Solicitation-MR-BunKPaving.pdf
PDF 351 KB Posted
- Attached to
- Bunkhouse Area Asphalt Project Federal contract opportunity
- Solicitation number
- AG-04R4-S-12-0018
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment2-Project-Plans.pdf | ||
| Attachment4-FSSS.pdf | ||
| Attachment3-Spec-List.pdf | ||
| Packet-to-Return.PDF |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PREQUEST FOR QUOTATION PAGE OF PAGES
(THIS IS NOT AN ORDER) THIS RFQ IS IS NOT A SMALL BUSINESS SET- ASIDE 1 46
1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT.DEF. RATING
AG-04R4-S-12-0018 08/21/12 598080
UNDER BDSA REG. 2
AND/OR DMS REG. 1
5a. ISSUED BY 6. DELIVER BY (Date)
Willamette NF Supervisor’s Office 3106 Pierce Parkway, Suite D Springfield OR 97477-7909
As specified herein
5b. FOR INFORMATION CALL (NO COLLECT CALLS) 7. DELIVERY FOB DESTINATION NAME TELEPHONE NUMBER OTHER (See Schedule)
AREA CODE NUMBER 9. DESTINATION
Contracting Officer:
Technical Contact – Jack Wilson
225-6334 822-7219
a. NAME OF CONSIGNEE
8. TO: Willamette NF Supervisor’s Office
a. NAME b. COMPANY b. STREET ADDRESS Front Desk USDA - FS
c. STREET ADDRESS c. CITY 3106 Pierce Parkway, Suite D
d. CITY e. STATE f. ZIP CODE d. STATE e. ZIP CODE Springfield OR 97477
10. PLEASE FURNISH QUOTATIONS TO THE
ISSUING OFFICE IN BLOCK 5A ON OR BEFORE
THE SUGGESTED RESPONSE DATE OF
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A. This request does not commit the Government to pay any costs incurred in the preparation of the
Local Time 09/10/2012 4:00 PM submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(a) (b) (c) (d) (e) (f)
Bunkhouse Area Asphalt Project
Willamette National Forest
McKenzie River Ranger District Lane County Oregon
See Attached
Requirements
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR
DAYS
c. 30 CALENDAR DAYS d. CALENDAR DAYS
12. DISCOUNT FOR PROMPT PAYMENT NUMBER PERCENTAGE
NOTE: Additional provisions and representations are are not attached.
13. NAME AND ADDRESS OF QUOTER 14. SIGNATURE OF PERSON AUTHORIZED TO 15. DATE OF
a. NAME OF QUOTER SIGN QUOTATION QUOTATION
b. STREET ADDRESS 16. SIGNER
a. NAME (Type or print) b. TELEPHONE
c. COUNTY AREA CODE
d. CITY e. STATE f. ZIP CODE c. TITLE (Type or Print) NUMBER
NSN 7540-01-152-8084
Previous edition not usable
18-121 STANDARD FORM 18 (Rev. 6-95) Prescribed by GSA-FAR (48 CFR) 53.215-1(a)
Sol. No. AG-04R4-S-12-0018 Willamette National Forest / McKenzie River RD
Bunkhouse Area Asphalt Project
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
ITEM
NO. DESCRIPTION PAY UNIT
EST.
QTY. UNIT PRICE TOTAL PRICE
15101 Mobilization Lump Sum All $__________ $__________
20464 Excavation, compaction method B, finishing method C
Lump Sum All $__________ $__________
32203 Aggregate base, grading D, compaction method B Cubic Yard* 68 $__________ $__________
40401 Minor hot asphalt concrete Ton 54.66 $__________ $__________
43007A Skin patch hot asphalt concrete mixture Ton 11.00 $__________ $__________
TOTAL $__________
OPTIONAL ITEM
43007B Skin patch hot asphalt concrete mixture Ton 110.00 $__________ $__________
TOTAL FOR ALL ITEMS $___________________
*Designates contract quantities
If quoter does not intend to charge for an item number, a price of “0” or “NO COST” should be shown. If the price is left blank or shown as “No Quote,” the entire quote may be considered Non-Responsive.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Pay Item No. 00301 - 01Mobilization.
DUNS Number_____________________ TIN Number_______________________
Email _____________________________
Bunkhouse Area Asphalt Project
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
Quoters must respond to the other factors as described in EVALUATION OF QUOTES in Section M.
Quote shall be submitted for the total item. Quote for less than the total item will not be considered.
Quotations may be submitted via fax to 541-225-6220, or sent hard copy to the address shown in block 5(a) of the Standard Form 18. Quotes will not be accepted via email.
The designated billing address is shown in block 5(a) of the Standard Form 18.
The estimated start work date is September 24, 2012. All work shall be completed within _ 21 calendar days after the effective date of the Notice to Proceed.
NOTE: Quoter MUST register in the Central Contractor Registration (CCR) data base – See FAR 52.204-7 and Online Representations and Certifications Applications (ORCA) – See FAR clause 52.204-8. These are now consolidated at the following site: https://www.sam.gov/portal/public/SAM/ Quoter shall register at this new website, before award will be made.
https://www.sam.gov/portal/public/SAM/
Bunkhouse Area Asphalt Project
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 STATEMENT OF WORK/SPECIFICATIONS - AGAR 452.211-72 (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
Work includes: Skin patching potholes with HMAC & constructing an asphalt pad over an existing lawn.
(End of clause)
C-2 PROJECT LOCATION
The project can be located as follows: From Eugene, Oregon, proceed east on Highway 126 to mile post
50. Turn right onto Horse Creek Road. Proceed 0.4 miles to Engles Drive (on the left), Beginning of Project.
C-3 SPECIFICATIONS
AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL
SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS FPMR
PART 101-29 (FAR 52.211-1) (AUG 1998)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Description, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to--
GSA Federal Supply Service Specifications Section, Suite 8100 470 East L'Enfant Plaza SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.
(End of provision)
AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF
FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM
DESCRIPTIONS (FAR 52.211-3) (JUN 1988)
The specifications cited in this solicitation may be obtained from:
Bunkhouse Area Asphalt Project
Specification Address
Standards Specifications for Available online at Construction of Roads and Bridges http://www.wfl.fha.dot.gov/design/specs/fp03.htm On Federal Highway Projects FP-03 U.S. Customary Units
ASTM Standards American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103
(215) 199-5462
AASHTO Standards American Association of State Highway and
Transportation Officials 341 National Press Building Washington, D.C. 20024
The request should identify the solicitation number and the specification requested by date, title, and number, as cited in the solicitation.
C-4 SUBMITTALS
Submittals shall include the following unless otherwise required in the specification:
1. Date and revision dates.
2. Project name and contract number.
3. Names of Contractor, subcontractor, supplier, and manufacturer.
4. Specifications section number.
5. Field dimensions and relation to adjacent structures.
6. Applicable standards such as ASTM or Federal Specifications.
7. Contractor's stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents. Provide all submittals within 14 calendar days of contract award unless otherwise required by the specification.
C-5 PRODUCT SAMPLES AND/OR SUBMITTALS
The following product samples and/or submittals are required for this project:
Title Referenced by
Specification No Time of Government Approval After Submittal
Schedule for Construction FAR 52.236-15 10 days Aggregate Base 703.05 10 days
Hazards Spill Plan 107.10 10 days
Bunkhouse Area Asphalt Project
Traffic Control Plan 156.04 10 days Minor hot asphalt concrete Job Mix Formula
430.10 10 days
C-6 SHOP DRAWINGS
The following shop drawings shall be submitted on this project:
Title Referenced by
Specification No Time of Government Approval After Submittal
C-7 MATERIAL CERTIFICATIONS AND TESTING REPORTS
The following material certifications and/or testing reports shall be submitted on this project:
Title Referenced by
Specification No Time of Government Approval After Submittal
Aggregate Base 703.05 10 days Minor hot asphalt concrete Job-Mix Formula
430.10, 404.10 10 days
C-8 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS - AGAR 452.211-73
(FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
Bunkhouse Area Asphalt Project
C-9 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON
FEDERAL HIGHWAY PROJECTS FP-03 U.S. CUSTOMARY UNITS
The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary Units are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
(a) Section 100 through 149 of the Standard Specification and all other Standard or Supplemental Specifications shown in the specification listing are applicable to this contract. All specifications not included in the specification listing, but referenced by listed specifications, are applicable. The Supplemental Specifications shown on the specification list are physically attached in Section C.
(b) See the following for the specification lists and supplemental specifications.
C-10 PRICE RANGE
between $25,000 and $100,000.
C-11 STANDARD SPECIFICATIONS
Attached in Section J
C-12 SUPPLEMENTAL SPECIFICATIONS
Attached in Section J
Bunkhouse Area Asphalt Project
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
Bunkhouse Area Asphalt Project
SECTION E--INSPECTION AND ACCEPTANCE
E-1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/vffara.htm
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-1 Contractor Inspection Requirements (APR 1984) 52.246-12 Inspection of Construction (AUG 1996)
E-2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at the project site.
E-3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT
The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.
E-4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
http://farsite.hill.af.mil/vffara.htm
Bunkhouse Area Asphalt Project
SECTION F--DELIVERIES OR PERFORMANCE
F-1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/vffara.htm
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
F-2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
The Contractor shall be required to (a) commence work under this contract within __10__ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than __21__ calendar days after the effective date of the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
F-3 SUSPENSIONS OF WORK FOR OTHER THAN GOVERNMENT'S CONVENIENCE
The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property.
Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to be muddy or unsuitable; or (2) failure of the Contractor to comply with specifications such as working in conditions which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by its operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for an equitable adjustment.
Bunkhouse Area Asphalt Project
SECTION G--CONTRACT ADMINISTRATION DATA
G-1 POST AWARD CONFERENCE (AGAR 452.215-73) (FEB 1988)
A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be at McKenzie River Ranger District, 57600 McKenzie Highway, McKenzie Bridge, OR 97413
G-2 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract. The Contracting Officer should be informed as soon as possible or any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
Bunkhouse Area Asphalt Project
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H-1 PHYSICAL DATA (FAR 52.236-4) (APR 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by _survey and visible observation of each site_.
(b) Weather conditions may be obtained at: www.weather.com
(c) Trasportation facilities Access project site by paved and aggregate state, county and forest service roads.
(d) N/A .
H-2 POTENTIAL SAFETY HAZARDS
(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.
(b) The following checked activities have been identified by the Government as potential safety hazards.
[ ] Confined space entry.
[ ] Temporary excavation/deep trenching/slope stability.
[] Tree falling.
[ ] Fall hazard from work heights exceeding six feet.
[ ] Blasting.
[] Traffic control on high-volume and/or high-speed and/or limited visibility roads.
[X ] Heavy equipment operation.
[ ] Tree climbing and/or tower climbing.
[] Fire hazards.
[X] Hazardous materials handling.
[ ] Electrical hazard.
[ X] Hydraulic and/or pneumatic and/or other high pressure hazards.
[] Mechanical hazards such as pulleys, springs, etc.
[ ] Other __________________________________ http://www.weather.com/
Bunkhouse Area Asphalt Project
H-3 INDUSTRIAL CAMPS
Forest Service regulations for Use of Campgrounds prohibit occupancy of developed recreation sites for other than primarily recreation purposes. No industrial camping will be authorized at these sites.
A special use permit is required on National Forest land for industrial camps. These permits are to be obtained by the Contractor through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor but may include use restrictions.
One self-contained camp unit will be allowed at each staging area and equipment or supply dump for use by a watchman.
H-4 SALVAGE RIGHTS
No Contractor salvage rights exist under the contract unless specifically provided elsewhere herein.
H-5 SPECIAL EQUIPMENT CLEANING REQUIREMENTS
All earth moving equipment (loaders, excavators, dump trucks, etc.) moved to the job site shall be cleaned of weeds and their seeds prior to each entrance onto the National Forest lands. Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose.
Equipment shall be made available for visual inspection by the Forest Service prior to entering Forest Service lands. The Contractor shall advise of a proposed date for mobilization. Inspections will take place at mutually agreeable en-route locations in advance of entry onto National Forest lands.
Special care shall be taken to assure removal of the following noxious weeds and their seeds:
spotted knapweed (Centaurea maculosa) diffuse knapweed (C. diffusa) yellow starthistle (C. solstitialis) gorse (Ulex europaeus) rush skeletonweed (Chondrilla juncea) tansy ragwort (Senecio jecobaea) purple loosestrife (Lythrum salicaria) distaff thistle (Carthamus lanatus) scotch broom (Cytisus scoparius)
The Contractor shall take special care under this contract to prevent contamination of water at the work sites with any petroleum residues from mechanical equipment operations. This shall include daily inspection and cleaning as appropriate.
H-6 LANDSCAPE PRESERVATION
(a) The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. The Contractor shall confine operations to within the clearing limits or other areas
Bunkhouse Area Asphalt Project designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.
(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states. If a spill of petroleum product should occur in water, the Contractor shall take immediate action to clean up or contain the spill, then immediately notify the Engineer and the Oregon Emergency Response System (OERS), telephone 1- 800-452-0311 or 1-503-378-4124, and then immediately notify the Contracting Officer.
Contractor shall have a SPILL RESPONSE KIT on the project whenever equipment is operating. The spill kit shall be sufficient to absorb 34 gallons of oil, designed to float on the surface, while absorbing oil and repelling water. The KIT shall meet or exceed the physical properties of “New Pig Products Spill Kit #408”.
Oil absorbing mats are required under all stationary equipment, or equipment being serviced within the Forest Boundary to prevent leaking or spilled petroleum base products from contaminating soil and water resources. Such material will be furnished by Contactor and approved by Contracting Officer.
Servicing of all equipment shall be done only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.
Equipment shall be furnished on a fully operational basis, of modern design and in good operating condition with no fuel or oil leaks. Repairs and move-in/move-out are the Contractor’s responsibility. All equipment shall be power washed and shall be clean prior to entering Forest Service Land.
(c) No objectionable material shall be allowed to enter any stream, river, lake, or other body of water.
Material which falls in these areas shall be retrieved and disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the project limits shall be repaired as directed by the Contracting Officer.
(d) The Contractor shall not operate equipment or otherwise disturb the natural vegetation and soil beyond the areas flagged on the ground or beyond two feet from edge of walkways, top of cuts, or toe of fills.
(e) The Contractor will make every reasonable attempt to preserve the scenic and natural environment along this construction project.
(f) Prior to the start of construction the Contractor shall submit to the Engineer for approval a schedule and plan for temporary pollution control measures for the following phases of work:
[THE FOLLOWING ARE EXAMPLES OF ITEMS THAT MIGHT BE ENVIRONMENTALLY
SENSITIVE.
(i) Item 20464, Excavation
H-7 MOISTURE SENSITIVE SOILS
Contractors are cautioned that the roadway structure is designed so that the completed road will support highway legal loads during a limited use season. Construction equipment often subjects the uncompleted roadway structure to loadings it is not designed to support. This is especially critical during periods of excessive moisture and will require careful selection and scheduling to permit efficient operation. Any damage resulting from operations which renders the material unsuitable for use or results in potential siltation of streams will be corrected by the Contractor at its expense.
H-8 PRODUCT SUBSTITUTION
Any modification of items, designs, materials, products or equipment (including Government-Furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
H-9 ROAD USE AND MAINTENANCE
Use of Roads
(a) The Contractor is authorized to use roads that are listed as access to this project.
Road Number
Name Termini Description of Authorization Restrictions or Requirements See Road Rules
Maintenance Required
2638340 Engles Drive beginning to end No weekend use N/A
If the Contractor requests use of a National Forest road or segment not designated for use, the Forest Service may authorize such use if not in conflict with the current Road Rules Document. Authorization to use such additional roads may include maintenance requirements and use limitations.
The roads authorized for use are subject to the following provisions:
1. The Road Rules in the current Siuslaw, Willamette, Mt. Hood, Deschutes and Umpqua National Forest Road Rules Document are applicable to all commercial road users. These documents titles
SIUSLAW NATIONAL FOREST ROAD RULES, COMMERCIAL HAULING ROAD RULES MAP
(Willamette National Forest), MT. HOOD NATIONAL FOREST ROAD RULES POLICY, DESCHUTES
Bunkhouse Area Asphalt Project
NATIONAL FOREST COMMERCIAL ROAD RULES, and COMMERCIAL ROAD RULES (Umpqua National Forest) are available for inspection at the Willamette and Siuslaw National Forest Supervisor's Offices.
2. State laws governing traffic rules and equipment requirements on State and County highways.
3. Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use of vehicles or equipment in excess of State legal highway loads or posted limits without valid State or Forest Service overload permits, damaging a road while using it, and blocking a road open to use by others, except as may otherwise be provided in the contract.
4. Federal Regulations contained in 36 CFR 261.54 as applied to the area by an order issued under 36 CFR 261.50. These regulations authorized the Forest Service as a sovereign act, to issue additional restrictions and closures any time conditions warrant. Such closures will be in addition to those shown in the current Road Rules Document and will be posted on the road.
5. Unless otherwise provided, the Government will not snowplow roads for the Contractor's use. The Contractor may snowplow any road designated for its use, unless snowplowing of the road is prohibited below or in the Road Rules Document. On roads where snowplowing is authorized, a permit defining snowplowing requirements is required. The Contractor will be responsible for repair of any damage to the road structure caused by the snow removal operations. Vehicles, other than conventional over-the-snow vehicles (snowmobiles), will not be permitted to use roads when there is an average uncompacted depth of more than 4 inches of snow unless the road has been snowplowed.
Traffic Control
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points, where the project crosses or coincides with an existing road or trail.
H-10 CONTROL OF MATERIAL
A Rights In and Use of Materials: The Contractor may use on the project suitable stone, gravel, or sand encountered in the excavation.
B Excavation: Unclassified.
C Material Sources:
1. Borrow sources, if needed, must be approved in advance by the Contracting Officer. Such borrow sources shall be restored to a natural appearance.
2. Native timber material used in construction shall not be taken within sight of any road or trail.
Bunkhouse Area Asphalt Project
Stumps resulting from tree cutting shall be no more than six (6) inches in height. All debris resulting from preparation of the native timber for use, shall be scattered not more than four (4) inches in depth and out of meadows, stream courses, lakes and ponds.
3. Rocks and mineral soil excavated within the normal excavation shall be conserved and used as needed.
D Storage and Stockpiling of Materials: Materials shall be stored to assure the preservation of quality and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by the Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment. All storage sites provided by the Forest Service shall be restored at the Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered lands.
E Local Disposal Sites: Designated disposal sites for this project are shown on the Plans.
F Earthwork Tolerances: Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Plans, indicated in the specifications, or designated on the ground.
"Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
H-11 CONSTRUCTION STAKES, LINES, AND GRADES
(a) The Forest Service has marked with flagging and/or wire flags the project centerline. Portions of the project to be reconstructed will be staked by the Forest Service. The flags, wire flags, hubs, and stakes constitute the field control from which the Contractor shall execute the work, and shall be left in place until the Engineer approves their removal.
(b) The Contractor shall do all further surveying, staking, and engineering to establish the horizontal and vertical control necessary to result in having the finished work comply with the lines and grades shown on the Plans or stated in the specifications. This work is incidental to the pay items.
(c) If any construction control points have been destroyed or displaced, or are erroneous, the Contractor shall promptly notify the Engineer. If these points are destroyed or displaced due to Contractor's negligence or operation, the cost for replacing them will be charged to the Contractor.
(d) In case of any construction changes, the Contractor shall cooperate with the Engineer and facilitate the prompt reestablishment of the field control for the adjusted work.
H-12 PROSECUTION OF WORK
(a) Construction activity shall be limited to the hours between 8 a.m. and 6 p.m., Monday through Friday, unless other hours are approved in writing by the Contracting Officer. The Contractor shall conduct activities so that interference with the public shall be kept at a minimum. The project site shall be open to
Bunkhouse Area Asphalt Project public access and free of hazards on weekends. Any activities requiring closure to the public shall be scheduled with the COR at least 7 days in advance.
(b) The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.
H-13 PROTECTION OF IMPROVEMENTS
Unless otherwise agreed to in writing, Contractor shall remove the existing traffic signs within the work area and reinstall to their approximate existing locations.
H-14 SANITATION REQUIREMENTS
Unless substitute measures or equipment are authorized in writing by the Contracting Officer, protection of air and water quality will include the use of approved chemical toilets by all persons engaged in road construction or in removing timber under this contract while they are within the boundaries of the Forest.
Such facilities shall be furnished by Contractor in quantities and at locations approved by the Engineer. No habitation or overnight dwelling by employees of Contractor will be permitted on National Forest land without advance written approval from the Contracting Officer.
H-15 FINAL CLEANUP
Contractor shall remove and dispose all of its own trash and refuse from the contract area. Material to be removed includes, but is not limited to camp refuse such as tin cans, aluminum foil, glass, paper, garbage, used engine oil, oil filters, oil cans, grease cartridges, etc. This Cleanup is a subsidiary item for which no special payment will be made. All debris shall be disposed off National Forest Land and in accordance with State and Local disposal requirements.
H-16 PROTECTION OF CULTURAL RESOURCES
Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1979 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by Forest Service. Forest Service may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object which is or may be entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas or objects by either party shall be promptly reported to the other party.
Contractor shall protect <> all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destruction, obliteration, removal or damage during Contractor's Operations. In accordance with 36 CFR 296.14(c), Contractor shall bear costs of restoration, provided that such payment shall not relieve Contractor from civil or criminal remedies otherwise provided by law.
Wheeled or track-laying equipment shall not be operated within such areas except on roads. Unless agreed otherwise, trees will not be felled into such areas.
H-17 AGAR 452.228-71 INSURANCE COVERAGE (NOV 1996)
Pursuant to FAR clause 52.228-5, Insurance - Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury.
Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
Bunkhouse Area Asphalt Project
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I-1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (DEC 2010) (Applicable if contract exceeds $30,000) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.217-7 Option for Increased Quantity -- Separately Priced Line Item (Mar 1989) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2011) 52.219-28 Post-Award Small Business Program Rerepresentation (Apr 2012) 52.222-3 Convict Labor (JUN 2003) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-8 Payrolls and Basic Records (JUN 2010) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-20 Walsh-Healy Public Contracts Act (OCT 2010) (Applicable if contract exceeds $15,000) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) (Applicable if contract exceeds $10,000) 52.222-26 Equal Opportunity (MAR 2007) (Applicable if contract exceeds $10,000) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) (Applicable if contract exceeds $10,000) 52.222-36 Affirmative Action for Workers with Disabilities (OCT 2010) (Applicable if contract exceeds
$15,000) 52.222-50 Combating Trafficking in Persons (FEB 2009) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
(Jul 2012) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) (Applicable if contract is awarded to an individual) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
(MAY 2008)
http://www.usda.gov/procurement/policy/agar.html
Bunkhouse Area Asphalt Project
52.223-18 Contractor Policy to Ban Text Messaging While Driving (Aug 2011) 52.224-1 Privacy Act Notification (APR 1984) 52.224-2 Privacy Act (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) (Applicable if contract exceeds $30,000) 52.228-11 Pledges of Assets (Jan 2012) (Applicable if contract exceeds $30,000) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) (Applicable if contract exceeds $30,000) 52.228-14 Irrevocable Letter of Credit (DEC 1999) (Applicable if contract exceeds $30,000) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003) 52.233-1 Disputes (JUL 2002) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR
1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)
Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984)
Alternate I (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)
Alternate I (APR 1984) Alternate II (APR 1984)
52.236-26 Preconstruction Conference (FEB 1995) 52.243-5 Changes and Changed Conditions (APR 1984) 52.244-6 Subcontracts for Commercial Items (DEC 2010) 52.245-1 Property Records (Apr 2012) 52.245-2 Government Property Installation Operation Services (Apr 2012) 52.245-9 Use and Charges (Apr 2012) 52.246-21 Warranty of Construction (MAR 1994)
Alternate I (APR 1984) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short From) (APR 1984) 52.249-10 Default (Fixed-Price Construction) (APR 1984)
Bunkhouse Area Asphalt Project
52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
(Applicable if contract is over $30,000) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
I-2 FAR 52.225-9 Buy American Act-Construction Materials (SEP 2010)
(a) Definitions. As used in this clause--
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means--
Bunkhouse Area Asphalt Project
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: “none”
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
Bunkhouse Area Asphalt Project
(c) Request for determination of inapplicability of the Buy American Act.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Bunkhouse Area Asphalt Project
Construction material description Unit of measure Quantity Price (dollars) * Item 1 Foreign construction material Domestic construction material Item 2 Foreign construction material Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
(End of clause)
I-3 FAR 52.228-13 Alternative Payment Protections (JUL 2000)
(a) The Contractor shall submit one of the following payment protections
(1) A payment…
This is the start of the file's text. The full file is on GovTribe.