SissonsRFP.docx
DOCX document 126 KB Posted
- Attached to
- IPNF, CdA River RD, Sissons Bridge Rehabilitation Federal contract opportunity
- Solicitation number
- AG-02RC-S-17-0136
About this file
RFP solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PAST_PERFORMANCE_SURVEY.docx | DOCX document | |
| SF24BidBondFillForm.pdf | ||
| 5_SissonsFinalDrawings.pdf | ||
| WorkersCompForm.docx | DOCX document | |
| 6_SissonsFinalFSSS.docx | DOCX document | |
| WageDecisionID170084.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION AG-02RC-S-17-0128 Page 3 of 44
CONSTRUCTION AG-02RC-S-17-0136 Page 40 of 44
OFFEROR'S COPY
NOTE: Attached forms must be completed and submitted intact.
Issuing Office:
USDA – Forest Service Region 1, Acquisition Management Idaho Montana Acquisition Team 3815 Schreiber Way Coeur d Alene, ID 83815
Offers Are Solicited For:
Sissons Bridge Rehabilitation Idaho Panahandle National Forests Coeur d Alene River Ranger District
| Solicitation No. RFP AG-02RC-S-17-0136 |
| HELP PREVENT FOREST FIRES |
IMPORTANT - NOTICE TO OFFEROR
1. This is a complete copy. Information and instructions for submission of proposals as well as contract provisions and specifications are contained in this OFFEROR REFERENCE COPY. This copy should be retained by offerors.
2. Note: An offer guarantee (Bid Bond) IS REQUIRED. Performance and Payment Bonds will be required of the successful offeror. (See Section I, FAR Clause 52.228-15.)
FS-6300-45 (11/79)
CONSTRUCTION RFP AG-02RC-S-17-0136
TABLE OF CONTENTS
Page(s)
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM 1 - 2
Standard Form 1442, Solicitation, Offer, and Award
SECTION B - SUPPLIES OR SERVICES AND PRICES 3
| B- 1 - Schedule of Items |
| B- 2 - Payment for Bond Premiums |
SECTION C - DESCRIPTION/SPECIFICATIONS 4-6
| C- 1 – Description and Location |
| C- 2 – Standard Specifications |
| C- 3 – Statement of Work/Specifications |
| C- 4 – Attachments to Statements of Work/Specifications |
| C- 5 – Biobsed Product Utilization |
SECTION E - INSPECTION AND ACCEPTANCE 7
E- 1 - Clauses Incorporated by Reference
SECTION F - DELIVERIES OR PERFORMANCE 8
| F- 1 - Clauses Incorporated by Reference |
| F- 2 - Commencement, Prosecution, and Completion of Work |
SECTION G – CONTRACT ADMINISTRATIN DATA 9
G- 1 – Post Award Conference
SECTION H - SPECIAL CONTRACT REQUIREMENTS 10-13
| H- 1 - Clauses Incorporated by Reference |
| H- 2 - Physical Data |
| H- 3 – Key Personnel |
| H- 4 – Incidental payment Items |
| H- 5 – Conformity with Drawings and Specifications |
| H- 6 - Local Material Sources |
| H-7 - Samples, Tests, Cited Specifications |
| H-8 - Barricades, Warning Signs, and Other Devices |
| H-9 - Weed Free Equipment |
| H-10 - Invoice Processing Platform (IPP) |
| H-11 - Contractor Performance Assessment Reporting System |
| H-12 – Reference Accident Prevention |
| H-13 - Idaho Worker’s Compensation Law |
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES 14-28
| I- 1 - Clauses Incorporated by Reference |
| I-2 - Post Award Small Business Program Rerepresentation |
| I-3- Paid Sick Leave Under Executive Order 13706 |
| I-4 - Affirmative Procurement of Biobased Products Under Service and Construction Contracts |
| I-5 - Buy American - Construction Materials |
| I-6 - Bid Guarantee |
| I-7 - Performance and Payment Bonds - Construction |
| I-8 - Alternative Forms of Security |
| I-9 - Federal, State, and Local Taxes |
| I-10 - Reimbursement For Bond Premiums - Fixed Price Construction Contracts |
| I-11 - Permits and Responsibilities |
| I-12 - Alterations In Contract |
| I-13 - Authorized Deviations in Clauses |
| I-14 - Order of Precedence - Construction |
PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS 29
| J- 1 - Wage Determination |
| J- 2 – Supplemental Specifications |
| J- 3 - Drawings |
| J- 4 - State of Idaho Certificate of Verification of Workers’ Compensation Insurance |
PART IV - REPRESENTATIONS AND INSTRUCTIONS
| SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER | 30-33 |
| STATEMENTS OF OFFERORS AND RESPONDENTS |
K- 1 - Annual Representations and Certifications K- 2 - Incorporation by Reference of Representations and Certifications
| SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS | 34-40 |
| AND RESPONDENTS |
| L- 1 - Solicitation Provisions Incorporated by Reference |
| L- 2 - System for Award Management |
| L- 3 - Inquiries |
| L- 4 - Instructions for the Preparation of Technical and Business Proposals |
| L- 5 - Amendments to Proposals |
| L- 6 - Type of Contract |
| L- 7 - Construction Wage Rate Requirements—Secondary Site of the Work |
| L-8 - Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity |
for Construction
| L-9 - Notice of Buy American Requirements - Construction Materials |
| L-10 - Service of Protest |
| L-11 - Site Visit (Construction) |
| L-12 - Preparation of Proposals – Construction |
| L-13 - Authorized Deviations in Provisions |
SECTION M - EVALUATION FACTORS FOR AWARD 41
| M- 1 - Evaluation Criteria |
| M- 2 - Award Statement |
| CONSTRUCTION AG-02RC-S-17-0128 | AG-0343-S-17-**** |
| *(Project Name/Location) |
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
RFP AG-02RC-S-17-0136
2. TYPE OF SOLICITATION
|_| SEALED BID (IFB)
|_| NEGOTIATED (RFP)
3. DATE ISSUED
8/1/2017
| PAGE OF PAGES | |
| 1 | * |
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
859909
6. PROJECT NO.
| 7. ISSUED BY | CODE |
| 8. ADDRESS OFFER TO |
USDA - Forest Service Region 1, Acquisition Management Idaho Montana Acquisition Team 3815 Schreiber Way Coeur d Alene, ID 83815
USDA - Forest Service Region 1, Acquisition Management Idaho Montana Acquisition Team 3815 Schreiber Way Coeur d Alene, ID 83815
| 9. FOR INFORMATION |
| CALL: |
| a. NAME |
Rita Loper, CO Brent Briggs, Technical
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(208) 765-7497
(208) 765-7436
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
Sissons Bridge Rehabilitation Coeur d Alene River Ranger District Idaho Panhandle National Forests Shoshone County, Idaho
The estimated price magnitude is: Between $250,000 and $500,000.
11. The Contractor shall begin performance within 10 calendar days and complete it within See Section F calendar days after receiving |_| award, |_| notice to proceed. This performance period is |_| mandatory, |_| negotiable. (See Section F, Clause 52.211-10)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12b.)
| |_| YES | |_| NO | |
| 12b. CALENDAR DAYS |
| 13. ADDITIONAL SOLICITATION REQUIREMENTS: | |||
| a. | Sealed offers in original and * copies to perform the work required are due at the place specified in Item 8 by 4:00 pm local time 8/30/2017. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due. | ||
| b. | An offer guarantee | |_| is, | |_| is not required. (If “is required” see AGAR Clause 452.228-70) |
| c. | All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference. | ||
| d. | Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. |
| NSN 7540-01-155-3212 | 1442-101 | STANDARD FORM 1442 (REV. 4-85) |
| Computer Generated | Prescribed by GSA |
FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
Duns No. ______________________________
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
| AMENDMENT NO. |
| DATE |
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
| 24. SUBMIT INVOICES TO ADDRESS SHOWN IN |
| (4 copies unless otherwise specified) |
| ITEM |
| 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO | |
| |_| 10 U.S.C. 2304(c)( ) | |_| 41 U.S.C. 253(c)( ) |
| 26. ADMINISTERED BY | CODE |
| 27. PAYMENT WILL BE MADE BY |
USDA – Forest Service Region 1 AQM Idaho Montana Acquisition Team 3815 Schreiber Way Coeur d Alene ID 83815
All invoices will be processed using the Department of Treasury’s Invoice Processing Platform (IPP), visit http://www.ipp.gov to learn more. Contractors must follow the instructions on how to register and submit invoices via IPP.
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
| |_| | 28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract. |
| |_| | 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary. |
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
RITA J LOPER
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES
SISSONS BRIDGE REHABILITATION 208-9.5
Coeur d Alene River Ranger District Idaho Panhandle National Forests Shoshone County Idaho
B-1 SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION
METH. OF
MEAS.
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101
Mobilization
LSQ
Lump Sum xx
55204
Structural Concrete Class A(AE)
CQ
CY
55403
Reinforcing Steel
LSQ
Lump Sum xx
72501
Structural Concrete Repair
CQ
LF
TOTAL $___________
* Designated Method of Measurement:
DQ – Designed Quantities; AQ - Actual Quantities, LSQ - Lump Sum Quantities; SQ – Staked Quantities; CQ – Contract Quantities
B- 2 Payment for Bond Premiums
Note: Payment for bond premiums in accordance with FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted
SECTION C - DESCRIPTION/SPECIFICATIONS
C- 1 - PROJECT DESCRIPTION AND LOCATION
a. Description of Work. This project consists of the rehabilitation of an existing 270’ two lane concrete bridge. The bridge is located on F.S. Road No. 208 at milepost 9.5. Work consists of, but is not limited to; mobilization, structural concrete repair, furnishing and installation of reinforcing steel, (drill and epoxy, placing and tying), forming and placing structural concrete.
b. Project Location This project is located on the Coeur d’Alene River Ranger District of the Idaho Panhandle National Forests, approximately 16 air miles north of Osburn in Shoshone County, Idaho. The legal description is the SW ¼ section 30, T. 51 N., R.4 E, B.M. Refer to the location map on the title sheet of the plans. Latitude and longitude at the site is 47.736800, -116.008216. To access the site from Interstate 90, take the Kingston exit. Travel north onto Forest Highway 9 for approximately 23 miles to Prichard, Idaho. At Prichard, stay left on forest road 208. Travel approximately 9.5 miles to the Sissons bridge.
c. Restrictions. No instream work is anticipated. See Supplemental Specification Section 156 for requirements for accommodating public traffic during work.
Project submittals shall be provided to the government prior to ordering materials. Allow 21 calendar days for the government’s review.
Written project schedules shall be submitted at the pre-work meeting and updated weekly.
C- 2 - STANDARD SPECIFICATIONS: " FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this Solicitation and any resultant contract.
Copies of the " FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS" are available for download at the following URL:
http://www.wfl.fha.dot.gov/design/specs/fp03.htm.
The following “FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract.
| SPEC. NO | TITLE | |||
| PREFACE | ||||
| Section 101 | TERMS, FORMAT, AND DEFINITIONS | |||
| Section 102 | BID, AWARD AND EXECUTION OF CONTRACT | |||
| Section 103 | SCOPE OF WORK | |||
| Section 104 | CONTROL OF WORK | |||
| Section 105 | CONTROL OF MATERIAL | |||
| Section 106 | ACCEPTANCE OF WORK | |||
| Section 107 | LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC | |||
| Section 108 | PROSECUTION AND PROGRESS | |||
| Section 109 | MEASUREMENT AND PAYMENT | |||
| Section 151 | MOBILIZATION | |||
| Section 153 | CONTRACTOR QUALITY CONTROL | |||
| Section 154 | CONTRACTOR SAMPLING AND TESTING | |||
| Section 155 | SCHEDULES FOR CONSTRUCTION CONTRACTS | |||
| Section 156 | PUBLIC TRAFFIC | |||
| Section 157 | SOIL EROSION CONTROL | |||
| Section 201 | CLEARING AND GRUBBING | |||
| Section 552 | STRUCTURAL CONCRETE | |||
| Section 554 | REINFORCING STEEL | |||
| Section 633 | PERMANENT TRAFFIC CONTROL | |||
| Section 701 | CEMENT | |||
| Section 703 | AGGREGATE | |||
| Section 709 | REINFORCING STEEL & WIRE ROPE | |||
| Section 711 | CONCRETE CURING MATERIAL & ADMIXTURES | |||
| Section 712 | JOINT MATERIAL | |||
| Section 713 | ROADSIDE IMPROVEMENT MATERIAL | |||
| Section 718 | TRAFFIC SIGNING AND MARKING MATERIAL | |||
| Section 725 | MISCELLANEOUS MATERIAL |
C-3 AGAR 452.211-3 Statement of Work/Specifications. (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
C-4 AGAR 452.211-4 Attachments to Statements of Work/Specifications. (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract
C- 5 Biobased Product Utilization The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February 2012, to provide biobased products.
The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative (COR).
The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
| Grease Removers | Insulating Foam | Concrete and Asphalt Release Fluids |
| Fluid-filled Transformers | Wood and Concrete Sealers | Composite Panels |
| Adhesive and Mastic Removers | Carpets | Roof Coatings |
| Hydraulic Fluid | Water Tank Coatings |
Biobased products that are designated for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.
In addition to the biobased products designated by the U.S. Department of Agriculture in the Biopreferred Program, the Contractor is encouraged to use other commercially available biobased products.
The Contractor shall submit a complete list of biobased products before work begins, indicating the name of the manufacturer, cost of each material, and the intended use of each of the materials that are to be used in carrying out the requirements of this contract.
Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).
The Contractor shall provide data on the quantity and dollar values of biobased products used in this contract. The data shall be submitted to the COR quarterly.
SECTION E - INSPECTION AND ACCEPTANCE
E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
| 52.246-11 | Higher-Level Contract Quality Requirement (DEC 2014) |
| 52.246-12 | Inspection of Construction (AUG 1996) |
SECTION F - DELIVERIES OR PERFORMANCE
F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
F- 2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than October 30, 2018. The time stated for completion shall include final cleanup of the premises.
Note: It is estimated that the notice to proceed under this contract will be issued approximately October 2017 to facilitate the contract submittal process and contractor ordering of materials.
SECTION G - Contract Administration Data
AGRICULTURE ACQUISITION REGULATIONS (48 CFR CHAPTER 4) CLAUSES
http://www.dm.usda.gov/procurement/policy/agar.html
G-1 AGAR 452-215-73 Post Award Conference (NOV 1996). A post award conference with successful offeror is required. It will be scheduled and held before work begins, after the date of contract award. The conference will be held at a location to be determined as agreed upon.
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.236-72 Use of Premises (NOV 1996)
H- 2 FAR 52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual observation.
H- 3 AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel:
| Site Superintendent |
| Quality Control |
Epoxy Injection Operator(s) (see FSSS 725)
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H- 4 Incidental Payment Items The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
H- 5 Conformity With Drawings and Specifications Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
H- 6 Local Material Sources
(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.
The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty payment requirements will be stated below.
When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.
Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.
(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.
H-7 Samples, Tests, Cited Specifications Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.
H-8 Barricades, Warning Signs, and Other Devices The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
H-9 Weed-Free Equipment In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.
The following is considered proof of weed-free equipment:
The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.
Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.
H-10 Invoice Processing Platform (IPP) The Forest Service is utilizing the Invoice Processing Platform (IPP) for the electronic submission and tracking of contracts/purchase orders, invoices, and payment information. IPP is a secure Government-wide, Web-based invoice processing service. Visit http://www.ipp.gov to learn more.
Upon award of a contract, Contractors will be enrolled automatically. Contractor will subsequently receive electronic notification from IPP of enrollment. IPP password will be delivered electronically to allow first login to IPP. Contractors shall submit all invoices electronically via IPP. Paper copies of invoices will no longer be accepted.
H-11 Contractor Performance Assessment Reporting System (FEB 2011)
(a) General. This contract is subject to Federal Acquisition Regulations (FAR), Agriculture Acquisition Regulations (AGAR), and Forest Service Acquisition Regulations (FSAR) that require past performance evaluations to be completed and entered into the Contractor Performance Assessment Reporting System (CPARS).
(b) Contact Information. At the Prework Meeting, the name and email address of the Contractor Representative will be required.
(c) Assessment. Upon completion of the work associated with the contract/delivery orders, an evaluation will be initiated by the Contracting Officer in the CPARS system and the Contractor Representative will receive an auto-email from CPARS with instructions for completion of the evaluation.
H-12 Reference FAR 52.236-13, Accident Prevention.
Safety. Contractors shall comply with OSHA regulations and provide employees a work environment that is sanitary and not hazardous, which includes providing personal protective equipment. Contractors must maintain a health and safety plan and an accident prevention program, which includes frequent and regular inspections of the project site, materials, and equipment. Contractors are responsible for risk management regarding contractor/employee and public safety, which include experience of operator to handle road and terrain conditions, getting to the worksite, traffic control, and coordination with other users.
H-13 Idaho Worker’s Compensation Law
(a) Prior to award of any contract subject to Idaho Workers' Compensation Laws, the Contractor must provide a completed State of Idaho Certificate of Verification of Workers’ Compensation Insurance form to the Government. This form will be submitted to the Idaho Industrial Commission by the Government in order to assure that the Contractor in line for award has the required worker’s compensation coverage or is exempt from the requirement for coverage.
(b) A copy of the State of Idaho Certificate of Verification of Workers' Compensation Insurance form has been provided for use in Section J and shall be completed and submitted as part of the offer.
(c) This certificate of verification shall be fully executed by the Contractor and signed by the Industrial Commission Compliance Officer prior to award of the contract.
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
| 52.202-1 | Definitions (NOV 2013) |
| 52.203-3 | Gratuities (APR 1984) |
| 52.203-5 | Covenant Against Contingent Fees (MAY 2014) |
| 52.203-7 | Anti-Kickback Procedures (MAY 2014) |
| 52.203-8 | Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) |
| 52.203-10 | Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) |
| 52.203-12 | Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) |
| 52.203-17 | Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014) |
| 52.203-19 | Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) |
| 52.204-4 | Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) |
| 52.204-10 | Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2016) |
| 52.204-13 | System for Award Management Maintenance (OCT 2016) |
| 52.209-6 | Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) |
| 52.209-10 | Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)) |
| 52.211-18 | Variation in Estimated Quantity (APR 1984) |
| 52.215-2 | Audit and Records - Negotiation (OCT 2010) |
| 52.219-6 | Notice of Total Small Business Set-Aside (NOV 2011) |
| 52.219-8 | Utilization of Small Business Concerns (NOV 2016) |
| 52.219-14 | Limitations on Subcontracting (JAN 2017) |
| 52.222-3 | Convict Labor (JUNE 2003) |
| 52.222-4 | Contract Work Hours and Safety Standards--Overtime Compensation (MAY 2014) |
| 52.222-6 | Construction Wage Rate Requirements (MAY 2014) |
| 52.222-7 | Withholding of Funds (MAY 2014) |
| 52.222-8 | Payrolls and Basic Records (MAY 2014) |
| 52.222-9 | Apprentices and Trainees (JULY 2005) |
| 52.222-10 | Compliance with Copeland Act Requirements (FEB 1988) |
| 52.222-11 | Subcontracts (Labor Standards) (MAY 2014) |
| 52.222-12 | Contract Termination - Debarment (MAY 2014) |
| 52.222-13 | Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) |
| 52.222-14 | Disputes Concerning Labor Standards (FEB 1988) |
| 52.222-15 | Certification of Eligibility (MAY 2014) |
| 52.222-21 | Prohibition of Segregated Facilities (APR 2015) |
| 52.222-26 | Equal Opportunity (SEPT 2016) |
| 52.222-27 | Affirmative Action Compliance Requirements for Construction (APR 2015) |
| 52.222-35 | Equal Opportunity for Veterans (OCT 2015) |
| 52.222-36 | Equal Opportunity for Workers with Disabilities (JUL 2014) |
| 52.222-37 | Employment Reports on Veterans (FEB 2016) |
| 52.222-40 | Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) |
| 52.222-50 | Combating Trafficking in Persons (MAR 2015) |
| 52.222-54 | Employment Eligibility Verification (OCT 2015) |
| 52.222-55 | Minimum Wages Under Executive Order 13658 (DEC 2015) |
| 52.223-3 | Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I (JULY 1995) |
| 52.223-5 | Pollution Prevention and Right-to-Know Information (MAY 2011) |
| 52.223-6 | Drug-Free Workplace (MAY 2001) |
| 52.223-18 | Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) |
| 52.224-1 | Privacy Act Notification (APR 1984) |
| 52.224-2 | Privacy Act (APR 1984) |
| 52.225-13 | Restrictions on Certain Foreign Purchases (JUNE 2008) |
| 52.227-1 | Authorization and Consent (DEC 2007) |
| 52.227-2 | Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) |
| 52.227-4 | Patent Indemnity--Construction Contracts (DEC 2007) |
| 52.228-2 | Additional Bond Security (OCT 1997) |
| 52.228-11 | Pledges of Assets (JAN 2012) |
| 52.228-12 | Prospective Subcontractor Requests for Bonds (MAY 2014) |
| 52.228-14 | Irrevocable Letter of Credit (NOV 2014) |
| 52.229-4 | Federal, State, and Local Taxes (State and Local Adjustments) (FEB 2013) |
| 52.232-5 | Payments Under Fixed-Price Construction Contracts (MAY 2014) |
| 52.232-9 | Limitation on Withholding of Payments (APR 1984) |
| 52.232-17 | Interest (MAY 2014) |
| 52.232-18 | Availability of Funds (APR 1984) |
| 52.232-23 | Assignment of Claims (MAY 2014) |
| 52.232-27 | Prompt Payment for Construction Contracts (JAN 2017) |
| 52.232-33 | Payment by Electronic Funds Transfer—System for Award Management (JUL 2013) |
| 52.232-39 | Unenforceability of Unauthorized Obligations (JUN 2013) |
| 52.232-40 | Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) |
| 52.233-1 | Disputes (MAY 2014) Alternate I (DEC 1991) |
| 52.233-3 | Protest After Award (AUG 1996) |
| 52.233-4 | Applicable Law for Breach of Contract Claim (OCT 2004) |
| 52.236-2 | Differing Site Conditions (APR 1984) |
| 52.236-3 | Site Investigation and Conditions Affecting the Work (APR 1984) |
| 52.236-5 | Material and Workmanship (APR 1984) |
| 52.236-6 | Superintendence by the Contractor (APR 1984) |
| 52.236-8 | Other Contracts (APR 1984) |
| 52.236-9 | Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
(APR 1984)
| 52.236-10 | Operations and Storage Areas (APR 1984) |
| 52.236-11 | Use and Possession Prior to Completion (APR 1984) |
| 52.236-12 | Cleaning Up (APR 1984) |
| 52.236-13 | Accident Prevention (NOV 1991) |
| 52.236-14 | Availability and Use of Utility Services (APR 1984) |
| 52.236-15 | Schedules for Construction Contracts (APR 1984) |
| 52.236-17 | Layout of Work (APR 1984) |
| 52.236-21 | Specifications and Drawings for Construction (FEB 1997) Alternate I (APR 1984) |
| 52.236-26 | Preconstruction Conference (FEB 1995) |
| 52.242-13 | Bankruptcy (JULY 1995) |
| 52.243-4 | Changes (JUNE 2007) |
| 52.244-2 | Subcontracts (OCT 2010) |
| 52.244-6 | Subcontracts for Commercial Items (JAN 2017) |
| 52.245-1 | Government Property (JAN 2017) Alternate I (APR 2012) |
| 52.245-2 | Government Property Installation Operation Services (APR 2012) |
| 52.245-9 | Use and Charges (APR 2012) |
| 52.246-21 | Warranty of Construction (MAR 1994) |
| 52.248-3 | Value Engineering--Construction (OCT 2015) |
| 52.249-2 | Termination for Convenience of the Government (Fixed-Price) (APR 2012) Alternate I (SEPT 1996) |
| 52.249-10 | Default (Fixed-Price Construction) (APR 1984) |
| 52.253-1 | Computer Generated Forms (JAN 1991) |
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
| 452.224-70 | Confidentiality of Information (FEB 1988) |
| 452.236-71 | Prohibition Against the Use of Lead-Paint (NOV 1996) |
| 452.236-73 | Archeological or Historic Sites (FEB 1988) |
| 452.236-74 | Control of Erosion, Sedimentation and Pollution (NOV 1996) |
| 452.236-76 | Samples and Certificates (FEB 1988) |
I-2 FAR 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)
(a) Definitions. As used in this clause—
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it |_| is, |_| is not a small business concern under NAICS Code ______________ assigned to contract number ______________.
[Contractor to sign and date and insert authorized signer’s name and title].
I-3 FAR 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017) )
(a) Definitions. As used in this clause (in accordance with 29 CFR 13.2)–
“Child”, “domestic partner”, and “domestic violence” have the meaning given in 29 CFR 13.2.
“Employee”–
(1) (i) Means any person engaged in performing work on or in connection with a contract covered by Executive Order (E.O.) 13706, and
(A) Whose wages under such contract are governed by the Service Contract Labor Standards statute (41 U.S.C. chapter 67), the Wage Rate Requirements (Construction) statute (40 U.S.C. chapter 31, subchapter IV), or the Fair Labor Standards Act (29 U.S.C. chapter 8),
(B) Including employees who qualify for an exemption from the Fair Labor Standards Act's minimum wage and overtime provisions,
(C) Regardless of the contractual relationship alleged to exist between the individual and the employer; and
(ii) Includes any person performing work on or in connection with the contract and individually registered in a bona fide apprenticeship or training program registered with the Department of Labor’s Employment and Training Administration, Office of Apprenticeship, or with a State Apprenticeship Agency recognized by the Office of Apprenticeship.
(2) (i) An employee performs “on” a contract if the employee directly performs the specific services called for by the contract; and
(ii) An employee performs “in connection with” a contract if the employee’s work activities are necessary to the performance of a contract but are not the specific services called for by the contract.
“Individual related by blood or affinity whose close association with the employee is the equivalent of a family relationship” has the meaning given in 29 CFR 13.2.
“Multiemployer” plan means a plan to which more than one employer is required to contribute and which is maintained pursuant to one or more collective bargaining agreements between one or more employee organizations and more than one employer.
“Paid sick leave” means compensated absence from employment that is required by E.O. 13706 and 29 CFR part 13.
“Parent”, “sexual assault”, “spouse”, and “stalking” have the meaning given in 29 CFR 13.2.
“United States” means the 50 States and the District of Columbia.
(b) Executive Order 13706.
(1) This contract is subject to E.O. 13706 and the regulations issued by the Secretary of Labor in 29 CFR part 13 pursuant to the E.O.
(2) If this contract is not performed wholly within the United States, this clause only applies with respect to that part of the contract that is performed within the United States.
(c) Paid sick leave. The Contractor shall–
(1) Permit each employee engaged in performing work on or in connection with this contract to earn not less than 1 hour of paid sick leave for every 30 hours worked;
(2) Allow accrual and use of paid sick leave as required by E.O. 13706 and 29 CFR part 13;
(3) Comply with the accrual, use, and other requirements set forth in 29 CFR 13.5 and 13.6, which are incorporated by reference in this contract;
(4) Provide paid sick leave to all employees when due free and clear and without subsequent deduction (except as otherwise provided by 29 CFR 13.24), rebate, or kickback on any account;
(5) Provide pay and benefits for paid sick leave used no later than one pay period following the end of the regular pay period in which the paid sick leave was taken; and
(6) Be responsible for the compliance by any subcontractor with the requirements of E.O. 13706, 29 CFR part 13, and this clause.
(d) Contractors may fulfill their obligations under E.O. 13706 and 29 CFR part 13 jointly with other contractors through a multiemployer plan, or may fulfill their obligations through an individual fund, plan, or program (see 29 CFR 13.8).
(e) Withholding. The Contracting Officer will, upon his or her own action or upon written request of an authorized representative of the Department of Labor, withhold or cause to be withheld from the Contractor under this or any other Federal contract with the same Contractor, so much of the accrued payments or advances as may be considered necessary to pay employees the full amount owed to compensate for any violation of the requirements of E.O. 13706, 29 CFR part 13, or this clause, including–
(1) Any pay and/or benefits denied or lost by reason of the violation;
(2) Other actual monetary losses sustained as a direct result of the violation; and
(3) Liquidated damages.
(f) Payment suspension/contract termination/contractor debarment.
(1) In the event of a failure to comply with E.O. 13706, 29 CFR part 13, or this clause, the contracting agency may, on its own action or after authorization or by direction of the Department of Labor and written notification to the Contractor take action to cause suspension of any further payment, advance, or guarantee of funds until such violations have ceased.
(2) Any failure to comply with the requirements of this clause may be grounds for termination for default or cause.
(3) A breach of the contract clause may be grounds for debarment as a contractor and subcontractor as provided in 29 CFR 13.52.
(g) The paid sick leave required by E.O. 13706, 29 CFR part 13, and this clause is in addition to the Contractor's obligations under the Service Contract Labor Standards statute and Wage Rate Requirements (Construction) statute, and the Contractor may not receive credit toward its prevailing wage or fringe benefit obligations under those Acts for any paid sick leave provided in satisfaction of the requirements of E.O. 13706 and 29 CFR part 13.
(h) Nothing in E.O. 13706 or 29 CFR part 13 shall excuse noncompliance with or supersede any applicable Federal or State law, any applicable law or municipal ordinance, or a collective bargaining agreement requiring greater paid sick leave or leave rights than those established under E.O. 13706 and 29 CFR part 13.
(i) Recordkeeping
(1) The Contractor shall make and maintain, for no less than three (3) years from the completion of the work on the contract, records containing the following information for each employee, which the Contractor shall make available upon request for inspection, copying, and transcription by authorized representatives of the Administrator of the Wage and Hour Division of the Department of Labor:
(i) Name, address, and social security number of each employee.
(ii) The employee’s occupation(s) or classification(s).
(iii) The rate or rates of wages paid (including all pay and benefits provided).
(iv) The number of daily and weekly hours worked.
(v) Any deductions made.
(vi) The total wages paid (including all pay and benefits provided) each pay period.
(vii) A copy of notifications to employees of the amount of paid sick leave the employee has accrued, as required under 29 CFR 13.5(a)(2).
(viii) A copy of employees’ requests to use paid sick leave, if in writing, or, if not in writing, any other records reflecting such employee requests.
(ix) Dates and amounts of paid sick leave taken by employees (unless the Contractor’s paid time off policy satisfies the requirements of E.O. 13706 and 29 CFR part 13 as described in 29 CFR 13.5(f)(5), leave shall be designated in records as paid sick leave pursuant to E.O. 13706).
(x) A copy of any written responses to employees’ requests to use paid sick leave, including explanations for any denials of such requests, as required under 29 CFR 13.5(d)(3).
(xi) Any records reflecting the certification and documentation the Contractor may require an employee to provide under 29 CFR 13.5(e), including copies of any certification or documentation provided by an employee.
(xii) Any other records showing any tracking of or calculations related to an employee's accrual or use of paid sick leave.
(xiii) The relevant contract.
(xiv) The regular pay and benefits provided to an employee for each use of paid sick leave.
(xv) Any financial payment made for unused paid sick leave upon a separation from employment intended, pursuant to 29 CFR 13.5(b)(5), to relieve the Contractor from the obligation to reinstate such paid sick leave as otherwise required by 29 CFR 13.5(b)(4).
(2) (i) If the Contractor wishes to distinguish between an employee's covered and noncovered work, the Contractor shall keep records or other proof reflecting such distinctions. Only if the Contractor adequately segregates the employee’s time will time spent on noncovered work be excluded from hours worked counted toward the accrual of paid sick leave.
This is the start of the file's text. The full file is on GovTribe.