questions_tonka_surfacing.doc

DOC document 109 KB Posted

Attached to
RECOVERY - Tonka Surfacing Phase II Federal contract opportunity
Solicitation number
AG-0489-S-09-0002
Issued by
Department of Agriculture Forest Service R10-Alaska Region

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY - Tonka Surfacing Phase II, newest first.
File Type Posted
bid_abstract_tonka_surfacing_phase_2.pdf PDF
sf-30_mod_two.doc DOC document
AG-0489-S-09-0002_tonka-surfacing_bid-pack.pdf PDF
AG-0489-S-09-0002_tonka-surfacing_complete-solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-0489-S-09-0002 Recovery – Tonka Surfacing Phase II

Amendment No. 1

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1
2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
One (1)
April 15, 2009
6. ISSUED BY
CODE
7. ADMINISTERED BY (If other than Item 6)
CODE

Tongass National Forest

Fed. Bldg., 648 Mission St.

Ketchikan, AK 99901

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code)
(X)
9A. AMENDMENT OF SOLICITATION NO.

FORMCHECKBOX

AG-0489-S-09-0002

RECOVERY – Tonka Surfacing Phase II

9B. DATED (SEE ITEM 11)

03/27/2009

FORMCHECKBOX

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FORMCHECKBOX

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers FORMCHECKBOX is extended, FORMCHECKBOX is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

FORMCHECKBOX

FORMCHECKBOX

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

FORMCHECKBOX

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

FORMCHECKBOX

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor FORMCHECKBOX is not, FORMCHECKBOX is required to sign this document and return

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

Additional Information - Answers to contractor questions.

This solicitation closing date is NOT extended.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Tonya Rymer, Contracting Officer

15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
16C. DATE SIGNED

(Signature of person authorized to sign)

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105
STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Question (1) – Was the contractor who was awarded Tonka Surfacing Phase I awarded any of the option items?

Answer – The Base plus Option Item One have been awarded to date on that contract.

Question (2) – Has the contractor for Phase I begun any part of their work?

Answer – No work has yet started on this contract.

Question (3) – If Phase II is awarded, can a contractor begin work right away or does he have to wait until Phase I is completed?

Answer – One contract is not expected to interfere with the other.

File details come from the government source that posted it. Updated .