_11_2006
Delete section 308 in its entirety and replace with the following:
Description
308.01 This work consists of placing Government furnished aggregate or furnishing and placing crushed aggregate for bedding, backfill and roadway aggregate course.
Material
308.02 Conform to the following Subsections:
Crushed aggregate 703.06
Water 725.01
Construction Requirements
308.03 Preparing Surface. Prepare the roadway surface on which aggregate course is placed as shown on the plans.
308.04 Placing Crushed Aggregate.
(a) Roadway aggregate. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.
Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 308.05(a) before placing the next layer.
(b) Bedding and backfill aggregate. Place and shape the mixture in layers that, when compacted, do not exceed 6 inches in depth.
308.05 Compacting and Finishing Crushed Aggregate.
(a) Roadway aggregate. Compact using the methods below, specified in the Schedule of
Items.
(1) Method 1. Operate equipment over the full width of spread aggregate.
(2) Method 2. Compact the aggregate by operating compaction equipment over the total width until visible deformation ceases. A minimum of three complete roller passes shall be made at a moisture content suitable for compaction.
(b) Bedding and backfill aggregate. Compact in 6 inch lifts by using a Forest Service approved mechanical compactor until no visible deformation is observed over the entire area of aggregate.
308.06 Acceptance. Crushed aggregate will be evaluated under Subsections 106.02 and
106.03. Furnish a production certification including gradation and quality properties for each source.
Construction of roadway aggregate courses will be evaluated under Subsections 106.02 and
106.04. Method 2 compaction will be evaluated under Section 106.04.
Placement of bedding and backfill aggregate will be evaluated under Subsection 106.02 and
Section 209.
Preparation of the surfaces on which crushed aggregate is placed will be evaluated under
Section 303 and 209 as applicable.
308.07 Measure the Section 308 items listed in the bid schedule according to Subsection
109.02 and the following as applicable.
Measure crushed aggregate by the cubic yard in-place on the road.
Measure width horizontally to include the top of aggregate width including designed widenings. Measure the length horizontally along the centerline of the roadway.
Payment
308.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 308 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
308.05_0803_us_03_20_2012
308.05 Compacting and Finishing Crushed Aggregate.
Delete second paragraph and add the following:
(1) Method 1. Compact each layer according to Subsection 204.11. Roll from the sides to the center, parallel to the centerline or the road. Along the curbs, headers, and walls, and all places not accessible to the roller. Compact the material with approved tampers until no more visible displacement, using a minimum of three passes.
602 - Culverts and Drains
602.03_nat_us_09_06_2005
602.03 General.
Add the following:
Ensure that the final installed alignment of all pipe allows no reverse grades, and does not permit horizontal and vertical alignments to vary from a straight line drawn from center of inlet to center of outlet by more than 2 percent of pipe center length or 1.0 feet, whichever is less.
625.00_0803_us_04_07_2009
625 - Turf Establishment
625.06 Fertilizing
(a) Dry method or (b) Hydraulic method: Add the following
Fertilzer shall be uniformly applied at the rate of 800 lbs per ac and shall have
A chemical analysis of 10% Nitrogen, 10% Phosphorus, 10% Potassium
625.07 Seeding (a) Dry method
Remove the last sentence “Lightly compact the seedbed within 24 hours after seeding.”
625.07 Seeding
“The seeding season shall be from January 1st to December 31st.
Seed and fertilizer shall be applied at the rates for one of the seeding periods as follows:
The clover shall be inoculated.
625.08 Mulching
Add the following:
Mulch shall be applied at the foll
Modified from Table 6-A (Seeding Mixtures for Erosion Control Plantings); Georgia Best Management Practices
For all seed mixes, planting depth <1/4 inch. Seeding rates are for broadcast seeding.
Fall Plantings
Seeding Rate Timing Fertilizer
Source Species lb./acre Peidmont
Pounds
(10-10-10) Comments
Crimson clover 15 bulk
Hairy Vetch 15 bulk
Wheat 60 bulk
Arrowleaf or crimson clover 15 bulk
Perennial ryegrass 15 bulk
Wheat 40 bulk
White clover (Dutch or Ladino) 5 bulk
Red clover 10 bulk
Perennial ryegrass 15 bulk
Annual rye 30 bulk
Wheat 30 bulk
Spring Plantings
Perennial ryegrass 20 bulk
Partridge pea 2 PLS
Bahiagrass 25 bulk
Brown Top Millet 25 bulk
Spring oats or brown top millet 30 /25 bulk
Switchgrass 'Alamo' 3 PLS
Big bluestem 'KY ecotype' or 'Kaw' 4 PLS
Indiangrass 'Americus' or 'KY ecotype' 4 PLS
Well drained clayey or loamy soils. Inoculate clover.
Tolerates lower soil pH.
500 Well drained sandy or loamy soils. Inoculate clover. Use annual rye when possible.
500 Well drained clayey or loamy soils. Perennial clover can persist for several years. Inoculate clover seed.
Maintaining pH above 6.0 is critical.
GA BMP
GA BMP
GA BMP Sept. 1 to Nov. 1
Sept. 1 to Nov. 1
Sept. 1 to Nov. 1
**For areas with high soil erosion concern. Low maintenance, reseeding annuals.
**For areas with high soil erosion concern.
Perennial cover with cover crop, seeding depth <1/4"Alternative with natives
April 1 to June 15 or dormant season from Dec. 1 thru
Feb.
GA BMP April 15 to July 1 500
GA BMP Feb. 15 to April 1 500 owing rates:
Hay or straw @ the rate of 4,000 pounds per acr, wood cellulose @ the rate of 1500 pounds per acre.
650 - Road Closure Devices
650.00_nat_us_06_28_2007
Description
650.01 Work. Furnish and install, or install only, road closure devices using fabricated gates and accessories, combination post and rail barriers, concrete barriers, earth mound barriers, and other devices.
Materials
650.02 Requirements. Furnish materials to be used in fabricating gates and barriers. Ensure that all hardware is galvanized in accordance with AASHTO M 232 and meets the requirements of ASTM A 307. Furnish plain or cut washers that are American Standard Washers.
Furnish timber posts, rails, and lumber that meet the requirements of AASHTO M 168. Provide timber of the species and type, and rate of preservative treatment.
Furnish concrete that meets the requirements of Subsection 601.03, method B or C.
Construct earth mound barriers from excavated material adjacent to the barrier location, or from other designated locations.
Construction
650.03 Performance. Place road closure devices at designated locations. Construct all devices to the required dimensions. In assembling gates, perform required welding in accordance with the best modern practice and the applicable requirements of AWS D1.1.
After assembly, clean non-galvanized steel pipe gates and paint them with one coat of zinc-rich primer and two coats of exterior enamel of the required type and color.
Set all posts vertically and embed them to the required depth. Place concrete for embedment against undisturbed earth within an excavation sized to achieve the embedment dimensions.
Compact the backfill in 6 inch layers to finished grade.
Furnish and install all signs and/or reflective warning markers accessory to the road closure device.
650.04 Acceptance. Construction of road closure devices will be evaluated under Subsections
106.02 and 106.04.
650.05 Measure the items listed in the bid schedule according to Subsection 109.02.
Payment
650.06 The accepted quantities, measured as provided in Subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 650 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See
Subsection 109.05.
718 - Traffic Signing and Marking Material
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
File details come from the government source that posted it. Updated .