Complete Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Road 1934 MP 2. 1 ERFO, newest first.
File Type Posted
Amendment1-S130026.pdf PDF
3-Rd1934ProjectSpecifications.pdf PDF
5-SF24BidBond.pdf PDF
2-Road1934ContractorReturnPacket.pdf PDF
4-Rd1934PlansAndDrawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-04T0-S-13-0026

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

07/03/2013

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

646029

6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SIUSLAW NATIONAL FOREST

ATTN: Contracting, AQM

3200 SW JEFFERSON WAY

CORVALLIS, OREGON 97331

ATTN: CONTRACTING, AQM

SIUSLAW NATIONAL FOREST

3200 SW JEFFERSON WAY

CORVALLIS, OREGON 97331

9. FOR INFORMATION

CALL:

A. NAME

Janet Paul, Contracting Officer

Brandon Green, Technical

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

541.750.7120

541.225.6351

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

RFP AG-04T0-S-13-0026

ROAD 1934 MP 2.1 ERFO

Middle Fork Ranger District Willamette National Forest Lane County, Oregon

Price Range: The Government's estimate is between $500,000 and $1,000,000.

Email proposals will NOT be accepted, see Block 13A below.

11. The Contractor shall begin performance within 10 calendar days and complete it within 120 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and -0- copies to perform the work required are due at the place specified in Item 7 by 4:00 PM local time 08/05/2013 . If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

USDS, OCFO, COD, APB

PO Box 60075 New Orleans, LA 70160

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

AG-04T0-S-13-0026

Road 1934 MP 2.1 ERFO

PART I - SCHEDULE OF ITEMS

SECTION B – SERVICES AND PRICES

B- 1 - SCHEDULE OF ITEMS (Page 1 of 3)

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

15101

Mobilization

Lump Sum

All

N/A

15201

Construction survey and staking, method 1, tolerance B

15401

Contractor testing

20104

Clearing and grubbing, disposal of tops and limbs (F2), logs (I), stumps (J)

Acre*

1.75

20358

Removal of 18” culvert, disposal method A

Each

20411

Embankment construction, compaction method E, finishing method A

Cubic Yard*

20457

Roadway excavation, compaction method E

20499

Excavation, placement method C

7,310

20701

Earthwork geotextile type II-A

Square

25104

Keyed riprap, class 3

25503

Select granular backfill

6,040

25550

Mechanically stabilized earth wall

Square Foot

7,222.3

32211

Aggregate surface course, grading F, compaction method B

B- 1 - SCHEDULE OF ITEMS (Page 2 of 3)

60278

24-inch corrugated polyethylene pipe, type A, method B

60502

Standard underdrain system

Foot*

60654

24-inch full circle polyethylene outlet pipe, type A

61701

Guardrail system G4, type 1, class A

212.5

61702

Terminal section type tangent terminal

TOTAL

* Denotes Contract Quantity

B-2 - NOTE:

Facsimile offers are accepted, see Section L-8, however, Facsimile Bid Guarantee IS NOT acceptable.

Offerors must respond to the other factors as described under EVALUATION CRITERIA in Section M.

Award will be made on the best value for the Government.

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

DUNS Number________________________

TIN Number__________________________

EMAIL ______________________________

B- 1 - SCHEDULE OF ITEMS (Page 3 of 3)

Note: prospective awardees MUST be registered, and active, in the System for Award Management (SAM) database to be awarded a Federal Government Contract. If you are not registered, please register at the following site: https://www.sam.gov/portal/public/SAM/

The estimated start work date is September 2013. Contract time is 120 calendar days, all work shall be completed by October 15, 2014.

For additional information, please contact Brandon Green at 541.225.6351.

Offers shall be submitted for the total item. Offers for less than the total item will not be considered.

If Offeror does not intend to charge for an item, a price of "0" or "NO COST" should be shown. If the price is left blank or shown as "No Bid," the entire offer may be considered Non-Responsive.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 STATEMENT OF WORK/SPECIFICATIONS - AGAR 452.211-72 (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J. Work includes, but is not limited to:

Traffic control, construction surveying and staking, materials testing, soil erosion control and prevention, clearing and grubbing, removal of existing culvert, embankment construction, excavation, geotextile placement, riprap placement, mechanically stabilized earth retaining wall construction, aggregate placement, culvert and downdrain placement, and guardrail placement.

C-2 PROJECT LOCATION

The project site can be located as follows: travel approximately 17.9 miles East on Aufderheide Drive, Forest Service Road 19, from Westfir, Oregon and turn right onto FS Road 1934. Continue on FS Road 1934 approximately 2.1 miles until you reach the project site.

C-3 SPECIFICATIONS

AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL

SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS FPMR

PART 101-29 (FAR 52.211-1) (AUG 1998)

(a) The GSA Index of Federal Specifications, Standards and Commercial Item Description, FPMR Part 101- 29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to--

GSA Federal Supply Service Specifications Section, Suite 8100 470 East L'Enfant Plaza SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978.

(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF

FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM

DESCRIPTIONS (FAR 52.211-3) (JUN 1988)

The specifications cited in this solicitation may be obtained from:

Specification Address

Standards Specifications for Available online at Construction of Roads and Bridges http://www.wfl.fha.dot.gov/design/specs/fp03.htm On Federal Highway Projects FP-03 U.S. Customary Units

ASTM Standards American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103

(215) 199-5462

AASHTO Standards American Association of State Highway and

Transportation Officials 341 National Press Building Washington, D.C. 20024

The request should identify the solicitation number and the specification requested by date, title, and number, as cited in the solicitation.

C-4 SUBMITTALS

Submittals shall include the following unless otherwise required in the specification:

1. Date and revision dates.

2. Project name and contract number.

3. Names of Contractor, subcontractor, supplier, and manufacturer.

4. Specifications section number.

5. Field dimensions and relation to adjacent structures.

6. Applicable standards such as ASTM or Federal Specifications.

7. Contractor's stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents. Provide all submittals within 14 calendar days of contract award unless otherwise required by the specification.

C-5 PRODUCT SAMPLES AND/OR SUBMITTALS

The following product samples and/or submittals are required for this project:

Title Referenced by

Specification No Time of Government Approval After Submittal

Schedule for Construction FAR 52.236-15 14 days Safety Plan FAR 52.236-15 14 days Hazardous Spill Plan 107.10 14 days Traffic Control Plan 156.03 14 days Erosion Control Plan 157.03 14 days Aggregate Surface Course 703.05 14 days Select Granular Backfill 704.10 14 days Riprap 705.02 14 days

C-6 SHOP DRAWINGS

The following shop drawings shall be submitted on this project:

Title Referenced by

Specification No Time of Government Approval After Submittal

MSE Wall Installation Drawings 104.03, 255.03 14 days

C-7 MATERIAL CERTIFICATIONS AND TESTING REPORTS

The following material certifications and/or testing reports shall be submitted on this project:

Title Referenced by

Specification No Time of Government Approval After Submittal

Welded Wire Wall 720.01 14 days Guardrail Material 617.09 14 days Aggregate Surface Course 703.05 14 days Select Granular Backfill 704.10 14 days Riprap 705.02 14 days Polyethylene Pipe 706.08 14 days Geotextile 714.01 14 days

C-8 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-73)

(FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C-9 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS FP-03 U.S. CUSTOMARY UNITS

The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S.

Customary Units are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.

(a) Section 100 through 149 of the Standard Specification and all other Standard or Supplemental Specifications shown in the specification listing are applicable to this contract. All specifications not included in the specification listing, but referenced by listed specifications, are applicable. The Supplemental Specifications shown on the specification list are physically attached in Section C.

(b) See the following for the specification lists and supplemental specifications.

C-10 STANDARD SPECIFICATIONS

See Section J.

C-11 SUPPLEMENTAL SPECIFICATIONS

See Section J.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

E-1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2)(FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

E-2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at the project site.

E-3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT

The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Supplemental Specifications.

E-4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

SECTION F--DELIVERIES OR PERFORMANCE

F-1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2)(FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.242-14 Suspension of Work (APR 1984)

F-2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(FAR 52.211-10)(APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after issuance of Notice to Proceed (project to be completed by 10/15/2014). The time stated for completion shall include final cleanup of the premises.

Estimated start work: September 2013

F-3 SUSPENSIONS OF WORK FOR OTHER THAN GOVERNMENT'S CONVENIENCE

The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to be muddy or unsuitable; or (2) failure of the Contractor to comply with specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements.

Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by its operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242- 14, Suspension of Work, and shall not qualify for an equitable adjustment.

SECTION G--CONTRACT ADMINISTRATION DATA

G-1 POST AWARD CONFERENCE (AGAR 452.215-73) (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be held at the Headquarters of the Willamette National Forest (Springfield, OR), or the Siuslaw National Forest (Corvallis, OR), or a mutually agreed upon location.

G-2 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract. The Contracting Officer should be informed as soon as possible or any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly.

(This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

G-3 GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the FAR clauses “52.245-1 -- Government Property”, or “52.245-9 -- Use and Charges” as applicable.

Item No. Description Quantity Delivery Date

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H-1 POTENTIAL SAFETY HAZARDS

(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.

(b) The following checked activities have been identified by the Government as potential safety hazards.

[] Confined space entry.

[X] Temporary excavation/deep trenching/slope stability.

[X] Tree falling.

[X] Fall hazard from work heights exceeding six feet.

[] Blasting.

[X] Traffic control on high-volume and/or high-speed and/or limited visibility roads.

[X] Heavy equipment operation.

[] Tree climbing and/or tower climbing.

[X] Fire hazards.

[] Hazardous materials handling.

[] Electrical hazard.

[X] Hydraulic and/or pneumatic and/or other high pressure hazards.

[X] Mechanical hazards such as pulleys, springs, etc.

[X] Other: Steep side slopes

H-2 INDUSTRIAL CAMPS

Forest Service regulations for Use of Campgrounds prohibit occupancy of developed recreation sites for other than primarily recreation purposes. No industrial camping will be authorized at these sites.

A special use permit is required on National Forest land for industrial camps. These permits are to be obtained by the Contractor through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor but may include use restrictions.

One self-contained camp unit will be allowed at each staging area and equipment or supply dump for use by a watchman.

H-3 SALVAGE RIGHTS

No Contractor salvage rights exist under the contract unless specifically provided elsewhere herein.

H-4 SPECIAL EQUIPMENT CLEANING REQUIREMENTS

All earth moving equipment (loaders, excavators, dump trucks, etc.) moved to the job site shall be cleaned of weeds and their seeds prior to each entrance onto the National Forest lands. Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose.

Equipment shall be made available for visual inspection by the Forest Service prior to entering Forest Service lands. The Contractor shall advise of a proposed date for mobilization. Inspections will take place at mutually agreeable en-route locations in advance of entry onto National Forest lands.

Special care shall be taken to assure removal of the following noxious weeds and their seeds:

spotted knapweed (Centaurea maculosa) diffuse knapweed (C. diffusa) yellow starthistle (C. solstitialis) gorse (Ulex europaeus) rush skeletonweed (Chondrilla juncea) tansy ragwort (Senecio jecobaea) purple loosestrife (Lythrum salicaria) distaff thistle (Carthamus lanatus) scotch broom (Cytisus scoparius)

The Contractor shall take special care under this contract to prevent contamination of water at the work sites with any petroleum residues from mechanical equipment operations. This shall include daily inspection and cleaning as appropriate.

H-5 PHYSICAL DATA (FAR 52.236-4) (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the plans and in the specifications are the result of the site investigations by surveys, auger borings, drive probing, and visible observations.

(b) Weather conditions: Normal fire season is June 15 to October 15. Weather conditions, data from:

http://www.weatherbase.com/weather/weather.php3?s=152653&refer=&cityname=Oakridge-Oregon- United-States-of-America

(c) Transportation facilities: Site is accessed via paved state highways, paved, and aggregate Forest Service roads.

(d) Utilities: Unknown

H-6 LANDSCAPE PRESERVATION

(a) The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. The Contractor shall confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states. If a spill of petroleum product should occur in water, the Contractor shall take immediate action to clean up or contain the spill, then immediately notify the COR and the Oregon Emergency Response System (OERS), telephone 1-800-452-0311 or 1-503-378-4124, and then immediately notify the Contracting Officer.

Contractor shall have a SPILL RESPONSE KIT on the project whenever equipment is operating. The spill kit shall be sufficient to absorb 34 gallons of oil, designed to float on the surface, while absorbing oil and repelling water. The KIT shall meet or exceed the physical properties of “New Pig Products Spill Kit #408”.

Oil absorbing mats are required under all stationary equipment, or equipment being serviced within the Forest Boundary to prevent leaking or spilled petroleum base products from contaminating soil and water resources.

Such material will be furnished by Contactor and approved by Contracting Officer.

Servicing of all equipment shall be done only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Equipment shall be furnished on a fully operational basis, of modern design and in good operating condition with no fuel or oil leaks. Repairs and move-in/move-out are the Contractor’s responsibility. All equipment shall be power washed and shall be clean prior to entering Forest Service Land.

(c) No objectionable material shall be allowed to enter any stream, river, lake, or other body of water.

Material which falls in these areas shall be retrieved and disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the project limits shall be repaired as directed by the Contracting Officer.

(d) The Contractor shall not operate equipment or otherwise disturb the natural vegetation and soil beyond the areas flagged on the ground or beyond two feet from edge of walkways, top of cuts, or toe of fills.

(e) The Contractor will make every reasonable attempt to preserve the scenic and natural environment along this construction project.

(f) Prior to the start of construction the Contractor shall submit to the Engineer for approval a schedule and plan for temporary pollution control measures for the following phases of work:

(i) ALL

H-7 MOISTURE SENSITIVE SOILS

Contractors are cautioned that the roadway structure is designed so that the completed road will support highway legal loads during a limited use season. Construction equipment often subjects the uncompleted roadway structure to loadings it is not designed to support. This is especially critical during periods of excessive moisture and will require careful selection and scheduling to permit efficient operation. Any damage resulting from operations which renders the material unsuitable for use or results in potential siltation of streams will be corrected by the Contractor at its expense.

H-8 VALUE ENGINEERING

Value engineering change proposals which change the service or function of a facility or produce irreconcilable conflicts with management objectives will not be considered.

The following work is excluded from consideration under the Value Engineering clause: None

H-9 PRODUCT SUBSTITUTION

Any modification of items, designs, materials, products or equipment (including Government-Furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

H-10 ROAD USE AND MAINTENANCE

Use of Roads

(a) The Contractor is authorized to use roads that are listed as access to this project.

Road Number Name Termini Description of Authorization

Restrictions or Requirements See Road Rules

Maintenance Required

FS Road 19 Aufderheide Drive

MP 0.0 to MP 18 Monday thru Friday None

FS Road 1934

MP 0.0 to MP 3.0

Monday thru Friday

None

If the Contractor requests use of a National Forest road or segment not designated for use, the Forest Service may authorize such use if not in conflict with the current Road Rules Document. Authorization to use such additional roads may include maintenance requirements and use limitations.

The roads authorized for use are subject to the following provisions:

1. The Road Rules in the current Siuslaw, Willamette, Mt. Hood, Deschutes and Umpqua National Forest Road Rules Document are applicable to all commercial road users. These documents titles SIUSLAW NATIONAL FOREST ROAD RULES, COMMERCIAL HAULING ROAD RULES MAP (Willamette National Forest), MT. HOOD NATIONAL FOREST ROAD RULES POLICY, DESCHUTES NATIONAL FOREST COMMERCIAL ROAD RULES, and COMMERCIAL ROAD RULES (Umpqua National Forest) are available for inspection at the Willamette and Siuslaw National Forest Supervisor's Offices.

2. State laws governing traffic rules and equipment requirements on State and County highways.

3. Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use of vehicles or equipment in excess of State legal highway loads or posted limits without valid State or Forest Service overload permits, damaging a road while using it, and blocking a road open to use by others, except as may otherwise be provided in the contract.

4. Federal Regulations contained in 36 CFR 261.54 as applied to the area by an order issued under 36 CFR

261.50. These regulations authorized the Forest Service as a sovereign act, to issue additional restrictions and closures any time conditions warrant. Such closures will be in addition to those shown in the current Road Rules Document and will be posted on the road.

5. Unless otherwise provided, the Government will not snowplow roads for the Contractor's use. The Contractor may snowplow any road designated for its use, unless snowplowing of the road is prohibited below or in the Road Rules Document. On roads where snowplowing is authorized, a permit defining snowplowing requirements is required. The Contractor will be responsible for repair of any damage to the road structure caused by the snow removal operations. Vehicles, other than conventional over-the-snow vehicles (snowmobiles), will not be permitted to use roads when there is an average uncompacted depth of more than 4 inches of snow unless the road has been snowplowed.

Traffic Control

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points, where the project crosses or coincides with an existing road or trail.

H-11 TANK TRUCK

In addition to the requirements under Fire Precautionary Measure 1 – Tank Truck (Section J), a tank truck is required during all contract operations.

H-12 CONTROL OF MATERIAL

A Rights In and Use of Materials: The Contractor may use on the project suitable stone, gravel, or sand encountered in the excavation.

B Excavation: Unclassified

C Material Sources:

1. Borrow sources, if needed, must be approved in advance by the Contracting Officer. Such borrow sources shall be restored to a natural appearance.

2. Native timber material used in construction shall not be taken within sight of any road or trail. Stumps resulting from tree cutting shall be no more than six (6) inches in height. All debris resulting from preparation of the native timber for use, shall be scattered not more than four (4) inches in depth and out of meadows, stream courses, lakes and ponds.

3. Rocks and mineral soil excavated within the normal excavation shall be conserved and used as needed.

D Storage and Stockpiling of Materials: Materials shall be stored to assure the preservation of quality and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by the Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment. All storage sites provided by the Forest Service shall be restored at the Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered lands.

E Local Disposal Sites: Designated disposal sites for this project are shown on Sheet 1 of the Plans.

F Earthwork Tolerances: Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Plans, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

H-13 CONSTRUCTION STAKES, LINES, AND GRADES

(a) The Forest Service has provided initial control points as shown on the plans. The Contractor shall do all further surveying, staking, and engineering to establish the horizontal and vertical control necessary to result in having the finished work comply with the lines and grades shown on the Plans or stated in the specifications.

(b) If any construction control points have been destroyed or displaced, or are erroneous, the Contractor shall promptly notify the COR. If these points are destroyed or displaced due to Contractor's negligence or operation, the cost for replacing them will be charged to the Contractor.

(c) In case of any construction changes, the Contractor shall cooperate with the COR and facilitate the prompt reestablishment of the field control for the adjusted work.

H-14 PROSECUTION OF WORK

(a) For the protection of natural resources, time restrictions will apply. Work will be conducted only during the following time frames unless other hours are approved in writing by the Contracting Officer:

Construction activity shall be limited to July 15th to October 15th, Monday through Friday.

The Contractor shall conduct activities so that interference with the public shall be kept at a minimum.

Any activities requiring closures to the public shall be scheduled with the COR at least 14 days in advance

(b) The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.

(c) Blasting is prohibited. The Contractor shall use mechanal equipment to excavate rock or non explosive means that will fracture rock, be non-toxic, and are approved in writing by the COR.

H-15 PROTECTION OF IMPROVEMENTS

Unless otherwise agreed to in writing, Contractor shall remove the existing traffic signs within the work area and reinstall to their approximate existing locations prior to final acceptance.

H-16 SANITATION REQUIREMENTS

Unless substitute measures or equipment are authorized in writing by the Contracting Officer, protection of air and water quality will include the use of approved chemical toilets by all persons engaged in road construction or in removing timber under this contract while they are within the boundaries of the Forest. Such facilities shall be furnished by Contractor in quantities and at locations approved by the COR. No habitation or overnight dwelling by employees of Contractor will be permitted on National Forest land without advance written approval from the Contracting Officer unless otherwise authorized under Industrial Camps clause.

H-17 STATE PERMITS

Roads in the project work area necessary to complete the project are designated as "within the immediate construction project" for consideration under ORS 767.025 as to the nonapplicability of PUC requirements.

H-18 FINAL CLEANUP

Contractor shall remove and dispose all of its own trash and refuse from the contract area. Material to be removed includes, but is not limited to camp refuse such as tin cans, aluminum foil, glass, paper, garbage, used engine oil, oil filters, oil cans, grease cartridges, etc. The Contractor shall also remove and dispose of upon completion of the trail construction, all stakes, old culverts, flagging, and similar debris within the project area.

This Cleanup is a subsidiary item for which no special payment will be made. All debris shall be disposed off National Forest Land and in accordance with State and Local disposal requirements.

H-19 PROTECTION OF CULTURAL RESOURCES

Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1979 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by Forest Service. Forest Service may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object which is or may be entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas or objects by either party shall be promptly reported to the other party.

Contractor shall protect all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destruction, obliteration, removal or damage during Contractor's Operations. In accordance with 36 CFR 296.14(c), Contractor shall bear costs of restoration, provided that such payment shall not relieve Contractor from civil or criminal remedies otherwise provided by law.

Wheeled or track-laying equipment shall not be operated within such areas except on roads. Unless agreed otherwise, trees will not be felled into such areas.

H-20 PROTECTION OF HABITAT OF ENDANGERED, THREATENED, AND SENSITIVE

SPECIES

Location of areas needing special measures for protection of plants or animals listed as threatened or endangered under the Endangered Species Act of l973, as amended, or as sensitive by the Regional Forester under authority of FSM 2670, are shown on the Plans and identified on the ground. Measures needed to protect such areas have been included elsewhere in this contract or are as follows: SEE PROSECUTION OF WORK.

If protection measures prove inadequate, if other such areas are discovered, or if new species are listed as Federally threatened or endangered or as sensitive by the Regional Forester, Forest Service may either cancel or unilaterally modify this contract to provide additional protection regardless of when such facts become known.

Discovery of such areas by either party shall be promptly reported to the other party.

H-21 AGAR 452.228-71 INSURANCE COVERAGE (NOV 1996)

Pursuant to FAR clause 52.228-5, Insurance - Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I-1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

52.202-1 Definitions (JAN 2012) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (APR 1984) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (OCT 2010) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (AUG 2012) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (DEC 2010) 52.209-9 Updates on Publicly Available Information Regarding Responsibility Matters (FEB 2012) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (OCT 2010) 52.219-3 Notice of HUBZone Set-Aside or Sole Source Award (NOV 2011) 52.219-8 Utilization of Small Business Concerns (JAN 2011) 52.219-14 Limitations on Subcontracting (DEC 1996) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL 2005) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-8 Payrolls and Basic Records (JUN 2010) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-35 Equal Opportunity for Veterans (SEP 2010) 52.222-36 Affirmative Action for Workers with Disabilities (OCT 2010) 52.222-37 Employment Reports on Veterans (SEP 2010) 52.222-40 Notification of Employee Rights under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (FEB 2009) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

(JUL 2012)

52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999) 52.228-15 Performance and Payment Bonds – Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-17 Interest (OCT 2010) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003) 52.233-1 Disputes (JULY 2002) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by The Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities & Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995)

52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (DEC 2010) 52.245-1 Government Property (APR 2012) 52.246-21 Warranty of Construction (MAY 1994) 52.248-3 Value Engineering – Construction (OCT 2010) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--Alternate I

(SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

I-2 CENTRAL CONTRACTOR REGISTRATION (FAR 52.204-7)(DEC 2012)

(a) Definitions. As used in this clause—

“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.

“Registered in the CCR database” means that—

(1) The offeror has entered all mandatory information, including the DUNS number or the DUNS+4 number, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see Subpart 4.14) into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”.

The offeror will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.

(b) (1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer.