Frick Creek additional SPS.docx

DOCX document 21 KB Posted

Attached to
Frick Creek Culvert Replacement, Chattahoochee National Forest Federal contract opportunity
Solicitation number
AG-435H-S-13-0019
Issued by
Department of Agriculture Forest Service R8-Southern Region

About this file

Additional Supplemental Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Frick Creek Culvert Replacement, Chattahoochee National Forest, newest first.
File Type Posted
schedule of items - rev 7-25-2013.xlsx XLSX spreadsheet
frickcreek drawings - rev 7-25-2013.pdf PDF
FRICK CREEK sup dwg.pdf PDF
Amdt 1.pdf PDF
Seeding Tables.pdf PDF
Frick_Ck_Prebid_attendees.pdf PDF
Bid Bond_SF 24.pdf PDF
Wage Determination.docx DOCX document
Frick creek final_drawings.pdf PDF
FrickCreek_SPS.pdf PDF
Technical Proposal Format.docx DOCX document
AG-435H-S-13-0019.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Frick Creek Culvert Replacement Additional Supplemental Specifications added July 25, 2013 Contents

209 - Structure Excavation and Backfill1
209.11 Compacting.1
625 - Turf Establishment1
625.05 Fertilizing1
625.07 Seeding1
625.08 Mulching,2
633 - Permanent Traffic Control2
633.02 Material.2
633.03 General.2
633.05 Panels.2

209 - Structure Excavation and Backfill 209.00_nat_us_03_24_2008

209.11 Compacting.

Delete the subsection and add the following:

Compact backfill using designated compaction method A, B, or C:

Method A. Ensure that backfill density exceeds the density of the surrounding embankment.

Method B. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each layer using appropriate compaction equipment until visual displacement ceases. For compaction under sections 252, 254, 255, 257, 258 and 262 compact with a vibratory steel wheeled roller with a mass of at least 8 tons.

Method C. Determine optimum moisture content and maximum density according to AASHTO T 99 method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact material placed in all layers to at least 95 percent of the maximum density. Determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.

625 - Turf Establishment

625.05 Fertilizing

(a) Dry method or (b) Hydraulic method Add the following:

Fertilizer shall be uniformly applied at the rate of 800 lbs. per acre and shall have a chemical analysis of 10% Nitrogen, 10% Phosphorus, and 10% Potassium.

625.07 Seeding

Seed shall be applied at the rates for both of the Methods for the seeding periods according to accompanying tables.

625.08 Mulching, Delete the last two sentences in the first paragraph

633 - Permanent Traffic Control 633.02_nat_us_03_03_2005

633.02 Material.

Add the following subsections

Protective Overlay Film
718.02
Edge Film
718.02

633.03_nat_us_03_03_2005

633.03 General.

Delete the subsection and add the following:

Furnish traffic control devices and guide signs according to the MUTCD, approved USDA-FS and state supplements, the current edition of USDA-FS EM-7100-15 Sign and Poster Guidelines for the Forest Service, and Standard Highway Signs published by FHWA. Submit the sign list for approval before ordering.

633.05_nat_us_03_03_2005

633.05 Panels.

Add the following:

Apply protective overlay film and top edge film as required and according to with manufacturer’s recommendations.

Delete the sentence: “Use antitheft fasteners where possible” in the fifth paragraph and replace it with the following: “For each sign panel use at least one antitheft fastener.”