WallCrk_RFQ.doc

DOC document 322 KB Posted

Attached to
IPNF, Bonners Ferry RD, Wall Creek Culvert Federal contract opportunity
Solicitation number
AG-02RC-S-15-0102
Issued by
Department of Agriculture Forest Service R1-Northern Region

About this file

Request for Quote solicitation package

View the file

Other files for this federal contract opportunity

Other files attached to IPNF, Bonners Ferry RD, Wall Creek Culvert, newest first.
File Type Posted
Wall_Amend_2.doc DOC document
Wall_Amend_1.doc DOC document
PastPerformanceSurvey.docx DOCX document
WageDecision.docx DOCX document
FoodStorage2011Signed.pdf PDF
Idaho_WCI.docx DOCX document
Wall_Creek-_Final_Plans.pdf PDF
Wall_Creek_AOP-FSSS.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION RFQ AG-02RC-S-15-0102, Wall Crk Culvert

REQUEST FOR QUOTATION

PAGE OF PAGES

(THIS IS NOT AN ORDER)
THIS RFQ
X
IS
IS NOT A SMALL BUSINESS SET- ASIDE
1
1. REQUEST NO.
2. DATE ISSUED
3. REQUISITION/PURCHASE REQUEST NO.
4. CERT. FOR NAT.DEF.
RATING
AG-02RC-S-15-0102
7/2/2015
752921
UNDER BDSA REG. 2

AND/OR DMS REG. 1

5a. ISSUED BY
6. DELIVER BY (Date)

USDA – Forest Service

Idaho Montana Acquisition Team 3815 Schreiber Way Coeur d Alene, ID 83815 complete by 10/15/2015

5b. FOR INFORMATION CALL (NO COLLECT CALLS)
7. DELIVERY

FOB DESTINATION

NAME
TELEPHONE NUMBER
X
OTHER (See Schedule)
AREA CODE
NUMBER
9. DESTINATION

RITA J. LOPER, CO

Rick Driggs, Technical

765-7497

265-6637

a. NAME OF CONSIGNEE

8. TO:
Bonners Ferry Ranger District
a. NAME
b. COMPANY
b. STREET ADDRESS
c. STREET ADDRESS
c. CITY
d. CITY
e. STATE
f. ZIP CODE
d. STATE
e. ZIP CODE
10. PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5a. This request does not commit the Government to pay any costs incurred in the preparation of the

8/3/2015 4:00 pm submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(a)
(b)
(c)
(d)
(e)
(f)

Wall Creek Culvert, Bonners Ferry Ranger District, Idaho Panhandle National Forests.

Price Range between $100,000 and $250,000

PLEASE PLACE YOUR QUOTE IN SECTION B- SCHEDULE OF ITEMS

FURNISHING QUOTATION: See Section L-9 Instructions.

a. 10 CALENDAR DAYS (%)
b. 20 CALENDAR DAYS
c. 30 CALENDAR DAYS
d. CALENDAR DAYS

12. DISCOUNT FOR PROMPT PAYMENT

(%)
(%)
NUMBER
PERCENTAGE
NOTE: Additional provisions and representations
X
are

are not attached.

13. NAME AND ADDRESS OF QUOTER
14. SIGNATURE OF PERSON AUTHORIZED TO
15. DATE OF
a. NAME OF QUOTER
SIGN QUOTATION
QUOTATION

DUNS NO. ________________________

email_____________________________

TIN NO.___________________

b. STREET ADDRESS
16. SIGNER
a. NAME (Type or print)
b. TELEPHONE

c. COUNTY

AREA CODE

d. CITY
e. STATE
f. ZIP CODE
c. TITLE (Type or Print)
NUMBER

NSN 7540-01-152-8084

Previous edition not usable

18-121
STANDARD FORM 18 (Rev. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES

Wall Creek Culvert Bonners Ferry Ranger District

Idaho Panhandle National Forest

Boundary County, ID

B- 1 - SCHEDULE OF ITEMS

ITEM

NO.

DESCRIPTION
METHOD of MEAS.
PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

15101
Mobilization
LSQ
LS
1
xx
$
15221
Construction Survey And Staking
LSQ
LS
1
xx
$
15713
Soil Erosion And Pollution Control
LSQ
LS
1
xx
$
20304
Removal Of Existing Corrugated Metal Culvert
LSQ
LS
1
xx
$
20411
Embankment Construction
CQ
CY
197
20806
Structure Excavation & Backfill
LSQ
LS
1
xx
$
25101
Placed Riprap, Class 5
CQ
CY
40
27250
Geocell Abutment Stabilization, 6 Inch Depth
CQ
SY
60
30809
Crushed Aggregate
CQ
CY
20
553A01
Precast Concrete Member, Stemwall Footings
LSQ
LS
1
xx
$
60304
Steel Structural Plate Arch, 13' -0" Span, 6'-9" Rise, 0.111" Thickness
CQ
LF
48
62201a
Hydraulic Excavator With Thumb
AQ
HR
8
62201b
Large Dump Truck
AQ
HR
8
62503
Seeding And Mulch, Dry Method
LSQ
LS
1
xx
$
64808
Rock Cross-Vane Structure
AQ
EA
5
67050
Slash Filter Windrow
LSQ
LS
1
xx
$

TOTAL ALL ITEMS

* Designated Method of Measurement:

DQ - Designed Quantities, AQ - Actual Quantities, LSQ - Lump Sum Quantities, SQ - Staked Quantities, CQ - Contract Quantities Under Clause 52.236-7, Permits and Responsibilities, Contractors shall be responsible for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. Questions regarding assessment of Idaho Use Tax on Government Furnished Property should be directed to the Idaho State Tax Commission at (208) 799-3491.

B- 2 Quote on all items. Only quotes to the nearest cent will be accepted.

B- 3 Payment for Bond Premiums *(Between $30,000-$150,000 payment protection is required upon award) Payment for bond premiums in accordance with FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

PART I - THE SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C- 1 Project Description and Location

(a) Description of Work. This project includes removal of an existing 48 inch culvert and replacing with a 13 ft-0 in x 6 ft-9 in Structural Plate Arch with precast concrete footings. This work will consist of constructing a stream channel through the pipe and installing grade control structures within the culvert and potentially outside the culvert near the inlet and outlet. Additionally a segment of road shall be reconstructed and shaped to obtain minimum cover and adequate approaches to the new structure together with commercial source surface aggregate placed on the reconstructed segment of road. This work will include placing commercial source riprap material at the inlet and outlet and for construction of the grade control structures

(b) Project Location. Forest Service Road 2542E is approximately 15 miles Northeast of Bonners Ferry, Idaho. Located at T.63N. R. 2E. in the SW corner of section 9, Boise Meridian. Latitude and Longitude of the site is 48°49'17.59"N, 116°13'2.51"W. Travel North from Bonners Ferry, Idaho on U.S 95 to 3 Mile Junction. Turn right onto U.S. Highway 2 East and continue for nearly 2 miles. Turn left onto County Road 34 (Meadow Creek Road). Continue along Meadow Creek Road about 6.6 miles from highway, to the junction with Forest Service Road 2542. Turn left onto road 2542 and head north bound for approximately 2.3 miles. Turn right onto Forest Service Road 2542E. Stay on road 2542E for around 0.15 miles and arrive at Wall Creek Crossing.

C- 2 Restrictions. In-stream work will be only allowed after July 15th and prior to September 15th of any construction year without prior approval by the Contracting Officer. Contractor shall develop and submit for Contracting Officer approval a Plan of Operation for de-watering and sediment containment to meet project BMP’s and Permits for Erosion and Sediment Control a minimum of 15 days prior to any in-stream work. Include in the Plan of Operation, Contractor’s proposed traffic and traffic sign placement and planned dates for any road closure.

C- 3 STANDARD SPECIFICATIONS. "FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this Solicitation and any resultant contract.

Copies of the "FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS" are available for download at the following URL:

http://www.wfl.fha.dot.gov/design/specs/fp03.htm The FP-03 U.S. Customary version is only available (for sale) through the Federal Lands Highway Headquarters office.

Headquarters Washington DC David K. Green Construction Standards Engineer Internet: david.green@fhwa.dot.gov Mail: Federal Highway Administration

HFPD-3

400 Seventh Street, SW Washington D.C. 20590

The following sections of “FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. The following Standard Specifications are applicable to this contract and are included by reference:

Spec No Title

Section 101 – Terms, Format, and Definitions Section 102 – Bid, Award, and Execution of Contract

Section 103 – Scope of Work

Section 104 – Control of Work

Section 105 – Control of Material

Section 106 – Acceptance of Work

Section 107 – Legal Relations and Responsibility to the Public

Section 108 – Prosecution and Progress

Section 109 – Measurement and Payment

Section 151 – Mobilization

Section 152 – Construction Survey and Staking

Section 153 – Contractor Quality Control

Section 155 – Schedules for Construction Contracts

Section 156 – Public Traffic

Section 157 – Soil Erosion Control

Section 203 – Removal of Structures and Obstructions

Section 204 – Excavation and Embankment

Section 208 – Structure Excavation and Backfill for Selected Major Structures

Section 251 – Riprap

Section 308 – Minor Crushed Aggregate

Section 553 – Prestressed Concrete

Section 603 – Structural Plate Structures

Section 622 – Rental Equipment

Section 625 – Turf Establishment

Section 703 – Aggregate

Section 704 - Soil

Section 705 – Rock

Section 707 – Metal Pipe

Section 713 – Roadside Improvement Material

Section 718 – Traffic Signing and Marking Material

Section 725 – Miscellaneous Material

C- 4 Supplemental Project Specifications and Drawings See Section J for the list of Special Project Specifications and Drawings that are incorporated into this solicitation and any resultant contract.

C-5 AGAR 452.211-72 Statement of Work/Specifications. (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C-6 AGAR 452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

PART I - THE SCHEDULE

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

52-246-6 Inspection-Time and Materials and Labor Hour (MAY 2001)

PART I - THE SCHEDULE

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984) F- 2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than October 15, 2015. The time stated for completion shall include final cleanup of the premises.

PART I - THE SCHEDULE

SECTION G - Contract Administration Data

G-1 AGAR 452.215-73 Postaward Conference. (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled within 10 days after the date of contract award. The conference will be held at: to be determined.

G-2 Government-Furnished Property. Waste Site Location for the project will be located within 3 miles of the project site and designated by the Contracting Officer.

Under Clause 52.236-7, Permits and Responsibilities, Contractors shall be responsible for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. Questions regarding assessment of Idaho Use Tax on Government Furnished Property should be directed to the Idaho State Tax Commission at (208) 799-3491.

PART I - THE SCHEDULE

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H- 1 FAR 52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual observation.

H- 2 AGAR 452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

On Site Representative/Superintendent

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H-3

CONTRACTOR WORKFORCE CERTIFICATION

Bonners Ferry Ranger District is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities.

Upon the request of the Contracting Officer, the Contractor shall submit a written report containing the following elements:

· Contractor Name and Address

· Contract Number

· Date of Report

· Identification of individual Contractor and/or Subcontractor employees, and identification of the city and state in which each individual employee maintains a primary residence.

· The following statement: “I hereby certify this list identifies all Contractor employees and subcontractor employees engaged in performance of this contract, and that the information contained in this report is accurate as of the date of this report.”

Contractor signature and date of signature.

H- 4 Fire Control

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.

An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

(12) Pump and Trailer. N/A

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Obtain a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

H- 5 Loss, Damage, or Destruction

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

All claims arising under this clause will be submitted to the Contracting Officer.

H- 6 Equipment Rental. This work consists of furnishing and operating equipment for work ordered by the CO not otherwise provided for under the contract. This work shall be authorized in advance by the Government and there is no guarantee that any hourly work will be ordered. Make equipment available for inspection and approval before use. Furnish and operate equipment with such auxiliary attachments, oilers, etc., as are usually needed for efficient operation of the equipment. Keep the equipment in good repair and operating condition. Daily written records, such as shift tickets to record the number of unit‑hours of operation are required to be signed and submitted with invoices. Do not measure time for moving equipment between project work sites. Do not measure non-operable equipment or equipment dependent upon another piece of non-operable equipment.

Payment. The working rate specified in the Schedule of Items shall be paid for all hours of actual operation of equipment on authorized work. Only quantities approved by the CO shall be accepted under this contract. The accepted quantities will be paid at the contract price per unit of measurement for the Rental Equipment pay item listed in the schedule of items. Payment will be full compensation for the work done and accepted. Adjustment of contract prices as described in FAR 52.211-18 Variation in Estimated Quantities shall not apply to hourly work. The Government reserves the right to reduce or eliminate entirely the work under this item with no adjustment in the contract unit prices.

H- 7 Incidental Payment Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H- 8 Conformity With Drawings and Specifications *(If applicable) Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H- 9 Local Material Sources *(If applicable)

(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.

The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty payment requirements will be stated below.

When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.

Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.

(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.

H- 10 Samples, Tests, Cited Specifications *(Use when applicable) Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.

H-11 Barricades, Warning Signs, and Other Devices *(If warning devices needed to warn public or other third parties prior to entering area; examples – road mtce, hazard tree falling, road decommissioning, blasting) The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

H-12 Weed-Free Equipment In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.

The following is considered proof of weed-free equipment:

The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.

Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.

H-13 Landscape Preservation

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H-14 Invoice Processing Platform (IPP)

The Forest Service is utilizing the Invoice Processing Platform (IPP) for the electronic submission and tracking of contracts/purchase orders, invoices, and payment information. IPP is a secure Government-wide, Web-based invoice processing service. Visit http://www.ipp.gov to learn more.

Upon award of a contract, Contractors must enroll at https://www.ipp.gov/vendors/enrollment-vendors.htm. Contractors shall submit all invoices electronically via IPP. Paper copies of invoices will no longer be accepted.

H-15 Contractor Performance Assessment Reporting System (FEB 2011)

(a) General. This contract is subject to Federal Acquisition Regulations (FAR), Agriculture Acquisition Regulations (AGAR), and Forest Service Acquisition Regulations (FSAR) that require past performance evaluations to be completed and entered into the Contractor Performance Assessment Reporting System (CPARS). Although the expected amount of this project is below the automatic reporting threshold, an evaluation may be entered into the CPARS system.

(b) Contact Information. At the Prework Meeting, the name and email address of the Contractor Representative may be required.

(c) Assessment. Upon completion of the work associated with the contract/delivery orders, an evaluation may be initiated by the Contracting Officer in the CPARS system and the Contractor Representative will receive an auto-email from CPARS with instructions for completion of the evaluation.

H-16 Reference FAR 52.236-13, Accident Prevention.

Safety. Contractors shall comply with OSHA regulations and provide employees a work environment that is sanitary and not hazardous, which includes providing personal protective equipment. Contractors must maintain a health and safety plan and an accident prevention program, which includes frequent and regular inspections of the project site, materials, and equipment. Contractors are responsible for risk management regarding contractor/employee and public safety, which include experience of operator to handle road and terrain conditions, getting to the worksite, traffic control, and coordination with other users.

H-17 Biobased Product Utilization REFERENCE: Section I, FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February 2012, to provide biobased products.

The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative (COR).

The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

(*Sample of biobased products for construction projects)

Grease Removers Insulating Foam Concrete and Asphalt Release Fluids

Fluid-filled Transformers Wood and Concrete Sealers Composite Panels

Adhesive and Mastic Removers Carpets Roof Coatings

Hydraulic Fluid Water Tank Coatings

Biobased products that are designated for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.

In addition to the biobased products designated by the U.S. Department of Agriculture in the Biopreferred Program, the Contractor is encouraged to use other commercially available biobased products.

The Contractor shall submit with the initial proposal a complete list of biobased products, indicating the name of the manufacturer, cost of each material, and the intended use of each of the materials that are to be used in carrying out the requirements of this contract (see Section I, FAR 52.223-2).

Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).

Within thirty (10) days of contract award, the Contractor shall submit an Operation Plan. This submittal will be approved by the COR in writing. The Contractor shall not commence work until this submittal is approved by the COR in writing. The Plan must be reviewed and updated annually, and as required by the COR. The Plan must contain and define the following elements:

· The Contractor’s written policy stating its commitment to the use of biobased products, employee health and safety, and sound environmental management practices.

· Detail on how the Contractor intends to keep abreast of the development and increasing availability of designated and non-designated biobased products and how any new or improved products will be incorporated on an ongoing basis into contract performance.

· Proposed biobased construction products which must be selected in accordance with the criteria included above. At a minimum, the Plan must identify products by brand name for each of the product types.

NOTE: A Contractor may propose more than one product within a product category and/or propose a product or products addressing more than one product category.

· The product guides which define standard operating procedures for instructing staff in the proper use, storage, and disposal of biobased products; proper maintenance of equipment; and other procedures/instructions to accomplish work under this contract.

The Contractor shall provide data on the quantity and dollar values of biobased products used in this contract. The data shall be submitted to the COR quarterly.

A demonstration of proper use, an effective training program, and technical assistance are essential to the success of the purchase and use of some biobased products that may function differently than a conventional product.

H-18 Idaho Workers Compensation Law

(a) Prior to award of any contract subject to Idaho Workers' Compensation Laws, the Contractor must provide a completed State of Idaho Certificate of Verification of Workers’ Compensation Insurance form to the Government. This form will be submitted to the Idaho Industrial Commission by the Government in order to assure that the Contractor in line for award has the required worker’s compensation coverage or is exempt from the requirement for coverage.

(b) A copy of the State of Idaho Certificate of Verification of Workers' Compensation Insurance form has been provided for use in Section J and shall be completed and submitted as part of the offer.

(c) This certificate of verification shall be fully executed by the Contractor and signed by the Industrial Commission Compliance Officer prior to award of the contract.

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (DEC 2014)

52.211-18 Variation in Estimated Quantity (APR 1984) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.222-3 Convict Labor (JUNE 2003)

52.222-6 Construction Wage Rate Requirements (MAY 2014)

52.222-7 Withholding of Funds (MAY 2014)

52.222-8 Payrolls and Basic Records (MAY 2014)

52.222-9 Apprentices and Trainees (JULY 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination--Debarment (MAY 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (MAY 2014)

52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (JUL 2014) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010)

52.222-50 Combating Trafficking in Persons (FEB 2009)

52.222-55 Minimum Wages Under Executive order 13658 (DEC 2014) 52.223-6 Drug-Free Workplace (MAY 2001)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (MAY 2008) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)

52.224-1 Privacy Act Notification (APR 1984)

52.224-2 Privacy Act (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases (JUNE 2008)

52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012)

52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014)

52.228-14 Irrevocable Letter of Credit (NOV 2014)

52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014)

52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (MAY 2014)

52.232-27 Prompt Payment for Construction Contracts (MAY 2014)

52.232-33 Payment by Electronic Funds Transfer—System for Award Management (JUL 2013)

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.233-1 Disputes (MAY 2014) Alternate I (DEC 1991)

52.233-3 Protest After Award (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984)

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.236-12 Cleaning Up (APR 1984)

52.236-13 Accident Prevention (NOV 1991)

52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

52.243-5 Changes and Changed Conditions (APR 1984)

52.244-6 Subcontracts for Commercial Items (OCT 2014)

52.245-1 Government Property (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (APR 1984)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.251-1 Government Supply Sources (APR 2012)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.224-70 Confidentiality of Information (FEB 1988)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) I- 2 FAR 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUL 2013)

(a) Definitions. As used in this clause:

“Executive” means officers, managing partners, or any other employees in management positions.

“First-tier subcontract” means a subcontract awarded directly by the Contractor for the purpose of acquiring supplies or services (including construction) for performance of a prime contract. It does not include the Contractor’s supplier agreements with vendors, such as long-term arrangements for materials or supplies that benefit multiple contracts and/or the costs of which are normally applied to a Contractor’s general and administrative expenses or indirect costs.

“Months of award” means the month in which a contract is signed by the Contracting Officer or the month in which a first-tier subcontract is signed by the Contractor.

“Total compensation” means the cash and noncash dollar value earned by the executive during the Contractor’s preceding fiscal year and includes the following (for more information see 17 CFR 229.402(c)(2)):

(1) Salary and bonus.

(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Financial Accounting Standards Board’s Accounting Standards Codification (FASB ASC) 718, Compensation-Stock Compensation.

(3) Earnings for services under non-equity incentive plans. This does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.

(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.

(5) Above-market earnings on deferred compensation which is not tax-qualified.

(6) Other compensation, if the aggregate value of all such other compensation (e.g., severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property) for the executive exceeds $10,000.

(b) Section 2(d)(2) of the Federal Funding Accountability and Transparency Act of 2006 (Pub.

L. 109-282), as amended by section 6202 of the Government Funding Transparency Act of 2008 (Pub.

L. 110-252), requires the Contractor to report information on subcontract awards. The law requires all reported information be made public, therefore, the Contractor is responsible for notifying its subcontractors that the required information will be made public.

(c) Nothing in this clause requires the disclosure of classified information

(d)

(1) Executive compensation of the prime contractor. As a part of its annual registration requirement in the System for Award Management (SAM) database (FAR provision 52.204-7), the Contractor shall report the names and total compensation of each of the five most highly compensated executives for its preceding completed fiscal year, if—

(i) In the Contractor’s preceding fiscal year, the Contractor received—

(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), cooperative agreements, and other forms of Federal financial assistance; and

(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), cooperative agreements, and other forms of Federal financial assistance; and

(ii) The public does not have access to information about the compensation of the executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986. (To determine if the public has access to the compensation information, see the U.S. Security and Exchange Commission total compensation filings at http://www.sec.gov/answers/execomp.htm.)

(2) First-tier subcontract information. Unless otherwise directed by the contracting officer, or as provided in paragraph (h) of this clause, by the end of the month following the month of award of a first-tier subcontract with a value of $25,000 or more, the Contractor shall report the following information at http://www.fsrs.gov for that first-tier subcontract. (The Contractor shall follow the instructions at http://www.fsrs.gov to report the data.)

(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor's parent company, if the subcontractor has a parent company.

(ii) Name of the subcontractor.

(iii) Amount of the subcontract award.

(iv) Date of the subcontract award.

(v) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.

(vi) Subcontract number (the subcontract number assigned by the Contractor).

(vii) Subcontractor’s physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district.

(viii) Subcontractor’s primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district.

(ix) The prime contract number, and order number if applicable.

(x) Awarding agency name and code.

(xi) Funding…