Solicitation.pdf

PDF 651 KB Posted

Attached to
Tree Lining/Stream Restoration Federal contract opportunity
Solicitation number
AG-04N7-S-13-0040
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Tree Lining/Stream Restoration, newest first.
File Type Posted
MapSteamboatWatershed.pdf PDF
ReturnPacket.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

640854

PAGE 1 OF

2. CONTRACT NO.

3.AWARD/EFFECTIVE DATE 4. ORDER NUMBER 5. SOLICITATION NUMBER

RFQ AG-04N7-S-13-0040

6. SOLICITATION ISSUE

DATE

July 24, 2013

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME Linda C. Harmon Contracting Officer

b. TELEPHONE NUMBER (No collect calls) 541.618.2021

8. OFFER DUE DATE/

LOCAL TIME

August 19, 2013

4:00 PM - PST

9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED SET ASIDE 100 % FOR

USDA Forest Service Rogue River-Siskiyou National Forest 3040 Biddle Road Medford, OR 97504

SMALL BUSINESS WOMAN –OWNED SMALL BUSINESS (WOSB)

HUBZONE SMALL BUSINESS ELIGIBLE UNDER THE WOMEN OWNED SMALL

BUSINESS PROGRAM

SERVICE DISABLE VETERAN- EDWOSB-

VETERAN-OWNED SMALL

BUSINESS 8(A)

NAICS Code 115310 Size Standard $ 7 M

11. DELIVERY FOR FOB

DESTINATION UNLESS

BLOCK IS MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13A. THIS CONTRACT IS RATED

ORDER UNDER DPAS (15 CFR 700

13B. RATING

14. METHOD OF SOLICATION

RFQ IFB RFP

15. DELIVER TO CODE 16. ADMINISTERED BY CODE

Umpqua National Forest North Umpqua Ranger District Roseburg, OR 97470

See Block 9

17a. CONTRACTOR/ OFFERER

TELEPHONE NO. DUNS #____________________

FAX NO. TIN #_____________________

E-Mail Address: ________________________

18a. PAYMENT WILL BE MADE BY

USDA, OCFO, COD, APB

PO Box 60075 New Orleans, LA 70160

17b CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH

ADDRESS IN OFFER

18b. SUMBIT INVOICES TO ADDRESS SHOWN IN BLOCK 18A UNLESS

BLOCK BELOW IS CHECKED SEE ADDENDUM

19.

ITEM NO

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

Tree Lining/Stream Restoration

Umpqua National Forest

Insert your prices on the schedule of items – Section B.

25. ACCOUNTING AND APPROPRIATION DATA

JOB CODE

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5. ARE ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN ONE

COPY TO ISSUING OFFICE, CONTRACTOR AGREES TO FURNISH AND DELIVER

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

HEREIN

29. AWARD OF CONTRACT: REFERENCE RFQ AG-05G1-S-12-00XX

OFFER DATED . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET

FORTH HEREIN , IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

31a. UNITED STATES OF AMERICA (Signature Of Contracting Officer)

30b. NAME AND TITLE OF SIGNER (Type or Print)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or Print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE STANDARD FORM 1449 (Rev. 2/2012)

Prescribed by GSA-FAR (48CFR 53.212

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

When submitting your offer, see Section E – 212-1 addendum for instructions. Return to the address in block 9. On your sealed envelope, please write RFQ AG-04N7-S-13-0040.

Qutoes submitted are considered to be confidential. The name of the Contractor and the amount of the contract will be disclosed only after an award is made.

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ________________________________________

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER

34. VOUCHER NUMBER 35. AMOUNT VERIFIED

CORRECTFOR

36. PAYMENT

COMPLETE PARTIAL

FINAL

37. CHECK NUMBER

PARTIAL

FINAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER

FOR PAYMENT

42a. RECEIVED BY (Print)

41 b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41 c. DATE 42b. RECEIVED AT (Location)

42c. DATE RECD (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV.2/2012) BACK

Umpqua National Forest, North Umpqua Ranger District

AG-04N7-S-13-0040

SECTION B-- SCHEDULE OF ITEMS

*ITE

M

NO.

SUPPLIES/SERVICES EST

QTY UNIT UNIT

PRICE

TOTAL

2013 Steamboat Creek Watershed Instream Large Woody Material Restoration

1 Tree Lining and Tree Falling 25 Tree $________ $___________

TOTAL (ALL OR NONE) $___________

EST QTY = Estimated Quantity

Unit price is to include movement of personnel, equipment, supplies and incidentals to and from the project area from the Contractor’s base of operations or from a previous project site.

Work will be scheduled to occur between September 1st and October 30th, 2013. It is possible that work may occur outside of that time period if a waiver is necessary, requested, and granted.

Contract Performance time is: 14 calendar Days

Estimate start work: September 2, 2013

DUNS NUMBER: ________________________________________________________

TAX IDENTIFICATION NUMBER (TIN): __________________________________

EMAIL ADDRESS: ______________________________________________________

Electronic proposals to a Forest Service email account are not allowed and will be rejected.

For technical questions, contact Ron McMullin at: 541.496.3532

Offerors must respond to the other factors as described under FAR 52.212-2 Evaluation – Commercial Items. Award will be made on the best value for the Government.

Note: All prospective awardee shall be registered in the System for Awards Management (SAM) data base prior to award. Information on registration may be obtained via the internet at:

https://www.sam.gov/portal/public/SAM/

REGISTERED IN SAM? YES _____

No award shall be made to a Contractor not registered in the System for Awards Management.

https://www.sam.gov/portal/public/SAM/

CONTRACT CLAUSES

Block 27 of SF1449: The full text of a clause or provision may be accessed electronically at www.arnet.gov/far.

52.212-4 --CONTRACT TERMS AND CONDITIONS -- COMMERCIAL ITEMS (JUL 2013)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights --

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C.3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to the Contract Disputes Act of 1978, as amended (41 U.S.C. 601- 613). Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include --

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, contract line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer— System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer— Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt Payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected contract line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in Section 611 of the Contract Disputes Act of 1978 (Public Law 95- 563), which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period at fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by

33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts;

18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. 3701, et seq., Contract Work Hours and Safety Standards Act; 41 U.S.C. 51-58, Anti-Kickback Act of 1986; 41 U.S.C. 265 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. 423 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause.

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments.

(9) The specification.

(t) System for Award Management (SAM).

(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(2)

(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:

(A) Change the name in the SAM database;

(B) Comply with the requirements of Subpart 42.12 of the FAR;

(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the SAM database. Information provided to the Contractor’s SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.

(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via SAM accessed through https://www.acquisition.gov .

(u) Unauthorized Obligations. (1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End Use License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal https://www.acquisition.gov/ instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(1) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

ADDENDUM TO FAR 52.212-4

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.211-18 Variation of Estimated Quantity (APR 1984) 52.223-6 Drug-Free Workplace (MAY 2001) (Applicable if contract is awarded to an individual) 52.232-11 Extras (APR 1984)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.236-73 Archaeological or Historic Sites (FEB 1988) 452.237-70 Loss, Damage, Destruction or Repair (FEB 1988)

FOREST SERVICE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

AGAR 452.211-72 STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified) to perform the Performance Statement of Work, Investigation plan and Quality Assurance Surveillance Plan referenced in the attachments.

http://www.arnet.gov/far/ http://www.usda.gov/procurement/policy/agar.html

AGAR 452.211-75 EFFECTIVE PERIOD OF CONTRACT (FEB 1988)

Contract time will start on the effective date of the Notice to Proceed. Work shall begin no later than 5 calendar days after the effective date of the Notice to Proceed. The Contractor shall maintain progress at a rate which will assure completion within the contract time indicated below.

Estimated start work date and contract time is as follows:

ITEM NO. ESTIMATED START WORK

DATE

CONTRACT TIME

ALL 9/2/13 14 calendar days

NOTICE TO PROCEED

A Notice to Proceed will be issued in writing by the Contracting Officer or Contracting Officer's Representative (COR). No work shall begin until receipt of this notice. Contract time shall commence on the day indicated on the Notice to Proceed.

SCHEDULES FOR SERVICE CONTRACTS

Contractor shall, at the pre-work meeting or within 10 days from receipt of any subsequent request from the Contracting Officer, submit a time chart or schedule of proposed progress to insure completion of the work within the time set forth in the contract. If Contractor's progress falls behind that scheduled, the Contractor shall take such action as necessary to improve his progress; in addition, the Contracting Officer may require Contractor to submit a revised schedule and proposed plan of work to ensure completion of the work within the time(s) set forth in the contract.

CONTRACTOR QUALITY CONTROL PLAN

A. Quality Control Plan

The Contractor shall provide a Quality Control Plan (QCP) as part of this Proposal. The Plan must demonstrate how the Contractor shall assure that quality of performance meets the objectives and requirements of the contract. The QCP shall specify:

• How quality will be monitored to ensure performance standards are met.

• How the work will be supervised.

• Identify the personnel responsible for performing quality control.

• How results of the monitoring will result in quality performance.

• A system to ensure that the Contractor’s employees are notified of any deficiencies in their area of responsibility.

The contractor shall inspect all work performed under the terms of this contract.

B. Contractor Quality Control Inspection

The Contractor shall assure that performance meets contract specifications, in accordance with FAR 52.212-4, Contract Terms and Conditions -- Commercial Items, paragraph (a), prior to requesting the Government to inspect for payment or acceptance. The Contracting Officer may observe the Contractor’s inspection at any time and shall otherwise have unlimited access to the inspection data.

Failure by the Contractor to implement the approved plan and pursue it diligently from the commencement of the contract may be considered grounds for default.

INSPECTION AND ACCEPTANCE

GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN AND ACCEPTANCE

REQUIREMENTS

A. Government Quality Assurance Inspection. The Government will, at its convenience, make periodic inspections of the work to assure itself of contract compliance and to perform Quality Assurance Inspections to determine confirm that the Contractor is performing quality control in accordance with its QCP and that Contractor monitoring results in quality performance of contract objectives.

B. Acceptance. Acceptance of the work under the contract will be made after steps in (a) above have been taken and the Contracting Officer has made the determination of satisfactory compliance with the specifications. For acceptance purposes, complete reports as defined in Section D and offers proposal shall be satisfactorily completed before acceptance will be made. Acceptance will not be made for segments broken by unacceptable portions of work.

C. Rework and Reinspection after Rework. When inspections indicates that the performance objectives were not met, the work will be deemed unsatisfactory and payment will not be made until the Contractor has assured the Government that its Quality Control measures have corrected the deficiencies. Inspections after rework will be made in the same manner as the first inspection. The cost to the Government for inspections necessitated by the rework will be deducted from any payments to the Contractor.

AGAR 42.215-73 POST AWARD CONFERENCE (NOV 1996)

(a) A post award conference with the successful offeror is required. It will be scheduled within 5 days after the date of contract award. The conference will be held at: Umpqua National Forest 2900 NW Stewart Parkway, Roseburg, OR unless otherwise changed by mutual agreement.

Note: The Contractor designated representative or foreman (whomever the Contractor will have on the site) shall be present at the prework conference.

GOVERNMENT-FURNISHED PROPERTY

The government will provide the following item(s) of government property to the contractor for use in the performance of this contract. This property shall be used and maintained by the contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract:

Map(s) of project location that illustrate specific lining placement sites.

Site design plans for each lining, falling, and machine placement site.

Logs suitable for instream placement.

DEFINITIONS - ADMINISTRATION TERMS

A. Contracting Officer (CO) - The person executing this contract on behalf of the Government, including any duly appointed successor and authorized representatives of the Contracting Officer acting within the limits of his/her authority.

B. Contracting Officer's Representative (COR) - The on-site contract administrator for the Contracting Officer. The duties and responsibilities of the COR are defined a letter (form) of designation issued by the Contracting Officer.

C. Inspector - The person(s) appointed in writing by the COR to conduct and document inspections according to contract specifications and provisions. The inspector's authorities are strictly limited, not to exceed the authority to issue to the contractor a Notice of Noncompliance.

D. Calendar Days - Every day shown on the calendar, Saturdays, Sundays and holidays included.

E. Work Order - An order written by the COR, which directs the Contractor to correct deficient performance. It may also be used to document acceptable completion of units and to approve starting on additional work units.

F. Notice of Noncompliance - A written notice from the CO or COR which documents, for the Contractor's attention, specific performance deficiencies.

G. Contract Item - A pay item designated on the bid schedule and described by a specification.

H. Labor Standards Provisions - Those statutory and regulatory requirements pertaining to the Contractor's employees and employment practices.

I. Specifications - That portion of the contract comprising a description of the general and technical requirements for materials, products or services to be furnished under the contract.

DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE (COR)

A. The Contracting Officer will designate an individual as Contracting Officer's Representative (COR) at time of award.

B. The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by a proper contractual documents executed by the Contracting Officer prior to completion of the contract.

C. The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

D. On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

E. The COR's major duties and responsibilities are contained in the Forest Service Handbook of Contract Administration. The COR is delegated full authority under this contract except for the following actions which are reserved for the Contracting Officer:

1. Approve Change Orders and Modifications

2. Take action to terminate the contract for default or Government convenience.

3. Make contract adjustments under the Differing Site Conditions clause.

4. Grant extensions of contract time.

5. Approve assignment of claims.

6. Make final decisions under the Disputes clause.

7. Make final acceptance under the contract.

8. Make final decisions under the Suspension of Work clause.

9. Make equitable adjustments.

10. Authorize change in amount of Payment Retention.

11. Approve subcontractors.

12. Approve payments with deductions or final payment.

13. Approve use and possession prior to completion.

14. Enforce the warranty provisions.

NOTIFICATION OF SUBCONTRACTING

The Contractor shall promptly notify the Contracting Officer upon entering into any subcontract arrangement. The subcontractor shall have the experience and be equipped for such work. The written notification shall include as a minimum:

A. The name, address and telephone number of the subcontractor.

B. The date upon which the subcontract was entered into and its duration.

C. A detailed description of the work being subcontracted including a listing of contract items, units, etc., as appropriate.

D. Documentation of the subcontractor's representative authority.

E. Subcontracting any portion of the contract shall not relieve the Prime Contractor of any responsibility under this contract. Any subcontract agreement shall contain all terms and conditions of the prime contract.

PUBLIC OFFICIALS NOT PERSONALLY LIABLE

There shall be no personal liability upon the Contracting Officer or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.

SAFETY

FSAR 4G52.222-704 PERSONAL PROTECTIVE EQUIPMENT (FEB 2007)

The Contractor shall train workers in the safe operation and use of equipment that the worker may use before the worker begins using such equipment.

Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered which may cause injury or impairment in the function of any part of the body. Defective or damaged personal protective equipment shall not be used.

The Contractor shall provide chain saw chaps to each employee who operates a chain saw, at no cost to the employee. These chaps must be approved by an Underwriters Laboratory or meet Forest Service specification 6170-47. The chaps shall cover the full length of the thigh and shall extend to the top of the boot on each leg.

The Contractor shall assure that each employee wears foot protection that provides adequate traction and ankle support. Employees operating chain saws shall wear foot protection that is constructed with cut-resistant material which will protect the employee against contact with a running chain saw.

In any area where the worker is exposed to the potential for flying or falling objects, the Contractor shall provide a hard hat, at no cost to the employee, and the Contractor shall assure that the employee wears the hard hat. The hard hat must meet the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.

The Contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.

The Contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise for example, chain saw operation.

SAFETY PLAN

Prior to allowing any work to commence on the project, the Contractor shall submit a Safety Plan to the Contracting Officer that is in accordance with OSHA Regulations. Such safety plan shall include all tasks and related activities anticipated to successfully complete the work. The safety plan shall include the Personal Protective Equipment (PPE) that the Contractor provides for his/her employees at no cost to them.

It shall include how often the PPE is inspected to insure that it is not defective or damaged. It shall include steps the Contractor takes to insure that his/her workers are using the PPE on the worksite and what steps the Contractor uses if an employee is found to be working without the required PPE. The Contractor shall include any safety training he/she provides to his/her employees.

JOB SPECIFIC SAFETY PLAN

Prior to the prework meeting, the Contractor shall provide a written job specific safety plan that recognizes the inherently hazardous conditions that will exist on this contract. Some of these hazardous conditions are, but not limited to: blasting, heavy equipment operation, traffic control on haul routes, loading an unloading of materials, site security, noises and dust contract and the use of personal protective equipment (PPE) in the work area. The plan shall be in accordance with OSHA Regulations. The plan shall include all tasks and related activities anticipated to successfully complete the work

SAFETY ITEMS

(a) Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the work site.

(b) The following checked activities have been identified by the Government as potential safety hazards.

[] Confined Entry Space.

[] Temporary excavation/deep trenching/slope stability.

[X] Tree Felling.

[] Fall hazard from work heights exceeding six feet.

[] Blasting.

[] Traffic control on high-volume and/or high-speed and/or limited visibility roads.

[X] Heavy equipment operation.

[X] Tree climbing and/or tower climbing.

[] Fire hazards.

[] Hazard materials handling.

[] Electrical hazard.

[X] Hydraulic and/or pneumatic and/or other high pressure hazards.

[X] Mechanical hazards such as pulleys, springs, etc.

[X] Power tool operation including eye protection.

[X] Overhead hazards.

WARNING SIGNS AND RESTRICTIONS

Contractor shall be totally responsible for safety signing, barricades and other signing to maintain a safe site to the public and Government employees.

DAMAGES

If the Contractor does not complete the work within the designated contract time, actual excess costs will be assessed, such as - but not limited to, additional COR and Inspector time and travel.

CONTRACTOR'S REPRESENTATIVE

The Government may, at its option, suspend work with full count of contract time continuing, if the Contractor fails to provide a Contractor's Representative (1) conversant in the English language and (2) able to read and understand the contract.

SPECIAL EQUIPMENT CLEANING REQUIREMENTS -- PRE-ENTRY AND PRE-

DEPARTURE

All equipment (loaders, excavators, dump trucks, etc.) moved to the job site shall be cleaned of weeds and their seeds prior to each entrance onto the National Forest lands AND prior to each departure from the project area. “Project Area” means work sites and roads listed in the special project specifications or other “Road Use And Maintenance” clause in the contract. Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds.

Equipment shall be made available for visual inspection by the Forest Service prior to entering National Forest lands and prior to departure from the project area. Any equipment removed from the contract area during the duration of the contract must be steam cleaned or pressure washed before it is returned to the contract area. The Contractor shall advise of a proposed date for mobilization-to or demobilization-from the project area. The Contracting Officer and Contractor shall then mutually agree as to the time and location for inspection. The Contracting Officer or their representative shall be present to visually inspect and verbally approve the cleaning, prior to completion of mobilization onto the National Forest.

Special care shall be taken to assure removal of the following noxious weeds and their seeds:

Spotted knapweed (Centaurea maculosa), yellow starthistle (C. solstitialis), rush skeletonweed (Chondrilla juncea), purple loosestrife (Lythrum salicaria), scotch broom (Cytisus scoparius), diffuse knapweed (C.

diffusa), gorse (Ulex europaeus), tansy ragwort (Senecio jecobaea), and distaff thistle (Carthamus lanatus).

LANDSCAPE PRESERVATION AND HAZARDOUS MATERIALS

(a) The Contractor shall confine operations to within the clearing limits, immediate work area, or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

The Contractor shall make all reasonable attempts to preserve the scenic and natural environment within and adjacent to this project.

(b) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, lakes, reservoirs, and other surface waters.

(c) No petroleum products or other hazardous substances shall be released on or into land or rivers, streams, impoundments or other waters, or into natural or manmade channels leading thereto or there from.

Servicing of all equipment shall be done only in the areas approved by the Contracting Officer. The Contractor shall transport off government lands all waste oil, vehicle oil filters (drained of free-flowing oil), and oily rags and shall dispose of such materials in accordance with applicable State and Federal regulations.

(1) If the total on-site oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare and implement a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer. This plan shall include notification of appropriate state and local officials, the Contracting Officer and other appropriate agencies.

(2) At all on-site work areas (including Contractor storage, transfer, fueling, mixing sites, etc., for oil, oil products or any hazardous materials), the Contractor shall take appropriate preventive measures to insure that any release of hazardous products does not enter any stream or other waters of the United States or any of the individual States and shall conform to the federal, state and local regulations. Planned spill containment locations in stream courses shall be established prior to commencement of work activities.

These locations will be reviewed by the Contracting Officer or representative. When deemed appropriate, additional planned preventive measures shall be established for review by the Contracting Officer or representative.

(3) The Contractor, acting independently, shall immediately take action to notify the appropriate agencies including the Contracting Officer, and to contain and clean up, without expense to the Government, all petroleum products or other hazardous substance releases which are on or in the vicinity of the project and which are caused by the Contractor's employees, directly or indirectly. The Contractor shall have the necessary materials on site to contain a spill which may occur on land or within live streams as appropriate for any potential flow conditions likely to occur. This may require absorbent pads and/or booms, or other containment devices. In the event the Government determines that additional resources beyond those of the Contractor's are required, the Contractor may be held liable for all damages and costs including, but not limited to additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government for the containment and clean-up of petroleum products or other hazardous substance releases caused by Contractor's employees or resulting from or related to construction operations.

(4) The Contractor shall notify the Contracting Officer of any hazardous materials to be used on the job and shall have Material Safety Data Sheets (MSDS) for those materials available on the job.

INDUSTRIAL CAMPS

Forest Service regulations for Use of Campgrounds prohibit occupancy of developed recreation sites for other than primarily recreation purposes. No industrial camping will be authorized at these sites.

A special use permit is required on National Forest land for industrial camps. These permits are to be obtained by the Contractor through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor but may include use restrictions.

One self-contained camp unit will be allowed at each staging area and equipment or supply dump for use by a watchman.

PROSECUTION OF WORK -- WORK HOUR LIMITS -- WORK ITEM LIMITS

The Contractor shall conduct activities so that interference with the public shall be kept at a minimum.

All work shall be scheduled for between September 1 and October 30, 2013 unless an in-stream work period waiver is necessary, requested, and granted.

SUBMITTALS

The following submittals are required for this project:

Referenced by Contract clause or Time of Government Title Specification No. Approval After Submittal

Traffic Control Plan Use of Roads by Contractor clause 7 days

Safety Plan, including Accident Prevention clause n/a Blasting Plan, where [FAR 52.236-13] applicable

Engineered Spill Landscape Preservation and 2 days Prevention Plan Hazardous Materials clause

Fire Plan R6-FS-6300-52 part 2 n/a R6-FS-6300-55 and Certification that your Fire Tools and Equipment are in full compliance with the contract requirements

FINAL CLEANUP

Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.

AGAR 452.209-71 ASSURANCE REGARDING FELONY CONVICTION OR TAX DELINQUENT

STATUS FOR CORPORATE APPLICANTS (FEB 2012) ALTERNATE I (FEB 2012)

(a) This award is subject to the provisions contained in the Consolidated Appropriations Act, 2012 (P.L.

No. 112-74), Division E, Sections 433 and 434 regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –

(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and

(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.

(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434.

END OF ADDENDUM TO 52.212-4

52.212-5 -- CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES

OR EXECUTIVE ORDERS -- COMMERCIAL ITEMS. (JUL 2013)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement…

This is the start of the file's text. The full file is on GovTribe.