SUPPORT_DOCUMENT_B_-_PROJECT_SPECIFICATIONS.pdf

PDF 1 MB Posted

Attached to
STANLEY LAKE CAMPGROUND PROJECT 2017 Federal contract opportunity
Solicitation number
AG-0261-S-17-0003
Issued by
Department of Agriculture Forest Service R4-Intermountain Region

About this file

SUPPORT DOCUMENT B

View the file

Other files for this federal contract opportunity

Other files attached to STANLEY LAKE CAMPGROUND PROJECT 2017, newest first.
File Type Posted
AMENDMENT_2.pdf PDF
AMENDMENT_1.pdf PDF
SUPPORT_DOCUMENT_D_-_WORKERS_COMP_-_PAST_PERFORMANCE.pdf PDF
SUPPORT_DOCUMENT_A_-_PROJECT_PLANS.pdf PDF
SUPPORT_DOCUMENT_C_-_PREPROJECT-PRE-BID_SITE_TOUR_NOTES.pdf PDF
AG-0261-S-17-0003_STANLEY_LAKE_CAMPGROUND_IMPROVEMENT_PROJECT_2017_-_Copy.pdf PDF
DRAFT_Conceptual_Drawing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPORTING DOCUMENT – B

AG-0261-S-17-0003

STANLEY LAKE CAMPGROUND

IMPROVEMENT PROJECT 2017

PROJECT SPECIFICATIONS

259 Pages (including this header page)

REVISED FINAL – 4/18/2017

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

STANLEY LAKE RECREATION COMPLEX RECONSTRUCTION

Revised Final – 4/18/2017

1.1 SCOPE OF CONTRACT

A. This project consists of the reconstruction of the Stanley Lake Recreation Complex, including a campground, overlook, trailhead, day-use area with picnic sites and beach access, boat ramp, floating dock and parking, and a lakeshore trail with a boardwalk segments. The work associated with this project includes:

B. Base Bid:

1. Demolition:

a. Removing all portions of the existing Stanley Lake Inlet Campground, including all manmade structures and site furniture. All portions not included in the reconstruction are to be obliterated and removed to allow the wetlands to rehabilitate. Some roadbeds are to be reused for the lakeshore trail.

b. Abandoning existing handpump wells as designated.

c. Pumping and removing designated vault restrooms.

d. Demolishing other designated items according to the demolition sheets, such as road obliteration, restrooms and furniture removal throughout the complex.

2. Stanley Lake Campground:

a. Constructing a new campground "loop", including new aggregate road, spurs, restrooms, family units and site furniture.

b. Constructing a new entrance road and central intersection, with pull-out and kiosk

c. Realigning existing roads and intersections.

d. Installing new road signs and campsite unit numbers

3. Day-Use Area and Boat Ramp:

a. Constructing a new road, day-use parking area, and boat ramp parking area.

Surfaces will be a mix of aggregate and asphalt.

b. Constructing a new concrete boat ramp, with floating dock and precast concrete planks, including some underwater construction.

c. Relocating a bulletin board.

d. Constructing a new picnic area, including a pathway system, signs and site furniture.

4. Lakeshore Trail:

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2

a. Constructing a new universally accessible pathway along the north and west sides of the lake to connect all portions of the complex together. The pathway contains both aggregate and native surfaces.

b. Constructing boardwalk segments with both helical pier and concrete foundations.

c. A portion of the trail is an optional bid item, as shown below.

C. Optional Bid Items:

1. Option #1: Renovations to Existing Campgrounds and Overlook

a. Constructing new aggregate roads, parking areas, pullouts, spurs, curb stops, signs and installing site furnishings and other items throughout portions of the existing campgrounds and overlook, including all work shown on Sheets C5 And C11, except vault toilets.

b. Installing new family units, including site furniture (as designated)

c. Regrading all existing roadways and spurs (that are not to be reconstructed) throughout the recreation complex.

2. Option #2: New Handpump Well and Modifications to Existing Handpump Well

a. Drilling a new potable water well and installing a handpump

b. Modifying an existing handpump well

3. Option #3: Trailhead

a. Constructing a new aggregate parking area, including curb stops and signs.

b. Constructing a new bulletin board

c. Includes all work shown on Sheet C2 and Sta. 0+00 to 7+00 of the Trailhead

Connector Trail

4. Option #4: Lakeshore Trail - Sta. 17+60 To 27+01

5. Option #5: Vault Toilets

a. Installing new restrooms

6. Option #6: Chip Seal for Asphalt Pavement

D. Quantities associated with these options are identified in the Schedule of Items.

1.2 PROJECT LOCATION

A. The project is located on the Sawtooth National Recreation Area on the Sawtooth National Forest, Custer County, Idaho. It is located approximately 2 miles north and 6 miles west of Stanley, Idaho (approximately 8 miles by road from Stanley). Portions of the project are in Sections 27, 28 and 33, T11N, R12E. GPS coordinates: 44.248981°, - 115.055332°. Driving directions from Stanley: Drive West on State Highway 21 for approx. 6 miles and turn South onto Stanley Lake Road (Forest Road 455).

B. Pit Locations:

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

1. Nip & Tuck Pit: Approx. 5 miles from project site. Latitude 44° 15’ 23.7” N, Longitude 114° 59’ 28.9” W. Government-furnished decomposed granite is available from this pit. Government-furnished barrier rocks will be stockpiled at this pit for contractor to haul to project site.

2. Stanley Lake Pit: Approx. 1.5 miles from project site. Latitude 44° 15’ 29.6” N, Longitude 115° 02’ 49.0” W. Contractor shall haul excess excavated material and oversized boulders to this pit, including material excavated from obliterated roads and wetland rehabilitation.

3. Champion Creek Pit: Approx. 25 miles from project site. Latitude 44° 00’ 43.9” N, Longitude 114° 49’ 46.3” W. Government-furnished select borrow is available from this pit.

4. Fourth of July Pit: Approximately 25 miles from project site. Latitude 44° 01’ 24.8” N, Longitude 114° 49’ 05.8” W. This pit is owned by the Idaho Transportation Department. Crushed gravel is available from this pit for a fee.

Processing by the contractor may be required.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. Due to the popularity of the site, the work shall occur in sequence to minimize the impact to the public using the entire Stanley lake complex. See Section 1.9 for construction sequence. The contractor shall submit for approval staging areas and closures for each sequence of work. Also, to lessen the impact to the public the Contractor will only be allowed to work within the following time frames:

a. From September 5 to Winter Shutdown, work can be done any day of the week including Saturday and Sunday and on Federal holidays. There will also be no limit of the time of day work can be performed.

b. From the date work resumes to May 24, 2018, the same work days and time limits apply as mentioned previously in Section 1.3_A_1_a.

c. From May 25, 2018 to September 11, 2018 the following work schedule shall be followed:

• Monday thru Thursday: 8:00 AM to 6:00 PM

• Friday: 8:00 AM to 5:00 PM

• No work shall be allowed on Saturdays, Sundays, and all Federal holidays.

d. After September 11, 2018, work can be done any day of the week including

Saturday and Sunday and on Federal holidays. There will also be no limit of the time of day work can be performed.

2. Construction areas for each phase will be closed to the public during construction.

The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.

3. Contractor will provide all materials and labor necessary to protect Stanley Lake and streams, wet or dry, during construction activities. The Contractor will be

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4

required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.

4. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

5. Water for construction purposes shall be drafted from the locations indicated on the Drawings. When drafting water from any one of the locations, the Contractor shall use one of the two Government provided pump screens which measure 6” in diameter with a length of 24” or 10” in diameter with a length of 36”. Both pump screens have threaded end connections in which the Contractor shall provide the required fittings necessary to connect to their intended pump to render a water-tight, secure connection.

a. Damage to either pump screen, as a result of the Contractor’s use or negligence, shall be repaired to equal or better condition at the Contractor’s expense. If a satisfactory repair is not possible, Contractor shall be responsible for replacing the respective screen, in kind, at no expense to the Government.

b. Pumps shall be enclosed in a containment basin having 110% of the pumps fuel capacity.

c. Upon completion of using a drafting site, the Contractor shall restore it to pre-construction condition or better as determined by the Contracting Officer, following completion of the work.

6. The Contractor shall provide temporary toilet facilities (porta-potty) at each work site during the duration of the project. The existing toilet facilities within the campgrounds are managed and controlled by the concessionaires and available only to the public.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Transportation Department. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-5

B. Any activities that occur in the parking area require prior approval by the Forest Service and the Idaho Transportation Department.

C. Overnight camping will be allowed only on the project site and within the approved staging areas. The Contractor shall get approval from the CO on the locations where they propose to set up work camps. The locations should be, as much as possible, obscured from the public’s view.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 START DATE

A. September 5, 2017.

1.8 CONTRACT TIME

A. Base Bid and Options: To Be Completed by October 31, 2018.

1.9 SEQUENCE OF CONSTRUCTION

A. In order to accommodate recreation use within the Stanley Lake Complex during construction, the following sequence of work shall be adhered to:

September, 2017 to Winter Shutdown

The “Base” contract work allowed to be performed during this time frame includes the following:

• The new campground road, spurs, and associated appurtenances (i.e. site furniture, signs, bulletin boards, gates, etc.)

• The new entrance road and decommissioning of the existing entrance road to the Overlook Parking and the Stanley Lake and Lakeview Campgrounds.

• The new trail from Station 9+72 to 17+60.

If awarded, the following optional work maybe started during this time frame:

• Renovation to the existing campgrounds and overlook (Option #1)

• New handpump well and modifications to existing handpumps (Option #2)

• Trailhead (Option #3)

• Lakeshore Trail – Station 17+60 to 27+01 (Option #4)

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-6

• Vault Toilets (Option #5)

Barrier rocks designated to be removed from the Stanley Inlet Campground area can be salvaged during this time frame.

Spring, 2018 to Contract Project Completion Date

When the project resumes during this time period, all of the work allowed during September 2017 to winter shutdown shall be completed before starting construction on the following:

• The new entrance road to the new day use and boat ramp parking lots.

• The new boat ramp parking lot.

• The new concrete boat ramp and dock.

• New day use parking lot.

• Boardwalk and trail section from 4+79 to 7+12.

• Removal of existing roadways and fill in the Stanley Lake Inlet area.

B. Access to the existing boat ramp on the beach shall remain open at all times until the new boat ramp and parking lot have been approved and accepted for use by the Forest Service.

C. During construction of the trailhead parking lot, Forest Service Road 649 shall remain open at all times. If it becomes necessary to block the road, then a maximum of 5 minutes will be allowed to temporarily stop vehicular traffic.

1.10 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

Section 000050 - Boardwalk Section 010250 - Construction Staking Section 011250 - Measurement And Payment Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 022040 - Loose Rock Riprap For Boat Ramps Section 022340 - Removal Of Existing Roadways And Fill Areas Section 023701 - Sediment And Erosion Control Measures Section 023800 - Earthwork Geotextiles For Boat Ramp Section 024100 - Waste Material Disposal Section 024102 - Removal And Disposal Of Structures And Obstructions Section 026460 - Colored Concrete Dumpster Pad Section 033000 - Cast-In-Place Concrete

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-7

Section 033020 - Concrete From Packaged Dry Mix For Minor Structures Section 033501 - Concrete Boat Ramp Section 061000 - Rough Carpentry Section 061323 - Heavy Timber Construction Section 061533 - Wood Patio Decking Section 061800 - Glued-Laminated Construction Section 099100 - Painting Section 099300 - Staining And Transparent Finishing Section 101110 - Bulletin Boards Section 101400 - Signs Section 101415 - Sign Fabrication (Wood) Section 129400 - Family Unit And Site Furnishings Section 129410 - Recycling Receptacle Section 129700 - Fee Tube Section 133400 - Precast Concrete Restrooms Section 137000 - Floating Boat Dock Section 221122 - Hand Pumps Section 221310 - Sewage Holding Tank Section 231126 - Facility Liquefied-Petroleum Gas Piping Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceway And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 312600 - Steel Helical Piers Section 321200 - Warm Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 321206 - Loose Rock Riprap For Culverts Section 321210 - Rockery Retaining Wall Section 321212 - Polymer-Modified Chip Seal Section 322100 - Tent Pad Section 322205 - Barrier Rocks Section 322622 - Precast Colored Concrete Curb Stops Section 322640 - Pavement Marking Section 323116 - Gates For Roads Section 323150 - Post And Pole Railing Section 329206 - Seeding Section 332100 - Water Supply Wells Section 332228 - Culvert Pipe And Pipe Arches

END OF SECTION C

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-8

May 2017

BOARDWALK 000050-1

USDA FOREST SERVICE, R4

STANLEY LAKE RECREATION COMPLEX RECONSTRUCTION

SECTION 000050 - BOARDWALK

PART 1 - GENERAL

1.1 SUMMARY

A. This contract involves the construction of new wood boardwalk with railings. The project includes earthwork, grading, new helical pier foundations installed in water and on shore, concrete foundations, gluelam beams, wood framing and decking, and wood railings.

1.2 MEASUREMENT AND PAYMENT

A. Boardwalk Reconstruction: The quantity to be measured shall be "Lump Sum Quantity" (LSQ) as shown on the Schedule of Items for portions of completed work for the Stanley Lake Recreation Complex Reconstruction project. Provide all labor, materials and equipment, including helical piers, deck framing, wood decking and railings to complete each phase. The pay item for each phase includes all mobilization, construction staking, sediment erosion control, waste material disposal, earthwork, clearing and grubbing, concrete, seeding and all incidentals necessary to complete that phase of the work

1. Beach Access Boardwalk:

a. Construction of the boardwalk on the Lakeshore Trail from Sta. 4+79 to 7+12, including railing.

2. Connector Boardwalk:

a. Construction of the boardwalk on the Lakeshore Trail from Sta. 24+10 to 26+62.

1.3 REFERENCE SPECIFICATIONS

A. The publications listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only.

2012 International Building Code 2010 Americans with Disabilities Act/Architectural Barriers Act Guidelines (ADA/ABAG) (http://www.access-board.gov/adaag/html/adaag.htm)

1.4 RELATED WORK

A. The work shall be in accordance with the following subsidiary specifications. The subsidiary specifications are referred to in the text by the Section designation only.

Section 000050 – Boardwalk Reconstruction Section 010250 - Construction Staking Section 011250 – Measurement and Payment Section 011900 - Mobilization

BOARDWALK 000050-2

Section 013300 – Submittal Procedures Section 014100 – Quality Control Section 023701 – Sedimentation and Erosion Control Section 024100 – Waste Material Disposal Section 024102 – Removal and Disposal of Existing Structures Section 033000 – Cast-In-Place Concrete Section 033020 – Concrete from Package Dry Mix for Minor Structures Section 061000 – Rough Carpentry Section 061323 – Heavy Timber Construction Section 061533 – Wood Patio Decking Section 061800 – Glue Laminated Construction Section 311000 – Clearing and Grubbing:

Section 312000 – Earthwork Section 312600 – Steel Helical Piers Section 321204 – Crushed Aggregate Base or Surface Course

1.5 SPECIAL REQUIREMENTS

A. Treated wood products shall be inspected on arrival and any pieces found to have visible residues or bleeding of preservative will be rejected.

B. Cutting and fabrication of structural and other elements of the boardwalk shall occur outside of wetland areas to the extent possible. Where cutting and fabrication activities must occur in wetlands, construction debris will be captured, retained (e.g. tarps) and disposed of properly.

C. Wood preservatives utilized shall be appropriate for such use, and consistent with EPA, IDEQ (2008), and NOAA (2009) guidance, and selected as informed through such recommended sources as: Treated Wood in Aquatic Environments — A Specification and Environmental Guide to Selecting, Installing and Managing Wood Preservation Systems in Aquatic and Wetland Environments (“Specification Guide”) (Western Wood Preservers Institute, 2006a).

D. The contractor shall demonstrate treated products have been certified as compliant with Best Management Practices for Treated Wood in Western Aquatic Environments (“BMP Manual”) (Western Wood Preservers Institute, 2006).

PART 2 - PRODUCTS AND EXECUTION

END OF SECTION 000050

MAY 2014

CONSTRUCTION STAKING 010250-1

USDA FOREST SERVICE, R4

STANLEY LAKE RECREATION COMPLEX RECONSTRUCTION

SECTION 010250 - CONSTRUCTION STAKING

PART 1 - GENERAL

1.1 SUMMARY

A. This work shall consist of the construction staking of roads, parking lots, parking spurs, family units, tent pads, paths, stairways, culverts, retaining walls, buildings, and utilities in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

1.2 QUALITY CONTROL

A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.

1.3 MEASUREMENT AND PAYMENT

A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS

A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include:

1. Control Points - Northing, Easting, Existing Elevations.

2. Roads, Spurs, Parking Areas - Northing, Easting, and Finish Elevations for centerline and edge of roads, spurs, parking areas.

3. Pathways - Northing, Easting, and Finish Elevations for centerline.

4. Boardwalk Pathways – Northing and Easting for boardwalk centerline. Finish

Elevations will be provided on the profile. Boardwalk helical pier locations shall to be determined by the contractor according to the provided centerline and Structural Drawings.

5. Buildings and Other Structures - Northing, Easting, and Finish Elevations for corners of buildings, other structures (septic tanks, fencing, etc).

6. Camp Sites, Picnic Sites, and Tent Pads – Northing and Easting for corners of Camp Picnic Sites. Finished elevations shall be field staked by the contractor and approved by the Contracting Officer.

CONSTRUCTION STAKING 010250-2

7. Utility Lines – Northing and Easting for centerline of utilities (Electrical Lines).

2.2 STAKES

A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

1. Roads, parking lots, and parking spurs -Orange

2. Waterlines, utilities, and culverts -Blue

3. Family Units, group units, stairs, and paths -Red

4. Buildings, excavation and grading -Yellow

5. Tent pads -Blue/White Striped

2.3 SURVEY NOTE PAPER AND BOOKS

A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.

The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

B. Accuracy requirements:

1. Minimum position close; 1/1000

2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)

3. Cross section and slope stake precision:

C. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

D. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.

E. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%.

Clearing limits: 1.0 ft.

CONSTRUCTION STAKING 010250-3

3.2 ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS

A. Access Roads, Parking Spurs, and Parking lots:

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, typical road section templates, as shown on the drawings and the information provided with staking points.

2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.

B. Group Units, Family Units and tent Pads

1. Slope stakes shall be established at the corners of family units. Slope stakes shall be written to reference the finish grade of the unit or pad being staked.

C. Paths and Trails

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, and typical path and trail section templates as shown on the drawings.

2. Slope stakes shall be set at 10-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points.

D. Culverts

1. Slope stakes and slope reference stakes shall be set at all culvert locations. A culvert reference stake and hub shall be set on the centerline of the culvert 10 feet from each end or beyond the clearing limit, which ever is greater. The following shall be recorded on these stakes:

a. The actual field measured length

b. The vertical and horizontal distance from hubs to the invert at the ends of the culvert.

E. Sewerline, & other Utilities

1. Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Sewerline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.

F. Buildings

1. Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.

CONSTRUCTION STAKING 010250-4

3.3 DISCREPANCIES

A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

3.4 VERTICAL CONTROL

A. Vertical control for construction shall be as referenced on the Drawings.

3.5 MARKING STAKES

A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line) BM Bench mark TBM Temporary bench mark BT Begin taper (any) ET End taper (any) C Cut F Fill L Centerline D Ditch W Width

3.6 SURVEY NOTES

A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.

B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey

CONSTRUCTION STAKING 010250-5

was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.

END OF SECTION 010250

MEASUREMENT AND PAYMENT 011250-1

USDA FOREST SERVICE, R4

STANLEY LAKE RECREATION COMPLEX RECONSTRUCTION

SECTION 011250 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

7. For bituminous material, volumes will be measured at 60°F or will be corrected to the volume at 60°F by using ASTM D1250 for asphalts. Emulsified asphalt will be measured at 60°F, or measured by converting the gallonage at another temperature to gallonage at 60°F by means of the following formula:

MEASUREMENT AND PAYMENT 011250-2

Gallons at 60°F = Gallons at A°F 1+0.00025 (A°F - 60°F)

* A°F is the temperature of the material at the time the gallonage is measured.

a. For vehicular shipments, net certified scale weights or weights based on certified volumes will be used as a basis of measurement. Measurements will be adjusted when bituminous material has been lost from the vehicle or the distributor, has been wasted, or has otherwise not been incorporated into this work. Determining true weights of hauling vehicles shall be made by weighing the empty vehicles at least once a day at the times the CO directs.

Each vehicle shall bear a plainly legible identification mark.

b. When bituminous materials are shipped, net certified weights, or volume corrected for loss of foaming, can be used for computing quantities.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

MEASUREMENT AND PAYMENT 011250-3

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

1.5 PRICE ADJUSTMENT (for Out-of-Specification Bituminous Materials)

A. Bituminous materials are defined as all types and grades of asphalt cement, liquid asphalt, emulsified asphalt, and dust oil.

MEASUREMENT AND PAYMENT 011250-4

B. If bituminous material fails one or more test requirements, and the Contracting Officer determines it is in the public interest to accept the material at a reduced price, the price reduction shall be based on the test results giving the largest percent price adjustment.

The contractor may remove and replace the defective material or accept the adjustment.

C. The price reduction shall apply to all pay items affected.

D. Price adjustment will be based on samples taken in duplicate in accordance with AASHTO T40 under the supervision of the Contracting Officer. Samples shall be sent to an authorized laboratory. The laboratory shall test one of each duplicate sample and retain the other. When any test result is not within the specification limits, the laboratory shall immediately notify the Contractor, the supplier, and the Contracting Officer. The Contractor, after notifying the Contracting Officer, may check test the retained sample.

E. If the retained sample tests satisfactorily, the material will be accepted. If the retained sample also fails, the following schedule of price adjustments shall apply. The average of test values for the two samples will determine the basis for price adjustment, except when test results on the samples differ by more than the applicable AASHTO or ASTM Repeatability Unit; then, the test result numerically nearest the specification requirement will be used. (A repeatability unit is defined as D2S or D2S% limit for single operator precision described in ASTM C670.)

F. The schedule of price adjustments shall not apply to the following tests:

Test AASHTO Test Method Spot Test T102 Particle Charge T59 Ductility T51

G. Bituminous materials failing to meet specifications for these tests shall be removed and replaced.

H. See Table 011250-1 for the schedule of price adjustments for bituminous materials that do not meet specifications.

MEASUREMENT AND PAYMENT 011250-5

Table 011250-1

Schedule of Price Adjustments for Out-of-Specification Bituminous Materials.

Application

Deviation from Specification Limit Measured in Re-producibility Units*.

Less than 1 1 but less than 2

2 but less than 3

3 or more

Price reduction applicable to bituminous base course and pavement mixture or to seal coat and bituminous material paid for as a separate item.

0% 5% 25% Remove & Replace

Price reduction applicable to bituminous ma-terial paid for as a separate item.

0% 10% 25% Remove & Replace

* A reproducibility unit is defined as D2S or D2S% limit for multi-laboratory precision described in ASTM recommended practice C670.

The Sieve Test (AASHTO T59) results may be exempt from the Schedule of Price Adjustments provided the contractor's quality assurance program includes checking the uniformity of bitumi-nous spread rates in increments no greater than 1 foot over the width of the spray bar and varia-tion between increments is no greater than 5 percent.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

MOBILIZATION 011900-1

USDA FOREST SERVICE, R4

STANLEY LAKE RECREATION COMPLEX RECONSTRUCTION

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

SUBMITTAL PROCEDURES 013300-1

USDA FOREST SERVICE, R4

STANLEY LAKE RECREATION COMPLEX RECONSTRUCTION

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

SUBMITTAL PROCEDURES 013300-2

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

SUBMITTAL PROCEDURES 013300-3

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

SUBMITTAL PROCEDURES 013300-4

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in…