CONN CREEK SECT J PG 19.pdf

PDF 30 KB Posted

Attached to
RECOVERY--CONN CREEK BRIDGE REPLACEMENT Federal contract opportunity
Solicitation number
AG-0489-S-10-0187
Issued by
Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center Northwest

About this file

Section J Page 19

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY--CONN CREEK BRIDGE REPLACEMENT, newest first.
File Type Posted
CONN CREEK AMEND 1_SF30.pdf PDF
CONN CREEK SOLICITATION.pdf PDF
CONN CREEK SOLICITATION_SECT J.pdf PDF
Conn Cr Br_Sheet01_Title.pdf PDF
CONN CREEK SOLICITATION_SECT J.pdf PDF
Conn Cr Br_Sheet07_Bridge Plan and Prof.pdf PDF
Conn Cr Br_Sheet02_Location Map.pdf PDF
SECT J 4 ARRA SIGN REQs.pdf PDF
Conn Cr Br_Sheet04_General Notes.pdf PDF
CONN CREEK SOLICITATION.pdf PDF
Conn Cr Br_Sheet05_Typical Sections.pdf PDF
Conn Cr Br_Sheet03_Summary Qtys.pdf PDF
Conn Cr Br_Sheet08_Stream Prof.pdf PDF
Conn Cr Br_Sheet06_Bridge Layout.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RECOVERY—CONN CREEK BRIDGE REPLACEMENT (SECTION J)

(a) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(b) Keep temporary traffic control devices clean.

(c) Remove all temporary traffic control devices upon contract completion or when approved.

(d) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags.

Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

Table 156-1

Temporary Road Closures

Road

Number

From

Terminus

(Milepost)

To

Terminus

Maximum

Consecutive

Days of

Closure

Minimum

Consecutive

Days Open

2430 0.0 1.1 7 All Other

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.

157 - Soil Erosion Control 157.03_nat_us_02_24_2005

157.03 General

Delete the first two paragraphs and add the following:

Prior to the start of construction, submit an Erosion Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction according to the contract specifications, contract permits, Section 107, and this Section. Contract permits amend the requirements of this Section. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the

Contracting Officer for approval. Do not begin work until the necessary controls for that particular phase of work have been implemented. Incorporate all permanent erosion control features into the