AG-0489-S-10-0258_kmrd-rd-south.pdf
PDF 630 KB Posted
- Attached to
- RECOVERY KMRD Road Storage South Federal contract opportunity
- Solicitation number
- AG-0489-S-10-0258
About this file
Solicitation (Section J Attachments have been uploaded separately. Bids are due by March 19 2010 at 2 00 pm PT)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| bid-abstract_kmrd-south.pdf | ||
| AG-0489-S-10-0258_kmrd-rd-south_amend2.pdf | ||
| AG-0489-S-10-0258_kmrd-rd-south_amend1.pdf | ||
| AG-0489-S-10-0258_kmrd-south_sectj.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
365957
US FOREST SERVICE
EROC NORTHWEST
16400 CHAMPION WAY
SANDY OR 97055
USDA FOREST SERVICE
EROC NORTHWEST
16400 CHAMPION WAY
SANDY, OR 97055
TONYA RYMER 503-668-1703
x
02/18/2010
AG-0489-S-10-0258
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
TAS::12 1102::TAS RECOVERY KMRD ROAD STORAGE SOUTH
This solicitation is issued under the provisions of the American Recovery and
Reinvestment Act of 2009.
NOTE:
(1) Bid bonds must be original and received by time of solicitation closing.
(2) This is a Competitive Hub-Zone Set-Aside procurement. All eligible and responsible Hub-Zone sources may submit a bid. Any questions about Hub-Zone eligibility should be directed to the Offeror's cognizant Small Business Administration Office.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 1010 calendar days and complete it within ________________ ________________ calendar days after receiving
Section F.2
03/19/2010
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
US FOREST SERVICE
EROC NORTHWEST
16400 CHAMPION WAY
SANDY OR 97055
TONYA R. RYMER
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
TABLE OF CONTENTS
KMRD ROAD STORAGE RECOVERY PROJECT
PART I – CONTRACT SPECIFICATIONS
• SECTION A -SF-1442
• SECTION B – Supplies or Services and Prices/Costs (Schedule of Items)
• SECTION C - Descriptions/Specifications/Statement of Work
• SECTION D- Packaging, Marking and Layout
• SECTION E - Inspection and Acceptance
• SECTION F - Deliveries and Performance
• SECTION G - Contract Administrative Data
• SECTION H - Special Contract Requirements
PART II – CONTRACT CLAUSES
• SECTION I - Clauses incorporated by reference
• AGAR/FSAR and SPECIAL CONTRACT CLAUSES
• ARRA Required Clauses (full text)
PART III – LIST OF DOCUMENTS,EXIBITS AND OTHER ATTACHMENTS
• SECTION J – Exhibits, Attachments, and Appendices
PART IV – REPRESENTATIONS AND INSTRUCTIONS
• SECTION K – Representations, Certifications and Other Statements of Offerors or Respondents
• SECTION L – Instructions to Offeror / Notices
• SECTION M – Evaluation Factors for Award
RECOVERY KMRD Road Storage South PAGE 2
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES
SCHEDULE OF ITEMS
KMRD Road Storage South
Ketchikan Ranger District
BASE ITEMS:
Item
Number Description
Unit
Estimated Quantity
Unit Price
Total
1.1 303(01) Roadway Reconditioning Mile 64.36 $_______ $__________
1.2*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated Bridge, Wood curbs, Sills and Backwalls
ROAD 8430050 MP 0.74
Lump Sum
1.3*
Structural Timber, 40’ Glue Laminated
ROAD 8430299 MP 0.08
1.4*
Structural Timber, 40’ Glue Laminated
ROAD 8446000 MP 4.49
1.5*
573(01) Minor Bridge Repair Road 8400000 Shoal Cove MP 26.848 (60'
MBS)
1.6*
573(01) Minor Bridge Repair Shelter Cove Road 8330000 MP 2.923 (70' MBS)
1.7*
Cove Road 8340000 MP 9.578 (70' MBS)
1.8*
Cove Road 8340000 MP 10.788 (60'
MBS)
1.9 802(01) Road Storage with drivable (pickup) waterbars
Mile 19.42 $_______ $__________
1.10 802(02) Road Storage with OHV waterbars
Mile 15.42 $_______ $__________
1.11 802(03) Road Storage with removed structures
Mile 7.86 $_______ $__________
1.12 807(2) Medium Sized Crawler Excavator with Operator
Hour 80 $_______ $__________
RECOVERY KMRD Road Storage South PAGE 3
1.13* 813(1) Spot Surfacing, Government Furnished, Compaction A
CY 100 $_______ $__________
1.14 833(1_24) 24 Inch Culvert Pipe, Contractor Furnish & Install
LF 36 $_______ $__________
1.15 833(1_36) 36 Inch Culvert Pipe, LF 36 $_______ $__________
1.16 833(1_48) 48 Inch Culvert Pipe, LF 40 $_______ $__________
1.17 833(1_60) 60 Inch Culvert Pipe, LF 44 $_______ $__________
1.18 861(01) Resurface Bridge Surface SF 1760 $_______ $__________
1.19* 151(01) Mobilization Shoal Cove LS 1 $_______ $__________
1.20* 151(01) Mobilization Shelter Cove LS 1 $_______ $__________
1.21* 151(01) Mobilization Upper Carroll Inlet LS 1 $_______ $__________
TOTAL
BASE
ITEMS
OPTION 1 ITEMS:
Item
Unit Price
Total
2.1*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated at Shoal Cove Road 8400000 MP 27.33
Each
2.2
Hour 32 $_______ $__________
OPTION
RECOVERY KMRD Road Storage South PAGE 4
OPTION 2 ITEMS:
Unit Price Total
3.1*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated at Shoal Cove Road 8430000 MP 6.519
3.2
Hour
OPTION 3 ITEMS:
Unit Price
Total
4.1*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated at Shoal Cove Road 8430000 MP 4.365
OPTION 4 ITEMS:
Unit Price
Total
5.1*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated at Shoal Cove Road 8440000 MP 1.571
RECOVERY KMRD Road Storage South PAGE 5
OPTION 5 ITEMS:
Unit Price
Total
6.1*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated at Shoal Cove Road 8440000 MP 2.181
OPTION 6 ITMES:
Unit Price
Total
7.1*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated at Shoal Cove Road 8400000 MP 31.437
OPTION 7 ITEMS:
Unit Price
Total
8.1*
571(06) Furnish and Install Treated Structural Timber, 40’ Glue Laminated at Shoal Cove Road 8400000 MP 31.608
B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under
151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted. *Denotes Contract Quantities
Vendor Name: Phone
Signature: Fax Address: Email City, State, Zip: TIN# Duns#
RECOVERY KMRD Road Storage South PAGE 6
SECTION C--DESCRIPTION/SPECIFICATIONS
C.1 Scope of Contract
The intent of the contract is to perform road maintenance activities. Work includes installing waterbars, excavate and sidecast road fill material, haul and place rock borrow, remove culverts and log bridges, clear brush from the roadway and drainage structure inlets, furnish and install culverts and bridges, excavate ditches, roadside brushing, and seeding and fertilizing exposed organic soils on and along roadsides on approximately 107 miles of National Forest System Roads on the Ketchikan Ranger District. The removed culverts and hardware become the property of the contractor and must be removed from the National Forest. The Contractor shall furnish all labor, materials, equipment, tools, transportation, supplies, and perform all work required to maintain the facilities in accordance with the attached typical drawings, supplemental specifications and parent specifications.
There are 3 separate Mobilization pay items in the contract. Work will be performed at Shoal Cove, Shelter Cove, and Carroll Inlet, at each of these sites Mobilization is a pay item. Mobilization progress payments for each work area will adhere to the percentages of work accomplished according to Specification 151, using the contract amounts for work at each specific work area.
Road storage work in this contract involves stabilizing roads regarding drainage. Work will include a combination of drainage structure removal, waterbar construction, excavating ditches, clearing the roadway and ditch of brush for project access and proper drainage, constructing temporary glulam bridges, and seeding and fertilizing bare organic soils.
Road storage work is payable on a per mile basis, regardless of the number of drainage structures removed or constructed for each mile, and the amount of seeding and fertilizing required. More than one type of waterbar will be constructed; some roads will have shallow waterbars to allow 2-wheel drive pickup travel. Some roads will have deeper waterbars designed for motorized off highway vehicles (OHVs) such as 4-wheelers. Some culverts, primarily in fish streams, will also be removed from these roads. A third type of road storage will include removing all existing drainage structures, including wood and metal culverts and bridges, and constructing additional waterbars where needed. Spacing between waterbars will be 200 to 750 feet apart on all types of road storage. Refer to the drawings and workog in Section J for details on each project road. The structures listed in the worklogs represent known locations of drainage structures. Additional structures may be located during the project, any work associated with additional structures located during the project on project roads is considered incidental to the rest of the project work. Interested bidders are encouraged to visit the work sites.
The contract also includes work on roads to remain open to motorized traffic. This work is required for project access and public safety. This work includes roadside brushing with a rotary brusher, ditch and drainage structure maintenance, culvert installations, and minor bridge repair. Roadside brushing will be Method B. Payment for most of this work is also by the mile (Roadway Reconditioning). For estimation purposes, ditch excavation will average about 1000 feet per mile, and no explosives will be needed for ditch reconstruction. Borrow excavation necessary for structure installation and road repair is considered incidental to other pay items in the project and will not be separately payable unless shown in the Schedule of Items.
RECOVERY KMRD Road Storage South PAGE 7
In-stream timing restrictions are included in the contract for work in streams with fish populations. Refer to Section H for times and locations where this will affect work scheduling.
Several 40’ treated glue-laminated bridges are included in the contract. The drawing for a typical installation is included in Section J. Locations where these structures are to be installed are typically over streams less than 5’ wide with total fill heights of less than 8’. All sites are on existing roads and serve as replacement structures over small fish streams. Structural excavations for bridge foundations are expected to be much less than for new installations.
Optional work in the contract includes removing existing structures and furnishing and installing additional 40’ glue-laminated bridges on existing roads as replacement structures at Shoal Cove.
The Contractor shall assume all risk, loss, damage, or expense arising out of prosecution of the work, except as otherwise provided in the contract.
The Government estimate is between $1,000,000 and $5,000,000 for the base and all options.
C.2 Description and Location
The project is located on Revilla Island in southeast Alaska. The forest road systems at Shoal Cove, Shelter Cove, and Upper Carroll Inlet are remote, accessible by either saltwater or air travel.
Ketchikan is the nearest full service community to the work sites.
C.3 Signing and Safety
(a) A reflectorized SLOW MOVING VEHICLE emblem shall be attached to any equipment not designed to maintain a safe travel rate or that will be moving at a slow rate while performing maintenance.
(b) It shall be the Contractor’s responsibility to furnish black and orange reflectorized maintenance warning signs to alert motorists of maintenance operations. A minimum of one (1) sign at each end of road sections under construction shall be kept in place at all times and shall be moved as work progresses in accordance with the Manual of Uniform Traffic Control Devices.
C.4 Technical Specifications
STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON
FEDERAL HIGHWAY PROJECTS, FP-03, U.S. Customary Units
The specifications are included by reference only. The requirements contained in these Standard Specifications are hereby made a part of this solicitation and any resulting work.
These specifications can be ordered from FHWA. For information on how to order books, go to the FHWA’s website, http://www.wrl.fha.dot.gov/design/specs/fp03.htm.
http://www.wrl.fha.dot.gov/design/specs/fp03.htm�
RECOVERY KMRD Road Storage South PAGE 8
Preface
Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions 101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
http://www.nist.gov/�
RECOVERY KMRD Road Storage South PAGE 9
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
RECOVERY KMRD Road Storage South PAGE 10
Figure 101-1—Illustration of road structure terms.
RECOVERY KMRD Road Storage South PAGE 11
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005 102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work 103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work 104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005 Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
RECOVERY KMRD Road Storage South PAGE 12
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
RECOVERY KMRD Road Storage South PAGE 13
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress 108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
201 - Clearing and Grubbing 201.01_tong_us_06_09_2008
201.01 Description
RECOVERY KMRD Road Storage South PAGE 14
Replace with the following This work consists of clearing brush and trees for equipment access and to improve drainage along older single lane logging roads. Clearing widths will be kept as narrow as needed for moving equipment along the roadway. Brush and slash around existing drainage structures shall be removed a minimum of 5 horizontal feet from structure inlets. All slash and debris resulting from clearing operations will be removed from ditches to not impede drainage patterns.
203 - Removal of Structures and Obstructions 203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
204 - Excavation and Embankment 204.14_1005_us_01_18_2005
Delete Section 204 in its entirety and replace with the following:
204.01 This work consists of excavating material and constructing embankments. This includes furnishing, hauling, stockpiling, placing, disposing, sloping, shaping, compacting, and finishing earthen and rocky material.
204.02 Definitions.
(a) Excavation. Excavation consists of the following:
(1) Roadway excavation. All material excavated from within the right-of-way or easement areas, except subexcavation covered in (2) below and structure excavation covered in Sections 208 and 209. Roadway excavation includes all material encountered regardless of its nature or characteristics.
(2) Subexcavation. Material excavated from below subgrade elevation in cut sections or from below the original groundline in embankment sections. Subexcavation does not include the work required by Subsections 204.05, 204.06(b), and 204.06(c).
(3) Borrow excavation. Material used for embankment construction that is obtained from outside the roadway prism. Borrow excavation includes unclassified borrow, select borrow, and select topping. Borrow excavation is available in various borrow sources located on the project sites, it will not be necessary to drill and shoot rock to produce borrow excavation. It will be necessary to excavate within the confines of existing borrow sources in order to produce borrow. Payment for borrow is incidental to other work.
(b) Embankment construction. Embankment construction consists of placing and compacting roadway or borrow excavation. This work includes:
(4) Preparing foundation for embankment;
(5) Construction roadway embankments;
(6) Benching for side-hill embankments;
RECOVERY KMRD Road Storage South PAGE 15
(7) Constructing dikes, ramps, mounds, and berms; and
(8) Backfilling subexcavated areas, hope, pits, and other depressions.
(c) Conserved topsoil. Excavated material conserved from the roadway excavation and embankment foundation areas that is suitable for growth of grass, cover crops, or native vegetation.
(d) Waste. Excess and unsuitable roadway excavation and subexcavation that cannot be used.
204.11 Compaction.
(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment over the full width of each layer until visible deformation of the layer ceases or, when a sheepsfoot roller is used, the roller walks out” of the layer. Make at last three complete passes.
204.13 Sloping, Shaping, and Finishing.
(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify the 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until visible displacement ceases.
(3) Method C. For roads designated as Construction Tolerance Class K, L, of M, finish the roadbed by spreading the excavation. Eliminate rock berms.
303-Road Reconditioning
Delete Section 303 in its entirety and replace with the following:
303.01 This work consists of reconditioning ditches, shoulders, and roadbeds.
Construction Requirements
RECOVERY KMRD Road Storage South PAGE 16
303.02 Ditch Reconditioning. Remove all slide material, sediment, vegetation, and other debris from the existing ditches and culvert inlets and outlets. Pull any trees over 3 inches in diameter. Reshape ditches and culvert inlets and outlets to achieve positive drainage and a uniform ditch width, depth, and grade. Dispose of waste on the downhill side of the road away from any live streams.
303.03 Shoulder Reconditioning. Repair soft and unstable areas according to Subsection 204.07.
Remove all trash, slide material, wind thrown logs, trees, and other debris from existing shoulders including shoulders of parking areas, turnouts, and other widened areas. Pull any trees over 3 inches in diameter. Reshape shoulders and dispose of waste as directed on the ground by the engineer.
303.04 Roadbed Reconditioning. Repair holes and unstable areas according to Subsection 204.07.
Remove all slide material, trash, wind thrown logs, tops, limbs, and other organic debris from the road bed. Remove brush from roadway and road sides according to Subsection 842 Method B.
Dispose of waste material as directed on the ground by the engineer.
303.05 Roadway Reconditioning. Perform all applicable work described in Subsections 303.02 through 303.05.
303.06 Acceptance. Road reconditioning work will be evaluated under 106.02.
Measurement
303.07 Measure the Section 303 items listed in the bid schedule according to 109.02j.
Payment
303.08 The accepted quantities will be paid at the contract price per unit of measurement for the
Section 303 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05
557 - Timber Structures 557.04_1005_us_05_20_2005
557.04 Treated Timber.
Replace the first sentence of the third paragraph with the following:
Use a copper naphthenate solution containing a minimum of 2 percent copper metal for field treatments of material originally treated with copper naphthenate, pentachlorophenol, creosote, creosote solution, or waterborne preservatives, unless specified otherwise in the contract. Impregnate all holes using equipment suitable for proper application of the preservative.
Add the following Subsection:
557.04A Untreated Timber. Coat the following untreated timber surfaces in accordance with AWPA M4:
(a) All ends and tops, and all contact surfaces of posts, sills, and caps.
(b) All ends, joints, and contact surfaces of bracing and truss members.
(c) All surfaces of timber bumpers and the back faces of bulkheads.
(d) All other timber that will be in contact with earth.
RECOVERY KMRD Road Storage South PAGE 17
557.06 Bolts and Washers.
Add the following to the first paragraph:
Do not galvanize glued laminated deck panel dowels.
Add the following to the second paragraph:
Place cut washers under nuts at steel surfaces. Malleable washers are not required under economy head bolts.
557.09 Framing Bents.
Add the following at the end of the Subsection:
Fasten posts to pedestals with dowels not less than 11/16-inch in diameter that extend at least 6 inches into the posts, or with other types of connectors as specified in the contract. Fasten posts to sills using one of the following methods, as specified in the contract:
(a) With dowels not less than 11/16-inch in diameter that extend at least 6 inches into posts and sills.
(b) With drift bolts not less than 11/16-inch diameter driven diagonally through the base of the post and extending at least 7 inches into the sill. Drive drift bolts into holes at a 45° angle to enter the post at least 6 inches above the post base.
(c) With other types of connectors as specified in the contract.
Treat, furnish, and drive timber piles in accordance with Section 551.
Add the following Subsection after the end of Subsection 557.14, and renumber Subsections 557.15 through 557.21 in the parent Specification to Subsections 557.16 through 557.22:
557.15 Glued Laminated Panel Decks. Do not drag or skid panels. When lifted, support panels in the weak-moment plane at a sufficient number of points to avoid overstressing, and protect the edges from damage.
When dowels are specified in the contract between deck panels, use a template or drilling jig to ensure that dowel holes are accurately spaced and drilled parallel to one another and to the horizontal surfaces of the panel. Drill holes to a depth ¼ inch greater than one-half the dowel length, and of a diameter that is 1/16 inch greater than the dowel, unless otherwise specified in the contract. Use a temporary dowel as a check for snug fit prior to production drilling. Use dowels of the size specified in the contract, with the tips slightly tapered or rounded. Use an approved lubricant to facilitate the connection process.
Start the tips of all dowels partially and equally into the holes of the two panels being joined. Draw the panels together keeping the edges parallel, until the panels abut tightly. Securely fasten each panel to each stringer as specified in the contract.
Assemble and match-mark panels prior to delivery to the construction site when specified in the contract. Follow erection procedures given in FPL-263, Forest Service, Forest Products Laboratory (FPL), Madison, Wisconsin.
571 - Prefabricated Bridges 571.00_nat_us_03_15_2005
RECOVERY KMRD Road Storage South PAGE 18
571.01 This work consists of designing, fabricating, delivering, and installing a prefabricated modular bridge superstructures, or transporting and installing Government-furnished prefabricated, modular superstructures and components. The work also includes constructing caps, bearings, and abutments including excavation and backfill and anchoring bridge superstructures to abutments as required
Materials
571.02 Requirements. Furnish materials that meet the requirements specified in the following sections:
Bridge Railing 556 Structural Metal 717 Prestressed Concrete 553 Reinforcing Steel 554 Steel Structures 555 Structural Concrete 552 Timber Structures 557 Material for Timber Structures 716 Concrete compressive strength, structural steel tensile strength, finish and designation, timber species, grade, and treatment, and other material specifications shall be as required or if not listed in the contract documents, take them from the manufacturer’s drawings, and have them approved by the CO prior to fabrication.
Construction Requirements
571.03 Design Requirements. For required loadings use the most recent AASHTO “Standard Specifications for Highway Bridges”.
When design of the structure is required, submit plans and calculations signed by a professional engineer registered in the state where the bridge will initially be located or in the state where the fabricator’s offices are located.
Use durable materials to allow removal, transportation, and re-installation without using specialized construction equipment. When required, design bridges to allow transportation by air or pack animals and complete construction by manual labor. Use design techniques and fabrication methods to minimize field installation difficulties. Fabricate primary components from steel.
Rig main superstructure components with permanent lifting devices to facilitate efficient installation and removal of these items. Place lifting devices so as not to interfere with traffic.
571.04 Design Drawings. When furnishing a prefabricated bridge superstructure, submit design drawings, calculations, or shop drawings at least 21 days in advance of the start of fabrication to allow time for review and correction of any changes and approval by the CO. Include plan, elevation, and section views of the modular bridge superstructure, dimensions of all components, welding and connection details, and general and specific notes regarding design and construction.
When Government-furnished prefabricated bridge superstructure components are specified, material lists, installation information, and manufacturer’s instructions will be furnished by the Government.
571.05 General. Perform excavation, backfill, and embankment work under Sections 204 and 209.
Dispose of all debris resulting from operations in accordance with Section 203.
571.06 Performance. Notify the CO at least before delivering the bridge.
RECOVERY KMRD Road Storage South PAGE 19
If the prefabricated superstructure is not installed immediately upon delivery to the project site, provide appropriate equipment and labor to unload and stack, support, and store all material at the delivery point.
Support and stack all components to prevent damage. Furnish and install blocking to support all components at least 12 inches above the ground.
Furnish all tools, devices, special equipment, and material needed for installation in well-marked watertight containers suitable for long-term, outdoor storage.
571.07 Abutments and Approaches. Construct required caps, bearing, and abutments according to Division 500. Construct approaches including excavation and backfill according to sections 204 and 209.
571.08 Contractor-Furnished Prefabricated Bridge Superstructure. Furnish the following items for approval prior to delivery of the bridge component:
(a) Supplier or inspection agency certification of wood species and grade of all timber and a conformance certificate for all sawn and glued laminated members.
(b) Certification by an approved inspection and testing agency of wood treatment, listing method of treatment, type of preservative, retention, and penetration. Supplier certification is permitted if each piece is stamped or branded with a legible American Wood Preservers Bureau quality mark.
(c) Certification of structural steel, fasteners, and hardware.
(d) Certification of galvanizing process used.
(e) Steel fabricator certification that steel fabrication and quality control meet the requirements of the AISC Code of Standard Practice; and that all welding meets the requirements of ANSI/AASHTO/AWS D 1.5 Bridge Welding Code.
(f) A complete list of all bridge components, hardware, and fasteners.
(g) Complete instructions and drawings. Provide drawings that are black line, of reproducible quality, on ANSI sheet size D (24 inches by 36 inches). Furnish the same information in an approved electronic format.
Mark each major component of the bridge superstructure with the same permanent serial number in a location that is clearly visible, both when stacked in storage and erected at the site.
Assemble bridge superstructure prior to delivery to assure proper fit-up of all components. Notify the CO of the assembly 2 weeks before assembly.
571.09 Government-Furnished Prefabricated Bridge Superstructure. For Government-furnished prefabricated bridge units, transport all material from the storage site(s) to the bridge site, and install the superstructure complete and in place, including connection of all girders, diaphragms, railings, panels, transoms, and other elements.
Upon taking possession of the Government-furnished units at the storage site, assume liability for damage resulting from handling, transporting, or erecting the units in place, until final acceptance of the project.
571.10 Non-pressure Epoxy Grout Anchors. Furnish non-pressure epoxy grout to cement anchor dowels and bolts. At least 15 days prior to use submit for approval manufacture’s test information on the non-pressure epoxy grout proposed for use.
Immediately prior to placing dowels or bolts, clean drill hole of dust and other material. Fill hole halfway with grout. Insert dowels by rotating it though one complete turn while tapping it down. Insert bolts according to manufacture’s instructions. If necessary add more grout to fill the hole.
RECOVERY KMRD Road Storage South PAGE 20
571.11 Acceptance. Furnish a production certification for timber, including glued-laminated lumber, structural steel, and fabricated steel. Furnish a certification for all wood treatment, fasteners, hardware, galvanizing processes, and non-pressure epoxy grout.
Measurement
571.12 Measure the Section 571 items listed in the bid schedule according to Subsection 109.02.
Payment
571.13 The accepted quantities, measured as provided in Subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 571 pay items listed in the bid schedule.
Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
573 - Bridge Repair 573.00_nat_us_05_12_2004
Description
573.01 This work consists of minor bridge repair and the repair of other concrete structures.
Material
573.02 Conform to the following Subsections:
Air-entraining admixtures 711.02 Chemical admixtures 711.03 Coarse aggregate 703.02 Curing material 711.01 Fine aggregate 703.01 Fly ash 725.04 Joint fillers 712.01 Portland cement 701.01 Precast concrete curbing 725.06 Precast concrete units 725.11 Reinforcing steel 709.01 Structural steel 717.01 Water 725.01 Epoxy Resin Adhesives 725.21
Construction Requirements
573.03 General. Perform excavation and backfill work under Section 209.
a) Concrete Removal: Remove loose concrete from the designated areas. Use jack hammers that weigh less than 30 pounds. Use chipping hammers that weigh less than 15 pounds to remove concrete from beneath reinforcing bars. Operate jack hammers and mechanical chipping tools at an angle less than 45 degrees from the slab surface.
Use hand tools (hammers and chisels) to finish the cavity.
RECOVERY KMRD Road Storage South PAGE 21
Inspect the cavity for remaining defective concrete by tapping with a hammer or steel rod on the concrete and listening for dull or hollow sounds. Dull or hollow sounds indicate defective concrete. In areas where tapping produces a dull or hollow sound, remove additional concrete until tapping produces a solid tone. Make the entire cavity at least 1 inch deep. Saw cut edges of cavity to avoid feather edging.
Prepare surface of cavity by sandblasting, grinding, or water blasting. Remove dust, dirt, and loosely bonded material resulting from cleaning. Allow cavity surfaces to dry.
For spalls to be repaired that are adjacent to joints and existing cracks insert preformed joint filler to the working faces of the spall. Trim filler to fit shape of the working faces of joint or crack so epoxy material is prevented from bypassing filler. Where practicable, extend filler horizontally and vertically into joint or crack opening. Secure filler strip in place prior to and during placement of epoxy concrete.
Apply a bond breaker to working faces at keyed joints. Keep bond breaker off of concrete surface to be bonded. After the epoxy concrete has completely cured, saw out the top 1 inch of the preformed joint filler and install liquid joint sealer.
(b) Reinforcing Steel: Clean all exposed reinforcing steel that is to remain in place. Remove all rust and corrosive products, including oil, dirt, concrete fragments, laitance, loose scale, and other coating of any character that would destroy or inhibit the bond with the new concrete.
When cleaned reinforcing steel will be exposed for more than seven days before placing the concrete, protect the steel from corrosion and contamination. Clean or replace all corroded or contaminated reinforcing steel.
Prevent cutting or damaging reinforcing steel designated to remain in place. Repair or replace any damaged bars.
(c) Forms: Design and construct forms that are free of bulge and warp and allow for removal without injuring the concrete. When concrete contains a retarding admixture, fly ash, or other pozzolan replacement for cement, design the forms for a lateral pressure equal to that exerted by a fluid weighing
2.5 tons per cubic yard.
Use wood, metal, or other suitable material for forms. Keep forms clean and coat with a form release agent or form oil before placing concrete.
Place and fasten reinforcing steel according to Subsection 554.08.
573.04 Epoxy Concrete and Mortar Composition:
Use the appropriate epoxy grout for the application.
Surfaces where a non- sagging epoxy resin is needed:
ASTM C 881, Type III, Grade 1 or 2, Class B or C without mineral filler. For walls and ceilings use ASTM C 881, Type III, Grade 3, Class B or C with filler.
Non-Pressure Epoxy Grout:
ASTM C 881 Type IV, Grade [2] [3], Class [B] [C] with or without mineral filler.
Crack Sealer for Pressure Grouting:
ASTM C 881, Type IV, Grade 1, Class [B] [C] without filler.
Crack Surface Sealer for Pressure Grouting:
ASTM C 881, Type IV, Grade 3, Class [B] [C] with mineral filler.
Aggregate: Provide dry aggregate. For material passing No. 200 sieve provide a non-plastic material composed of a minimum of 75 percent limestone dust, talc or silica inert filler. Epoxy concrete: Furnish
RECOVERY KMRD Road Storage South PAGE 22 fine aggregate meeting the requirements of 703.01. Epoxy mortar: Furnish fine aggregate meeting the requirements of AASHTO M-45.
Job Mix Formula: At least 15 days before work commences, submit a job-mix formula for each use of epoxy concrete or epoxy mortar. Include test reports with the mix design. Identify the source of the materials and include the proportions of aggregates and epoxy resin. When determining job mix, use samples of materials to be used on the job.
573.05 Mixing and Placing Materials.
Make batches small enough to ensure placement before binder sets. Mix materials according to manufacturer's recommendations.
Halt work when weather conditions detrimentally affect the quality of patching or bonding concrete.
Apply epoxy resin materials only when the contact surfaces are completely dry and if the atmospheric and surface material. Follow manufacturer's instructions for weather conditions and temperature ranges.
Do not permit vehicular or heavy equipment traffic on the pavement in the work area during the curing period.
(a) Epoxy Concrete: Prime dry cavity surfaces with epoxy resin using a stiff bristle brush. Make coating approximately 0.02 inch thick. Place epoxy concrete while primer is still tacky and in layers not exceeding 1 inch thick. Use vibratory floats, plates, or hand tampers to consolidate the concrete. Level each layer and screed the final surface to match the adjoining surfaces. Remove excess epoxy concrete on adjacent surfaces before the concrete hardens. Do not feather epoxy concrete out onto adjacent surfaces.
(b) Epoxy Mortar: Prime surfaces with epoxy resin binder. Scrub prime coat into surface with a stiff bristle brush. Make coating approximately 0.02 inch thick. Place epoxy mortar while primer is still tacky. Apply at a thickness recommended by the manufacturer. Work mortar into place and consolidate thoroughly so that contact surfaces are wetted by the mortar. Finish surface of mortar to the required texture. Do not feather epoxy mortar onto adjacent surfaces.
(c) Cementing Dowels: Immediately prior to placing the dowel, clean hole of dust and other deleterious material with high pressure air. Fill hole halfway with grout. Insert dowel in hole and rotate it at least one complete turn while tapping it down. If necessary add more grout to fill hole.
(d) Epoxy Grout for Cracks: Apply epoxy grout at a thickness recommended by the manufacturer.
Work grout into place and consolidate thoroughly so that contact surfaces are wetted by the grout. Finish surface of grout to the required texture. Do not feather epoxy grout onto adjacent surfaces.
(e) Pressure Grouting of Cracks: Clean each crack of dust, dirt, loose concrete and unsound material.
Insert a valve at both ends of each crack, at the junction of two cracks, and along the length of each crack at 20 inch intervals. Apply crack surface sealer between the valves. After crack surface sealer has hardened and cured, pump crack sealer into valve at one end of crack. For vertical surfaces start at lowest valve and work upwards. As crack sealer appears at next valve, pinch closed pumping valve and move to next valve and commence pumping. Continue procedure until other end of crack is reached.
Avoid delays in pumping operation. After crack sealer has hardened and cured grind valves off flush with concrete surface. Coat areas around valves with crack surface sealer and allow to harden and cure.
RECOVERY KMRD Road Storage South PAGE 23
(f) Curing: Cure epoxy materials according to manufacturer's recommendations. Furnish a representative sample of each batch of epoxy resin and aggregate. Clearly identify samples by designated name, specification number, batch number, project contract number, intended use and quantity involved. Check each repaired area for cracks, spalls, popouts and loss of bond between repaired area and surrounding concrete. Check each repaired area for voids by tapping with a hammer or steel rod and listening for dull or hollow sounds. Immediately repair defects.
573.06 Acceptance. Material for minor concrete structures including concrete, reinforcing steel, and structural steel for minor structures will be evaluated under Subsections 106.02 and 106.03. For confirming commercial certifications of compressive strength, AASHTO T 23 is modified to allow the 28-day cure in a waterproof mold.