J-3_Supplemental_Specifications.pdf

PDF 1 MB Posted

Attached to
Klahowya Campground Water System Improvements Federal contract opportunity
Solicitation number
AG-05G2-S-17-0015
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

J-3 Supplemental Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Klahowya Campground Water System Improvements, newest first.
File Type Posted
Amendment_003.pdf PDF
Amendment_No_002.pdf PDF
Amendment_No_001.pdf PDF
J-2_List_of_Specifications.pdf PDF
J-1_Acronyms_and_Definitions.pdf PDF
J-4_Klahowya_CG_Water_System_Improvements_Drawings.pdf PDF
Sol_No_AG-05G2-S-17-0016.pdf PDF
J-7_Experience_Questionnaire.pdf PDF
J-5_Wage_Determination_WA170047_0310201.pdf PDF
J-6_Fire_Plan.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

KLAHOWYA CAMPGROUND TABLE OF CONTENTS

WATER SYSTEM IMPROVEMENTS

1 July, 2015 TABLE OF CONTENTS-1

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

011100 – SUMMARY

012200 – UNIT PRICES

013113 – PROJECT COMMUNICATION AND COORDINATION

013119 – PROJECT MEETINGS

013215 – CONSTRUCTION SCHEDULES

013310 – SUBMITTAL PROCEDURES

013323 – SHOP DRAWINGS

014000 – QUALITY REQUIREMENTS

014523 – TESTING LABORATORY AND INSPECTION SERVICES

015719 – ENVIRONMENTAL POLLUTION CONTROL

016100 – BASIC PRODUCT REQUIREMENTS

016200 – SUBSTITUTION AND PRODUCT OPTIONS

016600 – PRODUCT STORAGE AND HANDLING

017123 – FIELD LAYOUT

017410 – CLEANING

017419 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 – CLOSEOUT PROCEDURES

017800 – CLOSEOUT SUBMITTALS

DIVISION 02 – EXISTING CONDITIONS

024116 – STRUCTURE DECONSTRUCTION

DIVISION 03 – CONCRETE

033000 – CAST-IN-PLACE CONCRETE

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

062013 – EXTERIOR FINISH CARPENTRY

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

072100 – BUILDING INSULATION

073130 – SYNTHETIC ROOF SHAKES

074000 – METAL ROOFING

1 July, 2015 TABLE OF CONTENTS-2

076100 – FLASHING AND SHEET METAL

079200 – JOINT SEALANTS

DIVISION 08 – OPENINGS

081113 – HOLLOW METAL DOORS AND FRAMES

083323 – OVERHEAD COILING DOORS

DIVISION 09 – FINISHES

099113 – INTERIOR EXTERIOR PAINTING

DIVISION 11 – EQUIPMENT

110500 – EQUIPMENT GENERAL REQUIREMENTS

DIVISION 22 – PLUMBING

221100 – SITE WATER SYSTEM PUMPS

DIVISION 26 – ELECTRICAL

260010 – BASIC ELECTRICAL REQUIREMENTS

260500 – COMMON WORK RESULTS

260526 – GROUNDING

262000 – LOW VOLTAGE ELECTRICAL TRANSMISSION

269000 – INTEGRATION & CONTROLS

DIVISION 31 – EARTHWORK

310516 – AGGREGATES FOR EARTHWORK

311000 – SITE CLEARING

312213 – SITE GRADING

312316 – EXCAVATION

312317 – TRENCHING

312323 – FILL

312513 – EROSION CONTROLS

DIVISION 33 – UTILITIES

331116 – SITE WATER UTILITY DISTRIBUTION PIPING

331216 – WATER UTILITY DISTRIBUTION VALVES

331233 – WATER METERS

331300 – DISINFECTING WATER UTILITY DISTRIBUTION

1 July, 2015 TABLE OF CONTENTS-3

331313 – WATER STORAGE TANK DISINFECTION

331613 – ABOVE GROUND WATER UTILITY STORAGE TANK

332100 – WATER SUPPLY WELLS

KLAHOWYA CAMPGROUND SECTION 011100

WATER SYSTEM IMPROVEMENTS SUMMARY

1 July, 2015 011100-1

PART 1 - GENERAL

1.01 SUMMARY

A. Section includes:

1. Replacement of approximately 5,378 linear feet of water main and appurtenances, associated site work, development of a new groundwater source well and booster pump/storage facility, installation of a new vault toilet building and replacement of the existing comfort station roof material.

2. Associated site work includes clearing, grubbing, removal of obstructions, excavation, trenching, filling, grading, paving, and restoration/cleanup.

3. Demolition and abandonment of existing facilities. Existing facilities to be demolished include an existing vault toilet facility, including existing tank, removal of various water faucets, valves, standpipes, abandonment of existing water mains, decommissioning of existing groundwater well, removal of existing comfort station roof and removal of existing wood-stave water storage reservoir.

B. Related Sections:

1. Section 013113 - Project Communication and Coordination

2. Section 013215 - Construction Schedules

3. Section 013310 - Submittal Procedures

4. Section 017700 - Closeout Procedures

1.02 DESCRIPTION

A. Unless otherwise indicated, work and responsibilities include, but are not limited to the following:

1. Employing specialists having experience in similar construction projects and in sufficient numbers for supervision and coordination of construction activities, including those by subcontractors and suppliers, and as required to maintain the Construction Progress Schedule and complete the portions of the work by the dates indicated in the Construction Progress Schedule.

2. Providing and paying for labor, materials, equipment, tools, machines, facilities, and services necessary for proper execution, supervision and completion of work.

3. Performing initial review and certification that submittals are complete and comply with requirements of the Contract Documents before submitting to the Contracting Officer (CO) for review.

4. Giving required notices.

5. Using new materials, except as noted.

6. Obtaining and paying for required permits, fees and notices if required for construction completion.

1.03 MISCELLANEOUS EXPLANATIONS - INTENT

A. Intent of Language Used in this Project Manual:

1. "Project Manual" means the volume usually assembled for the Work which may include the Proposal requirements, contractual conditions, general requirements and technical specifications.

2. The Project Manual is part of the Contract Documents between Government and Contractor and is therefore written addressing the Contractor. Although references to subcontractors are made occasionally, it is not the intent of the Project Manual to divide the work into subcontracts; this is the responsibility of the Contractor.

1 July, 2015 011100-2

3. The following information is provided to facilitate Project Manual comprehension, format, language, implications, conventions, and content. This information does not modify the substance of any requirements.

a. Project Manual is divided into divisions and sections for convenience. Division titles are not intended to fully describe the work of each division or section, and are not an integral part of the text specifying requirements.

b. Division and section numbers listed in Table of Contents, and items of work included in each section, conform in general to the Construction Specifications Institute’s "Masterformat - Master List of Numbers and Titles for the Construction Industry,”. Numbering of sections is merely for identification and may not be consecutive. Verify contents to be sure manual is complete in accordance with Table of Contents.

c. Except for sections in Division 00, Proposal and Contract Requirements, and certain Division 01 Sections, sections are usually subdivided into three “parts” for uniformity and convenience (Part 1 - General; Part 2 - Products; and Part 3 - Execution).

d. Section pages are numbered independently for each section. Section numbers and page numbers appear at the right bottom of each page of most sections.

e. Trade Associations and General Standard Abbreviations: Generally understood abbreviations may be used in text.

f. The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1) Imperative mood and streamlined language are generally used in the

Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2) Specification requirements shall be performed by Contractor unless specifically stated otherwise.

4. Reference to Specifications Sections in Division 01: Where General Conditions provisions and Modifications thereto relate generally to work of Contractor and subcontractors as project administrative requirements, procedural requirements, temporary facilities, and the like, these provisions may be amplified by specifications sections in Division 01, “General Requirements.”

5. Government's Representative:

a. The Contracting Officer (CO) is the Government's Representative for contractual and administrative procedures as well as technical matters.

b. The Government’s On-Site Representative or the Contracting Officer’s

Representative (COR) is responsible for day-to-day communications and on-site observation.

B. Intent of Drawings:

1. The Drawings are the graphic and pictorial portions of the Contract Documents showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules and diagrams. Drawings are in part diagrammatic and do not necessarily show complete details of construction, work or materials, performance or installation. They do not necessarily show how construction details, other items or work, fixtures, and equipment may affect any particular installation. Ascertain and correlate the work to bring the parts together into a satisfactory and completed whole.

2. Drawings do not show exact characteristics of the Work, piping or necessary number of fittings. The Drawings indicate only such details as are necessary to show intent of the work. In order to illustrate the Work, the CO may furnish additional Drawings, 1 July, 2015 011100-3 explanations and clarifications consistent with the original Drawings, purpose and intent of the Contract. Conform Work to such Drawings and explanations. The furnishing of such additional Drawings, explanations or clarifications is for the convenience of the Contractor and shall not entitle the Contractor to an increase in the Contract time or Contract Sum.

3. Furnish and install work not covered under any heading, Section, branch, class or trade of the Project Manual, but shown on or reasonably inferable from the Drawings.

This includes work necessary to produce the intended results.

4. Do not scale drawings. Dimensional accuracy is not guaranteed, and field verification of dimensions, locations, and levels to suit field conditions is required.

C. First Class Workmanship is expected.

1. Prior to installing an item or material, verify that receiving surfaces are plumb, level, true to line, and straight to the degree necessary to achieve tolerances specified or required. Perform without extra cost shimming, blocking, grinding, or patching required to make such surfaces plumb, level, true to line and straight.

2. Take care in attention to details and fitting at intersections and junctures of materials.

Joints are to be tight, straight, even, and smooth.

D. Fastening and Connections: Furnish fastenings and connections necessary and adequate to assemble work whether indicated or not. Provide proper assemblage for intended performance of components and assemblies; bonds shall bond properly, fastening shall fasten properly; operable items shall operate smoothly, without sticking or binding, and without “play” or looseness; and the like.

E. Presence of Government's Representatives: Do not construe presence of these persons at the Project Site as assuring compliance with Contract Documents.

F. General Installation Provisions: Provide items, articles, materials, and operations listed, including labor, materials, equipment and incidentals required for their completion.

1. Installer’s Inspection of Conditions:

a. Require the installer of each major unit of work to inspect the substrate to receive work and conditions under which the work is to be performed.

b. The installer shall report unsatisfactory conditions in writing to the Contractor.

c. Do not proceed with the work until unsatisfactory conditions have been corrected in a manner acceptable to the installer. Start of work constitutes acceptance of substrates.

2. Inspection of Items to be Installed:

a. Inspect each item of materials or equipment immediately prior to installation.

b. Reject damaged and defective items.

3. Attachment and Connection:

a. Provide attachment and connection devices and methods for securing work.

Secure work true to line and level, and within recognized industry tolerances.

Allow for expansion and building movement.

b. Provide uniform joint width in exposed work. Arrange joints in exposed work as drawn or to obtain the best visual effect. Refer questionable visual-effect choices to the CO for final decision.

4. Measurements: Check measurements and dimensions of the work, as an integral step of starting each installation.

5. Dimensions and Measurements on Drawings:

a. Dimensions govern.

b. Do not scale.

1 July, 2015 011100-4

c. Check dimensions in the field and verify them with respect to adjacent or incorporated work.

1) Information concerning existing conditions was considered suitable for preparation of the Drawings and is given for Contractor’s convenience. CO and Government do not guarantee accuracy of such conditions.

6. Weather Conditions:

a. Install each unit of work during weather conditions and project status which will ensure the best possible results in coordination with the entire work.

b. Isolate each unit of finished work and protect as necessary to prevent deterioration.

c. Inspection and Tests: Coordinate enclosure of the work with required inspections and tests, so as to minimize the necessity of uncovering work for that purpose.

7. Inspection and Tests: Coordinate enclosure of the work with required inspections and tests, so as to minimize the necessity of uncovering work for that purpose.

1.04 SEQUENCE/PHASING

A. Use any sequence of operations compatible with monthly Progress Schedule, in accordance with Section 013215, Construction Schedules, and following:

1. These documents shall not be interpreted implicitly or explicitly as definition of procedure and sequence of operations. Order as to procedure and sequence of operations are Contractor’s options, consistent with Contract Documents and as approved by Government.

2. Protect existing operations and maintenance functions from disruption during construction of new facilities until new facilities have been occupied and are fully functional. Conduct demolition of existing facilities and site work to be removed in a manner that does not interrupt Government activities. Maintain public access to all areas not actively under construction.

3. Access Road: Schedule to minimize impacts on Government’s use of premises. No temporary roads or access corridors shall be constructed without prior approval.

B. The project site includes an operational United States Department of Agriculture Forest Service (USDA FS) campground. The project includes demolition and replacement of restroom facilities. The Contractor shall schedule the construction work in a phased manner to maintain adequate facilities at all times.

1. Contractor shall schedule Work in a manner conforming to the requirements of this

Construction Sequence. Contractor shall schedule the Work, prepare and submit a critical path schedule in accordance with Section 013215, Construction Schedules.

Contractor may submit for review a proposed alternate sequence that meets the requirements of the project. It shall be the Contractor’s responsibility to locate staging and project trailers in a manner consistent with the phased construction of the site.

2. Contractor shall prepare a Stormwater Pollution Prevention Plan, including a

Temporary Erosion and Sedimentation Control (TESC) plan, and shall construct TESC measures in accordance with Section 312513, Erosion Controls. The stormwater controls shall follow the phasing of construction.

3. Utility construction and demolition of existing facilities shall be scheduled such that services to the occupied campground areas are maintained at all times.

1 July, 2015 011100-5

C. Construction vehicle access shall be via the existing access. Contractor shall provide traffic control in accordance with DOT requirements. A project specific traffic control plan shall be provided to the CO or COR for review and approval prior to commencement of work.

1.05 CONTRACTOR’S USE OF PREMISES

A. Contractor shall have use of the premises as indicated in for execution of the work during the contract time. Schedule and coordinate work in areas indicated as "intermittent work areas" to minimize impacts to Government use.

1. Construction Staging Area: To protect subgrade in areas designated for infiltration facilities, Contractor shall limit parking, staging, temporary offices and stockpiling to areas already paved or otherwise compacted.

2. Coordinate use of Project Site with the CO or COR prior to utilization of area and during the construction phase. Modify or change the staging and parking areas as required.

3. Coordinate staging and parking areas with subcontractors and material suppliers.

4. Protection of existing trees and sensitive vegetation: Take steps to assure protection of trees and vegetation to be retained including “unique species areas”.

B. Assume full responsibility for the protection and safekeeping of products and equipment under this Contract, stored on the Project Site.

C. Move stored products at no cost to the Government, under Contractor’s control, which interfere with operations of the Government or separate contractors.

D. Obtain and pay for the use of additional storage or work areas on or off Project Site as needed for operations.

E. Do not allow storage of flammable liquid or hazardous materials in any of the campground buildings.

F. Procedure in the event unknown hazardous materials are encountered:

1. Immediately stop work and seal off the areas.

2. Immediately report discovery to CO or COR.

G. The contractor may request use of one or more camp sites for overnight occupancy during the project. Requests for site usage should be made to the CO or COR prior to site occupancy.

1.06 EXISTING UTILITIES

A. Utilities of record are shown on the Drawings. Utilities are shown for convenience only. The Government and Government’s representatives assume no responsibility for improper locations or failure to show utility locations on the Drawings. At own expense, immediately repair utilities damaged during construction.

B. Prior to commencing activities which may damage utilities, exercise appropriate care (by use of probes, hand excavation, and the like) to locate and prevent damage to existing utilities and drainfields.

C. Contact locating services as needed to assure utility locations on site and in Right-of-Way.

1 July, 2015 011100-6

1.07 CONFLICTS AND OMISSIONS IN DRAWINGS AND SPECIFICATIONS

A. Contractor shall carefully study and compare the Contract Documents with each other and with information furnished by Government. If, during the performance of the Work, Contractor finds a conflict, error, inconsistency, or omission in the Contract Documents, it shall promptly and before proceeding with the Work affected thereby, report such conflict, error, inconsistency, or omission to the CO and COR in writing.

1. Where conflicts and omissions have not been brought to the CO and COR’s attention, it is understood that provisions for the most costly method or methods have been made.

1.08 MISCELLANEOUS

A. Miscellaneous Items include, but are not limited to:

1. Maintaining pedestrian and vehicular access to and around existing facilities. No pioneering roads may be created without prior approval.

2. Not unreasonably encumbering site with materials or equipment.

3. Not loading existing structures with weight that may endanger them.

4. Repairing to original conditions damage to existing paving or adjacent buildings or improvements.

5. Maintaining existing “accessible” routes.

END OF SECTION

KLAHOWYA CAMPGROUND SECTION 012200

WATER SYSTEM IMPROVEMENTS UNIT PRICES

1 July, 2015 012200-1

1.01 SUMMARY

A. Section includes:

1. Administrative and procedural requirements for unit prices.

1.02 DEFINITIONS

A. Unit prices include all necessary material, labor, equipment, services, mobilization, demobilization, safety and tool costs, delay and impact costs, insurance, overhead, profit, and applicable taxes.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Comply with Specifications and standards for each applicable product.

PART 3 - EXECUTION

3.01 UNIT PRICE SCHEDULE

A. Construct Groundwater Source Well (Well #4) – Section 332100:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, the furnishing of all labor, tools, equipment, and material, performing all operations in connection with drilling and installing a functional water supply well in accordance with the project plans and specifications.

B. 4” HDPE DR-9 Water Main - Section 331116:

1. Basis of Measurement: By the Linear foot.

2. Basis of Payment: Includes, but is not limited to, hand trimming, excavation, supplying all necessary pipe and fittings, completion of installation, including bedding and concrete thrust restraints, testing and connection to building service piping and to other installed features.

C. 4” R/S Gate Valve – Section 331216:

1. Basis of Measurement: By the unit (each).

2. Basis of Payment: Basis of Payment: Includes, but is not limited to, supplying all valves and necessary fittings and completion of full installation in accordance with the project plans and specifications, including installation of all valve boxes, markers and accessories.

D. 1” Air & Vacuum Release Valve Assembly – Section 331116:

1. Basis of Measurement: By the unit (each).

2. Basis of Payment: Includes, but is not limited to supplying all necessary labor equipment and materials including valve assembly fittings, specified meter box, saddle, pipe, support post, and all necessary accessories and completion of full operational installation in accordance with the project plans and specifications.

1 July, 2015 012200-2

E. 1” Water Service Connection & Piping – Section 331116:

1. Basis of Measurement: By the unit (each).

2. Basis of Payment: Includes, but is not limited to supplying all necessary labor equipment and materials including, saddle, required fittings, pipe and accessories and completion of full operational installation in accordance with the project plans and specifications.

F. Filling Station Hydrant – Section 331116:

1. Basis of Measurement: By the unit (each).

2. Basis of Payment: Includes, but is not limited to, supplying all necessary labor equipment and materials including, hydrant assembly, all required fittings, pipe, support post, and accessories and completion of full operational installation in accordance with the project plans and specifications. Payment also includes all necessary work required to make hydrant area and location accessible in accordance with Forest Service Outdoor Recreation Accessibility Guidelines.

G. Trench Backfill – Section 310516:

1. Basis of Measurement: By the cubic yard.

2. Basis of Payment: Includes, but is not limited to, supplying backfill material, hauling, stock piling, placing, compacting and testing in accordance with the plans and specifications.

H. Crushed Aggregate Surface Course – Section 310516:

1. Basis of Measurement: By the ton.

2. Basis of Payment: Includes, but is not limited to, supplying crushed surfacing, hauling, stock piling, preparing base, placing, compacting and testing in accordance with the plans and specifications.

I. Crushed Aggregate Base – Section 321204:

1. Basis of Measurement: By the ton.

2. Basis of Payment: Includes, but is not limited to, supplying crushed surfacing, hauling, stock piling, preparing base, placing, compacting and testing in accordance with the plans and specifications.

J. Demo. Existing Water Main Appurtenances and Abandon Existing Main – Section 024116:

1. Basis of Measurement: Lump sum.

2. Basis of Payment: Includes removal of accessories including but not limited to spigots, valves, boxes, drains, exposed piping, and other appurtenances that will not be utilized in the proposed system. Work includes cutting and abandoning buried waterline in place, and removal or decommissioning of other items needed to ensure that they will not create a hazard, or otherwise impede the safety, operation, or maintenance of the system in the future in accordance with the project plans and specifications.

K. Demo. Existing Vault Toilet Station and Appurtenances Including Tank – Section 024116:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, demolition, removal and disposal of all structures, concrete pads/foundations, associated walkways and access paths, pumping, demolition and removal (where indicated) of all tanks, and completion of all filling, grading and native seeding as needed to restore the area in accordance with the plans and specifications.

1 July, 2015 012200-3

L. Demo. Existing Comfort Station Roof – Section 024116:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, demolition, removal and disposal of all roofing material, including gutters and downspouts, and inspection of the roof support structure.

M. Abandon Existing Groundwater Well – Section 024116:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, supplying all labor, equipment and materials necessary to complete the groundwater well abandonment in accordance with the specifications and WAC 173-160-381.

N. Removal of Structures and Obstructions – Section 024116:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, removal and disposal of all structures

(including fixtures, plumbing and electrical connections), concrete pads/foundations, associated walkways and access paths, and completion of all filling, grading and native seeding as needed to restore the area in accordance with the plans and specifications. Work also includes relocation of any barrier logs and rocks as needed in accordance with project plans and specifications.

O. Clearing and Grubbing – Section 311000:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, clearing and grubbing all areas as necessary for the completion of the project in accordance with the plans and specifications.

P. Site Grading – Section 312213:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, all rough and final grading (including filling) necessary for the completion of the project in accordance with the plans and specifications and as necessary to make all filling station hydrants and vault toilet facilities accessible in accordance with Forest Service Outdoor Recreation Accessibility Guidelines.

Q. Gravel Borrow Including Haul – Section 310516:

1. Basis of Measurement: by the cubic yard.

2. Basis of Payment: Includes, but is not limited to, supplying borrow material, hauling, stock piling, placing, compacting grading and seeding in accordance with the plans and specifications.

R. Install Comfort Station Roof – Section 073130:

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, supplying and installing roofing material (approximately 8 squares required), including new gutters, downspouts and splash blocks in accordance with the plans, specifications and the manufacturer’s recommendations.

S. Construct Pump House and Booster Pump Facility – Section (Multiple)

1. Basis of Measurement: Lump Sum.

2. Basis of Payment: Includes, but is not limited to, supplying all required labor, equipment and materials necessary to complete the pump house construction in accordance with the project plans and specifications. This includes completion of the

1 July, 2015 012200-4 pump house building, all required external/internal electrical work and all required internal/external plumbing/mechanical work including piping, appurtenances and electrical work from pump house to new groundwater well. Payment also includes completion of all necessary site grading.

T. Install CXT Vault Toilet Facility, Double Unit – Section 110500:

1. Basis of Measurement: By the unit (each).

2. Basis of Payment: Includes, but is not limited to, supplying all material, completing all necessary site work, setting all necessary tanks and base material, complete facility installation, backfilling and final grading, and all other work necessary for the complete installation of the facility in accordance with the plans and specifications. Payment also includes all necessary work required to make vault toilet location accessible in accordance with Forest Service Outdoor Recreation Accessibility Guidelines.

KLAHOWYA CAMPGROUND SECTION 013113

WATER SYSTEM IMPROVEMENTS PROJECT COMMUNICATIONS AND

COORDINATION

1 July, 2015 013113-1

1.01 SUMMARY

A. Section includes:

1. Procedures and formats for communications.

2. Procedures for coordination of the Work of the Contract.

3. Discrepancies and contract document review.

B. Related Sections:

1. Section 013119 - Project Meetings:

2. Section 013215 - Construction Schedules

3. Section 013310 - Submittal Procedures

4. Section 013323 - Shop Drawings

5. Section 016200 - Substitutions and Product Options

6. Section 016600 - Product Storage and Handling

7. Section 017700 - Closeout Procedures

1.02 COMMUNICATIONS

A. General:

1. Telephone communication and correspondence shall be between Contractor’s

Representative and the CO.

2. Subcontractors shall not contact members of the design team directly unless explicitly agreed to by Contractor and CO. Such contact and discussions shall be documented in writing by the subcontractor and submitted to the CO through the Contractor.

3. Transmit problems or questions in writing using a Request for Information (RFI) form through the Contractor.

4. Incorporate any cost affect this may have on the progress of the Project into the Base Bid. No overtime payments will be authorized, or time delays allowed, for the Contractor or subcontractors to communicate with the CO outside of the Contractor’s normal working hours.

5. On-Site Lines of Authority and Communications: Establish on-site lines of authority and communications including attendance at pre-construction meeting and progress meetings as required by the Governments CO. All on-site lines of authority and communications shall be established through the Governments CO.

B. Emergency Communication:

1. An Emergency List shall be established for use in case of emergencies in off-hours.

a. Identify a person that shall be available to contact during all off-hours with authority to address any emergency situation. Additional names and numbers may be necessary to be provided depending on the trade and activity.

b. Submit the list to the Governments CO, who will include the same information for design team members and Government representatives.

C. Correspondence:

1. Correspondence to and from Contractor shall be routed through the Governments CO.

2. Number correspondence sequentially beginning with Serial Number 001. Include

Government's project title and project number.

D. Request for Information (RFI):

1 July, 2015 013113-2

1. When field conditions or Contract Document contents require clarification or verification by the CO a written RFI in electronic form shall be submitted in conformance with the following:

a. Identify the nature and location of each clarification/verification using a RFI form;

provide as a minimum the following information:

1) Project name and contract number;

2) Date;

3) Date response is required by; allow 5 working days for returning responses. The CO will expedite those RFI’s indicated by the Contractor as being critical to the construction process.

4) RFI number;

5) Subject;

6) Initiator of the question;

7) Indication of costs, if known;

8) Location on site;

9) Contract drawing reference;

10) Contract specification section and paragraph reference;

11) Descriptive text;

12) Contractor suggested options to address the issue;

13) Space for reply on same page as questions; and

14) Single subject matter, 1 item each.

b. Number each RFI sequentially beginning with #001. Only one question per RFI.

2. Route and Copy: RFI’s in same manner as correspondence

1.03 PROGRESS PHOTOGRAPHS

A. Submit photographs with each application for payment, taken not more than 3 days prior to submission of application for payment.

B. Photography Type: Digital; electronic files.

C. Provide photographs of site and construction throughout progress of Work produced by contractor's staff photographer.

D. In addition to periodic, recurring views, take photographs of each of the following events:

1. Completion of site clearing.

2. Excavations in progress.

3. Foundations in progress and upon completion.

4. Final completion, minimum of ten (10) photos.

E. Views:

1. Provide non-aerial photographs from four cardinal views of overall site at each specified time, until Date of Substantial Completion.

2. Provide factual presentation.

3. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

F. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: Via email or posting to Project FTP site.

2. File Naming: Include project identification, date and time of view, and view identification.

1 July, 2015 013113-3

3. Photo CD(s): Provide 1 copy including all photos cumulative to date, with files organized in separate folders by submittal date.

1.04 COOPERATION AND COORDINATION OF WORK

A. General:

1. Coordinate scheduling, submittals, and work of the various sections of Specifications to assure efficient and orderly sequence of installation of construction elements, with provisions for accommodating items to be installed later.

2. Coordinate work between the parts of the Contract Documents to avoid conflicts and omissions. Take special care to coordinate work which is normally indicated in some but not all architectural, mechanical, electrical and other major divisions of the Contract Documents.

B. Coordinate installation of the work and that of subcontractors to ensure compliance with the Contract Documents and to expedite the progress of the Project.

C. Ensure that the work of subcontractors complies with Conditions of the Contract, Division 01

- General Requirements, and the work of other Sections related to their own work. No additional payments or time extensions will be authorized for failure on the part of subcontractors to be familiar with and in compliance with the aforementioned specification divisions and sections.

D. Project Coordination and Scheduling Control: Responsibility for coordination and close adherence to time schedules rests solely with the Contractor who shall maintain coordination and scheduling control at all times:

1. Each subcontractor responsible to the Contractor shall cooperate diligently with the

Contractor in the execution of their work so as to cause no delay in the completion of the Project. This responsibility includes the completion of work in a timely manner and items of equipment connected and fully operating at the time of Substantial Completion of each phase. Each subcontractor shall diligently comply with the following requirements:

a. Cooperate in planning and layout of the work well in advance of operations to properly interface with work of other trades and Government’s separate contractors.

b. Inform other trades of requirements at proper time to prevent delay or revisions.

c. Be informed on the requirements of other trades and check own work for conflicts with the work of other trades.

d. Ensure delivery of materials and performance of work on coordinated schedule with other trades.

e. Attend Pre-Installation conferences as described in Section 013119, Project

Meetings.

2. Ensure that the subcontractors and equipment suppliers are responsible for compatibility and completeness of the installation and operation of the equipment in their respective Specification Sections including conformance with code requirements.

If power, piping, ductwork, or other work required for complete installation is not provided by others to equipment location or is not adequate for complete installation, the subcontractor or equipment supplier shall be responsible for providing the necessary connections.

3. Notify CO in a timely manner of items/issues requiring field verification by CO and subconsultants.

4. Schedule and coordinate any utility shutdowns with CO:

1 July, 2015 013113-4

a. Submit a schedule of equipment and utility shutdowns within 14 days after the Notice to Proceed.

b. Confirm requests for equipment and utility shutdowns in writing to the CO not less than 14 days prior to the proposed date. Include, as a minimum, the following information:

1) Equipment or utility services affected;

2) Reason shutdown is required;

3) Work to be accomplished during the shutdown;

4) Proposed date and time; and

5) Duration of the shutdown.

c. The actual time and date of shutdowns will be subject to approval of the CO.

Shutdowns normally will be scheduled for days, Tuesday through Thursday, or other low intensity use periods.

d. The duration of shutdowns shall be held to a reasonable minimum as determined by the CO.

e. Materials and equipment required for the work to be accomplished during shutdown shall be complete and available on the job for review by the CO 3 days prior to the shutdown, if requested. If Contractor is not adequately prepared, the shutdown will be canceled and rescheduled.

f. Government’s personnel may shut down and restart equipment and utilities. The CO or COR will inspect the installation prior to restarting and will not restart if an unsafe condition exists. Confirm responsibility for shutdown of equipment 7 days prior to the occurrence of the work. In the event Contractor’s work is not completed during the time scheduled for the shutdown, The CO may elect to restart the equipment or utility service. In that event, additional shutdown requirements shall be rescheduled in accordance with the preceding requirements. Restarting shall not be construed as acceptance of the work as complete.

g. Include in the bid all costs associated with equipment and utility shutdowns. The CO will make no extra payment for overtime work, schedule changes or failure to complete utility connections within authorized shutdown periods.

E. Notification and Correction of Defective Work:

1. Before starting a section of work, each contractor and subcontractor shall carefully examine preparatory work that has been executed to receive each contractor’s work.

Check carefully, by whatever means required to ensure that the work and adjacent, related work will finish to proper contours, planes, and levels.

2. Subcontractors shall promptly notify the Contractor of any defects or imperfections in preparatory work which will in any way affect satisfactory completion of the work.

Under no condition shall a section of work proceed prior to preparatory work having been completed, cured, dried, or otherwise made satisfactory to receive such related work.

3. Correction of defective work shall be the responsibility of the Contractor or subcontractor providing the defective work. Correction of work due to underlying defects shall be the responsibility of the Contractor or subcontractor providing work.

F. Intent of Drawings: The work of each contractor and subcontractor shall conform to the intent of the contract drawings. Drawings are partly diagrammatic and do not intend to show in detail all features of work. Each contractor shall carefully review the work to be performed by other trades, compare related drawings and shall thoroughly understand the building conditions affecting their work.

1. Changes required in the work caused by failure to do so shall be at no expense to the

Government.

1 July, 2015 013113-5

G. Interferences and Right-Of-Way:

1. Make proper provisions to avoid interferences.

2. Submit conflicts which cannot be resolved to CO for instructions.

H. Cooperate and coordinate with any other separate contractors and subcontractors under Contract with the Government.

1.05 COORDINATION OF SUBMITTALS

A. Schedule and coordinate submittals specified in Section 013310, Submittal Procedures, and Section 013323, Shop Drawings.

B. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service equipment.

C. Coordinate requests for substitutions to assure compatibility of space, of operating elements, and affect on work of other sections.

1.06 COORDINATION OF SPACE

A. Coordinate use of Project space and sequence of installation of all work which is indicated diagrammatically on Drawings. Follow routings shown as closely as practicable, with due allowance for available physical space; make runs parallel with lines of building. Utilize space efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

B. In finished areas, except as otherwise shown, conceal pipes, ducts, wiring and the like within the construction. Coordinate locations of fixtures and outlets with finish elements.

1.07 COORDINATION OF CONTRACT CLOSEOUT

A. Coordinate completion and cleanup of work by the various trades involved in preparation for Substantial Completion.

B. After Government occupancy of premises, coordinate access to Project Site by the various trades involved for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Government’s activities.

C. Assemble and coordinate closeout submittals specified in Section 017700, Closeout Procedures, and Section 017800, Closeout Submittals.

1.08 DISCREPANCIES AND CONTRACT DOCUMENT REVIEW

A. The intent of the Specifications and Drawings is to describe a complete Project to be constructed in accordance with the Contract Documents. Furnish labor, materials, equipment, tools, transportation, permits, and supplies, and perform the Work required in accordance with the Drawings, Specifications, and other provisions of the Contract Documents.

B. The Contract Documents are complementary. What is required by one part of the Contract Documents shall be binding as if required by all. Anything mentioned in the Specifications

1 July, 2015 013113-6 and not shown on the Drawings, or shown on the Drawings and not mentioned in the Specifications, shall be of like effect as if shown or mentioned in both.

C. Contractor shall carefully study and compare the Contract Documents with each other and with information furnished by the Government. If, during the performance of the Work, Contractor finds a conflict, error, inconsistency, or omission in the Contract Documents, it shall promptly and before proceeding with the Work affected thereby, report in writing such conflict, error, inconsistency, or omission to the CO.

D. Do no Work without applicable Drawings, Specifications, or written modifications, or Shop Drawings where required, unless instructed to do so in writing by the CO. If Contractor performs any construction activity, and it knows or reasonably should have known that any of the Contract Documents contain a conflict, error, inconsistency, or omission, Contractor shall be responsible for the performance and shall bear the cost for its correction.

E. Provide any work or materials, the provision of which is clearly implied and is within the scope of the Contract Documents, even if the Contract Documents do not mention them specifically.

F. Questions regarding interpretation of the requirements of the Contract Documents shall be referred to the CO.

KLAHOWYA CAMPGROUND SECTION 013119

WATER SYSTEM IMPROVEMENTS PROJECT MEETINGS

1 July, 2015 013119-1

1.01 SUMMARY

A. This Section specifies administrative and procedural requirements for project meetings, including, but not limited to, the following:

1. Preconstruction meeting;

2. Progress meetings;

3. Monthly construction schedule meetings;

4. Record Documents update meeting;

5. Coordination meetings;

6. Pre-installation meetings prior to starting certain work;

7. Project closeout meetings.

B. Related Sections:

1. Section 013113 - Project Coordination

2. Section 013215 - Construction Schedules

3. Section 013310 - Submittal Procedures

4. Section 014000 - Quality Requirements

5. Section 017700 - Closeout Procedures

6. Section 017800 - Closeout Submittals

1.02 PRECONSTRUCTION MEETING

A. The Government’s CO will schedule a preconstruction conference before starting construction, at a time convenient to the Contractor and the CO. The conference will be held at the Project Site or another convenient location as selected by the Government’s CO.

B. Attendance is required of the following:

1. CO;

2. COR(s);

3. Contractor’s Superintendent and Project Manager; Contractor’s Quality Control (CQC)

Representative; Contractor’s Safety Coordinator;

4. Major subcontractors invited by the contractor (not required);

5. Others, as requested.

C. Discussion will cover items of significance, including the following:

1. Communication chain and persons authorized to direct changes;

2. The Work;

3. Government’s CO and COR roles;

4. Work hours, sequence, phasing, and occupancy;

5. Procedures and processing:

a. Application for payments;

b. Change Order Proposals (COP);

c. Construction Change Directives (CCD);

d. Change Orders;

e. Requests for Information (RFI);

f. CO Supplemental Instructions (COSI)

g. Field decisions;

h. Submittals;

i. Others as appropriate.

6. Project record documents including review of record documents ("as-builts") on a regular basis during construction;

1 July, 2015 013119-2

7. Contractor and construction access to the site;

8. Construction facilities, and controls;

9. Security procedures;

10. Housekeeping procedures;

11. Utility shutdowns / Outage Request Form;

12. Parking;

13. Equipment deliveries and priorities;

14. Schedule Review;

15. Contractor's Quality Control (CQC) System:

a. CQC Representative;

b. CQC daily report;

16. Hazardous material abatement procedures, if any;

17. Use of Project Site and premises by Forest Service, Park Visitors/Campers, and

Contractor;

18. Construction Waste Management Plan;

19. Others, as appropriate.

D. The CO or COR will:

1. Conduct the meeting to review contract administration requirements.

2. Record, produce, and distribute copies of the minutes to the CO and (General)

Contractor within 7 days of the meeting.

E. The (General) Contractor shall distribute copies to all other contractor attenders.

1.03 PROGRESS MEETINGS

A. For purposes of coordination and scheduling, after start of the work, Contractor’s QC representative, project manager and superintendent and all subcontractors whose work is in progress as otherwise requested, shall attend a progress meeting which shall be held once every second week at the Project Site or as otherwise designated, to enable an orderly review of the construction progress and to provide for systematic discussion and analysis of concerns that may arise relative to execution of the Work.

B. Contractor and subcontractors as required shall incorporate attendance at these meetings as part of the Base Bid of the project - no overtime payments will be authorized for Contractor or subcontractors to attend regularly scheduled Progress Meetings or other special meetings if required.

C. Meeting Locations: Project site unless otherwise agreed.

D. Attendance: Representatives attending meetings are required to be qualified and authorized to act on behalf of their firms. Attendance shall include:

1. Government’s CO or COR;

2. Contractor’s Superintendent, Project Manager, and CQC Representative;

3. Subcontractors, as appropriate;

4. Suppliers, as appropriate;

5. Others, as appropriate.

E. Agenda: Discussion will pertain to items, such as:

1. Attenders; list of attenders and company they represent;

2. Review and approve minutes of previous meeting; written corrections, additions and/or deletions to previous minutes acknowledged;

3. Review work in progress since previous meeting together with previous “look-ahead” schedule;

1 July, 2015 013119-3

4. Review plans for progress for subsequent work period together with new “look-ahead” schedule;

5. Review construction schedule; confirm current status of work;

6. Present corrective measures and procedures to regain project schedule, as applicable;

7. Present field observations, problems, and conflicts; discuss concerns pertaining to:

a. Civil and landscaping items;

b. Equipment.

8. Discuss problems impeding progress schedule;

9. Review Contractor’s quality control system; discuss any concerns and corrective measures;

10. Review submittal schedules and logs; present methods to expedite as required;

11. Review off-site fabrication;

12. Review delivery schedules;

13. Review outstanding RFIs;

14. Review proposed changes for:

a. Effect on construction schedule and on completion date;

b. Effect on any other contracts of the project.

15. Review Change Order Proposal log and finalize prices;

16. Review draft of Application for Payment (at end of month);

17. Confirm status of the record (“as-built”) drawings and review required revisions to

Project Record Documents; see update requirements specified below;

18. Confirm status of shop drawing submittals and approvals;

19. Review project safety;

20. Review any outstanding Non-Compliance Notices;

21. Review any other business;

22. Confirm next meeting date, location and time plus those requested to be in attendance.

F. Government’s CO or COR will:

1. Attend progress meetings throughout work progress;

2. Ascertain that work is prosecuted consistently with contract documents and construction schedules.

G. At Contractor's option, twice-monthly progress meetings can be held integrally with monthly CPM scheduling meeting and Record Documents Update meeting specified herein.

H. Contractor shall provide the following at each meeting:

1. Current (and updated if necessary) construction schedule with 3 week ‘look ahead’.

2. One set of record documents (drawings, specifications, Change Order’s, COPs, RFIs, FAs, etc.).

3. Current (and updated if necessary) submittal schedule.

4. Current (updated) set of Project Record Documents.

1.04 MONTHLY CONSTRUCTION SCHEDULE MEETINGS, REPORTING

A. In addition to specific coordination meetings for each element of work, and other regular project meetings for other purposes, hold general scheduling meeting each month to review status according to recent updated schedule reports.

B. Require each entity then involved in planning, coordination or performance of work to be properly represented at each meeting. Review each entity's present and future needs including interface requirements, time, sequences, deliveries, access, site utilization, temporary facilities and services, hours of work, hazards and risks, housekeeping, change orders, and documentation of information for payment requests.

1 July, 2015 013119-4

C. Discuss whether each element of current work is ahead of schedule, on time, or behind time in relation with updated progress schedule. Determine how behind-time work will be expedited, and secure commitments from entities involved in doing so.

D. Discuss whether schedule revisions are required to ensure that current work and subsequent work will be completed within Contract Time.

E. Review everything of significance which could affect progress of the work.

F. Contractor’s representative shall take meeting notes of each…